Normandy ports maintenance dredging framework 2026-2029

Participation
Not assessed
Project facts checked

Eight call-off lots were concluded on 12 November 2025 for a four-year maximum framework beginning in 2026; the award chain is confirmed, while the first 2026 call-off, vessel mobilisation, measured quantity and port acceptance remain unpublished

Project sources

Ports de Normandie coordinated a joint procurement with the Syndicat Mixte des Ports de la Seine-Maritime for maintenance dredging across Caen-Ouistreham, Cherbourg, Dieppe, Le Treport, Fecamp, Saint-Valery-en-Caux and Le Havre's fishing port. The result separates trailing-suction hopper dredging, grab or pontoon dredging, stationary suction and five marine-levelling packages among four award chains. Each authority places and executes its own call-off orders, so the framework award is not evidence that every quantity band has been ordered or dredged.

Aerial view of Dieppe's inner harbour and navigation channel, one of the seven ports covered by the 2026-2029 maintenance-dredging framework

Ports de Normandie / Biplan-Stephane Leroy; Dieppe operating-port context, not evidence of framework mobilisation

Location

France / Europe

Segment

Maintenance dredging and operating-port access

Phase

Award / Confirmed

Last checked

2 August 2026

Coverage

Related sectors

Maintenance dredging and operating-port access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Syndicat Mixte Ports de Normandie as procurement coordinator with Syndicat Mixte des Ports de la Seine-Maritime; each authority signs and executes its own call-off agreement for its requirements
Delivery parties
SARL Eco Systemes de Dragage / Van den Herik grouping - lots 1 and 2 for trailing-suction hopper dredging and grab or pontoon dredging with barge, Entreprise Marc SA - lot 3 for stationary-suction dredging at Le Treport and Saint-Valery-en-Caux, CCI Caen Normandie - lot 4 marine levelling at Caen-Ouistreham and Cherbourg and lot 8 marine levelling at Le Havre-Peche, Compagnie de Remorquage de Dieppe - lots 5, 6 and 7 for marine levelling at Dieppe, Le Treport and Fecamp, Hydrographic-survey, disposal, environmental-monitoring, towing, pipeline, barge and other downstream subcontractors remain undisclosed
Contract route
Joint open procurement for eight single-award works framework lots under CPV 45252124. Contracts 2025-076lot1 through 2025-076lot8 were concluded on 12 November 2025. The agreements run for one year and may renew tacitly three times, to a maximum of four years. Ports de Normandie synchronises orders, while each purchasing authority signs and administers its own call-offs.
Execution window
The procurement notice set a 1 January 2026 start and a one-year initial term with up to three annual renewals through 2029. The 27 January 2026 award notice confirms the contract chain but does not establish that any 2026 call-off has been placed, mobilised or accepted.
Works package
Lot 1 sets trailing-suction hopper bands of 265,000-730,000 m3 for Ports de Normandie and 35,000-100,000 m3 for the Seine-Maritime ports. Lot 2 sets grab or pontoon-with-barge maxima of 20,000 m3 and 30,000 m3 respectively. Lot 3 allows up to 35,000 m3 of stationary-suction dredging. Lot 4 provides 100-350 marine-leveller hours at Caen-Ouistreham and Cherbourg. Lots 5-8 set marine-levelling bands of 90,000-250,000 m3 at Dieppe, 7,000-20,000 m3 at Le Treport, 0-15,000 m3 at Fecamp and 0-5,000 m3 at Le Havre-Peche.
Marine interfaces
The framework must coordinate four dredging methods, seven ports, two public authorities and synchronised call-offs while preserving live navigation. Survey definitions, sediment classification, disposal or beneficial-use routes, plant assignment, production records and post-work bathymetry remain port- and order-specific acceptance evidence.
Commercial evidence boundary
TED records an aggregate EUR 6,876,196 value across the eight winning tenders. That published award value must not be presented as actual spend, final account or guaranteed workload. The official quantity table provides order bands, not completed production, and the four prime award chains do not reveal downstream subcontracting.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

TED published the eight-lot award result

The notice identifies eight contracts, four award chains and an aggregate EUR 6,876,196 winning-tender value. It confirms procurement outcome, not call-off execution, spend or physical completion.

Source

Ports de Normandie recorded the lot quantity bands

The official committee record maps the awardees to technique- and port-specific minimum and maximum bands and authorises contract signature. The bands are ordering limits rather than measured dredging production.

Source

All eight framework contracts were concluded

The result notice gives the same conclusion date for contracts 2025-076lot1 through 2025-076lot8, while leaving individual call-off dates and operating mobilisation open.

Source

The joint authorities opened the multi-port competition

The contract notice established a one-year framework renewable three times and separated the requirement into eight lots across the seven named ports.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • First 2026 call-off by port and lot
  • Named TSHD, grab dredger, stationary-suction plant and marine levellers
  • Ordered versus measured quantities within each published band
  • Hydrographic survey scope and accepted depth
  • Sediment testing, disposal or beneficial-use route
  • Downstream survey, barge, towing, pipeline and environmental parties
  • Renewal decisions for the 2027-2029 terms
  • Actual payments versus the EUR 6.876 million aggregate award value

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
2 August 2026
Cited sources
4