Project record
Grand Port Maritime de Dunkerque concluded contract 25 7 001 with Baggerbedrijf de Boer B.V. on 13 January 2025 to remove an existing submerged pipeline and install a new submerged sand-discharge line in front of the Braek dike. The official award notice records EUR 1,720,365 excluding VAT, five electronic bids and a winning variant. The tender required the asset in service no later than 31 May 2025. Public owner and contractor records publish no removal, installation, testing, acceptance, final-value or downstream delivery milestone.
France / Europe
Coastal protection and dredged-sand reuse
Baggerbedrijf de Boer holds the EUR 1.720365 million replacement contract concluded on 13 January 2025; the planned 31 May 2025 in-service deadline has passed, while physical completion, acceptance and downstream packages remain unverified / Confirmed
5 August 2026
Coverage
Coastal protection and dredged-sand reuse is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogBOAMP published the EUR 1.720365 million result, five-bid statistic and winning-variant field. Publication does not prove physical progress.
SourceContract 25 7 001 created a signed removal-and-replacement obligation under procedure 24ANI004, while physical execution and owner acceptance remained separate milestones.
SourceThe corrected notice set seven months overall, preparation up to three months and service no later than 31 May 2025.
SourceThe predecessor award linked the same owner and contractor to a 1.5 km line supporting repeated beneficial use of maintenance-dredging sand.
SourceEvidence gap