Location
United States / Americas
Project record
The U.S. Army Corps of Engineers and Sabine-Neches Navigation District are deepening and extending the Texas Gulf Coast waterway through federal and non-federal dredging packages. An April 2026 USD 239 million Callan Marine contract covers about 20 million cubic yards, two anchorage basins, and 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont by April 2028. That package is a major delivery step, not completion of the full 48-foot inland and 50-foot offshore programme.
United States / Americas
Dredging and waterways
Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate / Confirmed
15 July 2026
Coverage
Dredging and waterways is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe USD 239 million contract covers about 20 million cubic yards, two anchorage basins, and 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont by 15 April 2028. Its early-June dredging date was a schedule, not evidence of mobilisation or production.
SourceThe memorandum allowed SNND to execute the Callan package while remaining eligible to receive federal funds for at least 60 percent of the contract cost. It changed the delivery and funding path but did not itself prove an appropriation, payment, or physical dredging start.
SourceSNND reported that Contract 2B completed about 12.2 million cubic yards in December 2024 and Contract 3 finished about 7 million cubic yards in September 2025. The publication date anchors this record because the underlying completion dates were stated only by month.
SourceThe USD 219.108 million firm-fixed-price award established the federal offshore delivery contract after two bids, with a government estimated completion date of 24 March 2027. Later inland Contracts 7, 8 and 9 were neither awarded nor completed by this action.
SourceThe pre-bid conference notice moved the offshore eight-foot deepening and ocean-disposal package into an active federal procurement process. It was a solicitation milestone, not a contract award or construction start.
SourceEvidence gap