The U.S. Army Corps of Engineers and Sabine-Neches Navigation District are deepening and extending the Texas Gulf Coast waterway through federal and non-federal dredging packages. An April 2026 USD 239 million Callan Marine contract covers about 20 million cubic yards, two anchorage basins, and 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont by April 2028. That package is a major delivery step, not completion of the full 48-foot inland and 50-foot offshore programme.
Project signal
Construction in United States
Track usable-draft acceptance by reach and contract. The Callan award does not complete the 48-foot channel, and the Great Lakes offshore package does not establish awards or acceptance for inland Contracts 7, 8, and 9.
Current statusCallan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separateSource confidenceConfirmed
Location
United States / Americas
Segment
Dredging and waterways
Status
Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate / Confirmed
Evidence reviewed
15 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
U.S. Army Corps of Engineers, Galveston District, and Sabine-Neches Navigation District
Delivery parties
Callan Marine, Great Lakes Dredge & Dock
Contract route
The programme combines federal USACE contracts with packages procured by the local non-federal sponsor. The U.S. Department of Defense recorded a USD 219.108 million firm-fixed-price award to Great Lakes Dredge & Dock for Contract 6 in September 2024; the contractor later described base work and options of about USD 235 million. In April 2026, SNND signed a separate USD 239 million contract with Callan Marine after a public bid process. SNND says an April 2026 memorandum with USACE allows the district to execute that work while remaining eligible to receive federal funds for at least 60 percent of the contract cost.
Execution window
Programme construction began in 2019. SNND's November 2025 package record says first-cut Contracts 2A, 2B, and 3 were complete, with Contract 3 finishing in September 2025. The Great Lakes offshore Contract 6 has a government estimated completion date of 24 March 2027. The Callan package was scheduled to start dredging in early June 2026 and must finish by 15 April 2028. Full-depth Contracts 7, 8, and 9 remain separate and their timing depends on Contract 6 completion.
Works package
The authorized programme deepens the inland channel from 40 to 48 feet and offshore reaches from 42 to 50 feet, extends the offshore channel by 13.2 miles, widens selected reaches, eases bends, and adds turning and anchorage capacity. The 2026 Callan package removes about 20 million cubic yards, constructs two additional anchorage basins, and delivers 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont. USACE's Contract 6 covers about 41 offshore miles, including the extension, and approximately 35.8 million cubic yards of hopper dredging. Later inland packages are still required for the second four-foot cut to the authorized 48-foot depth.
Marine interfaces
Delivery crosses an operating energy, petrochemical, LNG, liquid-bulk, and military waterway with more than 50 regulated facilities. Hopper and pipeline dredging, active ship traffic, anchorage availability, dredged-material placement, berth-side private deepening, hydrographic survey, federal/non-federal funding, and reach-by-reach navigation authorization must remain coordinated. A dredged quantity or contractor completion notice alone does not establish usable draft across the full system.
Commercial read
USACE, Great Lakes and SNND documents establish two large current awards on different scopes and commercial bases. The Great Lakes federal base award is USD 219.108 million, while later USACE and contractor notices describe total value including options at roughly USD 235 million; the Callan non-federal contract is USD 239 million. Those figures should not be combined into a single final-project value or interpreted as covering unawarded Contracts 7, 8 and 9. SNND's schedule-acceleration claim remains an owner forecast until the later packages and acceptance evidence close.
Next milestone
Track dated Callan mobilisation and production, the two anchorage basins, placement-area performance, reach-by-reach pre- and post-dredge surveys, 44-foot usable-draft acceptance by April 2028, Great Lakes Contract 6 completion and offshore acceptance, procurement of Contracts 7 through 9, and final publication of authorized 48-foot inland and 50-foot offshore navigation availability.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
SNND awarded the 44-foot inland package to Callan Marine
The USD 239 million contract covers about 20 million cubic yards, two anchorage basins, and 44 feet of usable draft from Taylor Bayou to Port Arthur and Beaumont by 15 April 2028. Its early-June dredging date was a schedule, not evidence of mobilisation or production.
SNND and USACE established a federal funding route for sponsor delivery
The memorandum allowed SNND to execute the Callan package while remaining eligible to receive federal funds for at least 60 percent of the contract cost. It changed the delivery and funding path but did not itself prove an appropriation, payment, or physical dredging start.
Owner schedule documented completion of two first-cut reaches
SNND reported that Contract 2B completed about 12.2 million cubic yards in December 2024 and Contract 3 finished about 7 million cubic yards in September 2025. The publication date anchors this record because the underlying completion dates were stated only by month.
USACE awarded offshore Contract 6 to Great Lakes Dredge & Dock
The USD 219.108 million firm-fixed-price award established the federal offshore delivery contract after two bids, with a government estimated completion date of 24 March 2027. Later inland Contracts 7, 8 and 9 were neither awarded nor completed by this action.
The pre-bid conference notice moved the offshore eight-foot deepening and ocean-disposal package into an active federal procurement process. It was a solicitation milestone, not a contract award or construction start.
Track dated Callan mobilisation and production, the two anchorage basins, placement-area performance, reach-by-reach pre- and post-dredge surveys, 44-foot usable-draft acceptance by April 2028, Great Lakes Contract 6 completion and offshore acceptance, procurement of Contracts 7 through 9, and final publication of authorized 48-foot inland and 50-foot offshore navigation availability.
Decision watchpoints
Callan Marine mobilisation and verified production start
Two new anchorage basins and their operating acceptance
Dredged-material placement capacity and environmental controls
Great Lakes Contract 6 completion and offshore hydrographic acceptance
Reach-by-reach evidence of 44-foot usable draft
Contracts 7, 8, and 9 procurement, value, and delivery sequence
Final 48-foot inland and 50-foot offshore navigation authorization
Callan MarineOrganization profile / Dredging and marine construction contractor
Project availability status
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed15 July 2026Sources in this record6
Source record
The April 2026 SNND press release controls the Callan award, quantity, anchorage scope, 44-foot usable-draft boundary, work window, and funding memorandum. The SNND construction schedule explains the two four-foot phases and identifies Contracts 7, 8, and 9 as the later inland full-depth work. The USACE project page controls the overall 48/50-foot geometry, offshore extension, programme phase, and federal partnership. The Department of Defense award and USACE contractor briefing establish the Great Lakes base award and later total-with-options figure. The package-level evidence does not convert a 44-foot contract into full-project completion.
Phase: construction. Evidence reviewed: 15 July 2026.