Location
Brazil / Americas
Project record
Concession assumed on 31 July 2026; revised tariffs effective 4 October; 13.3-metre operating draft
Paranaguá Port Channel Company assumed the access-channel concession on 31 July 2026, according to Portos do Paraná and PPCC's formal tariff notice. Its first revised access tariffs took effect on 4 October. The operator publishes a 13.3-metre current operating draft, a 15.5-metre Phase 2 target and September survey listings alongside its long-term dredging, hydrography, navigation-aid and traffic-management duties.
Brazil / Americas
Dredging
Delivery / Confirmed
21 October 2026
Coverage
Dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe operator's 4 September notice sets 4 October for the first contractual INFRAMAR adjustment. Access-cost checks now use that schedule; the current portal retains a 13.3-metre operating draft and a separate 15.5-metre Phase 2 target.
SourcePortos do Paraná confirms the effective concession date and directs Table I payments to PPCC for ships berthed from that date. PPCC's formal September notice records the same assumption date, replacing the earlier expected 1 August transition.
SourcePPCC publishes a 13.3-metre current operating draft, 15.5-metre target, March 2026 bathymetry, and VTS under implementation. Its year-five VTS label differs from ANTAQ's first-two-year summary, so neither summary page should be promoted into an accepted contract milestone.
SourcePortos do Paraná says Table I will move to PPCC and gives 1 August 2026 as the expected concession start. This is a transition notice, not evidence that handover, tariff collection, or service acceptance has occurred.
SourcePortos do Paraná placed Van Oord's Vox Amalia on the 2026 campaign and targeted end-June completion. The campaign belongs to the pre-handover maintenance regime and does not name the concession fleet or prove completion.
SourceDEME confirms the signed contract and PPCC operating vehicle. Signature moved the project into mobilisation and transition, but it did not deliver the future 15.5-metre target or establish physical works acceptance.
SourceHomologation confirmed CCGD as the selected consortium and closed the auction stage while leaving contract signature, transfer, mobilisation, dredging, and service performance for later evidence.
SourceTwenty live bids produced a 12.63% tariff discount and R$276 million grant fee, with R$1.22 billion of first-five-year investment. The auction created a long-term delivery obligation rather than a completed deepening result.
SourceEvidence gap