Project record

Cabedelo access-channel and turning-basin deepening

Participation
Awarded
Participation checked

DTA award and signed funding addendum; design expected November and works March 2027

Participation source

A signed BRL 6.7 million funding addendum lifts Cabedelo's dredging allocation to BRL 71.15 million. The awarded design-build package combines sediment and rock removal with a monthly measurement-to-invoice payment sequence.

Cabedelo diagram distinguishes BRL71.15m funding and federal/state shares from the BRL68.818m DTA award and planned 2027 works.

IMWO original engineering diagram; source: Brazil Ministry of Ports and Airports

Location

Brazil / Americas

Segment

Capital dredging and navigation-channel deepening

Phase

Award / Confirmed

Last checked

31 October 2026

Coverage

Related sectors

Capital dredging and navigation-channel deepening is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Companhia Docas da Paraiba
Procurement references
007/2026; 31.203.000055.2026; Termo de Compromisso 003/2026
Delivery parties
DTA Engenharia Ltda: September adjudicated contractor for integrated design and dredging.
Contract route
Procurement references: 007/2026; 31.203.000055.2026; Termo de Compromisso 003/2026. Integrated procurement combining design with result-based deepening and rock removal. The 17 September adjudication names DTA at BRL 68,817,995.57; the ministry records the separate 23 October funding addendum.
Execution window
Ministry expects design from November 2026, physical work March 2027 and completion July 2027. Actual dates require the executed programme and work records.
Works package
Basic and detailed design, access-channel and turning-basin deepening, sediment dredging and rock removal. Planned turning-circle diameter grows from 330m to 450m.
Marine interfaces
Starting bed, target surface and soil/rock distribution define excavation and plant selection. Sedimentation during the work can increase the material required to deliver the result.
Commercial evidence boundary
Funding allocation BRL 71.15 million combines federal BRL 44.45 million and state BRL 26.70 million. Tender payment follows monthly measurement, approval and invoice; financing-cost risk is allocated to the contractor in the published matrix.

Evidence gap

What remains unverified

Outstanding evidence

  • Design commencement and the confirmed March-July works programme
  • Rock investigation, target geometry and accepted measurement records
  • Executed contract payment terms and subsequent actual receipts

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
31 October 2026
Cited sources
4