USACE lists Rockbridge active at Lewes & Rehoboth Canal from 1 October. The southern dredging cut connects through hydraulic pumping to northern placement cells, with transport and receiving capacity affecting production.
Dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Philadelphia District
Delivery parties
Cottrell Contracting Corporation
Contract route
W912BU25CA009; the owner reports a $9.6 million award for southern-canal dredging and northern placement.
Execution window
DQM lists 1 October 2026 start and 28 February 2027 estimated end. The August owner announcement expected the October-March winter campaign.
Works package
Approximately89,000yd³ announced from Route 9 Bridge south to Rehoboth Bay, hydraulically pumped to northern placement areas using booster pumps.
Marine interfaces
The advancing dredge, booster and pipe arrangement connects the southern cut to receiving cells along a navigation waterway used by commercial and recreational craft.
Commercial evidence boundary
A pumping estimate needs the selected cut, pipe configuration and receiving-cell duty. The aggregate award includes work beyond excavation and supplies no standalone measured dredging unit rate.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
U.S. Army Corps of Engineers, Philadelphia District
Evidence status
Confirmed
Source position
Approximately89,000yd³ announced from Route 9 Bridge south to Rehoboth Bay, hydraulically pumped to northern placement areas using booster pumps. Source
Programme
Documented delivery conditions
Named party
Cottrell Contracting Corporation
Evidence status
Confirmed
Source position
DQM lists 1 October 2026 start and 28 February 2027 estimated end. The August owner announcement expected the October-March winter campaign. Source
Evidence gap
What remains unverified
Outstanding evidence
Pipe configuration and booster duty as the cut advances
Receiving-cell capacity, water management and discharge records
Progress surveys and the remaining winter work programme