Dredging Delivery
Bristol's field notices outlast the original dredging contract window
IMWO artist's impression accompanying this evidence brief, depicting Baltic Wharf
Find a Tender fixes Bullo Limited's original GBP 392,500 contract through 26 June. Bristol Harbour Authority later scheduled Baltic Wharf dredging in late July and again from 10 to 17 August, with a floating pipeline and Bullo call sign. The public chain shows a live delivery question, not a proven extension or completion.
The harbour notice chain now extends beyond the signed period
Find a Tender identifies Bullo's legal supplier role, price, original period and performance metrics. Bristol Harbour Authority publishes the later work windows, floating-pipeline interface, navigation measures and Bullo call sign. The later notices are not contract amendments and do not establish mobilisation on 10 August, completed dredging, accepted quantity or handover. Bullo's company pages supply general capability context only.
A call sign links the field interface to the named prime
The current notice links a named award supplier to a precise operating interface: western Baltic Wharf, a dredger, floating pipeline, marker pole, slipway disruption, VHF channel 73 and restricted navigation near Underfall Yard. It also exposes a date mismatch that procurement monitoring should not smooth over. The later work may reflect a variation, overrun, call-off or follow-on instruction, but none is public.
Evidence conclusion
The missing document is contractual, then physical
Bristol's below-threshold contract gives Bullo an original 30 March-26 June term and six performance metrics. Notice 35/26 scheduled western Baltic Wharf work for 27-31 July; notice 36/26 schedules another weather-dependent window for 10-17 August and uses call sign Bullo. Because notice 36/26 was current at the start of 10 August, it is treated as a schedule rather than proof that the move has occurred. Contract modification, actual work dates, accepted depth and quantity, sediment route, plant assignment, lower tiers, final account and handover remain open.
Outstanding evidence
- Contract variation, extension, call-off or follow-on instruction after 26 June
- Harbour notice confirming the August work started, finished or changed
- Pre- and post-dredge survey and accepted depth
- Measured and accepted silt quantity by harbour reach
- Dredging method, pipeline destination and licensed sediment route
- Project-specific dredger, tug, barge, survey and environmental plant
- Named lower-tier contractors and scope allocation
- Six supplier-performance outcomes, final payment and owner handover
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- Harbour Maintenance Dredging procurement process ocds-h6vhtk-067353 Find a Tender, Notice published 24 March 2026; process reviewed 10 August 2026
- 027070-2026 Harbour Maintenance Dredging contract details notice Find a Tender, 24 March 2026
- Local notices to mariners, including 35/26 and 36/26 Bristol City Council / Bristol Harbour Authority, Current notices reviewed 10 August 2026
- Bristol Harbour Bristol City Council, Current authority page reviewed 10 August 2026
- Bullo Marine Contractors Bullo Limited, Current company page reviewed 10 August 2026
- Bullo fleet Bullo Limited, Current fleet page reviewed 10 August 2026