Coastal Sand Infrastructure

Braek's replacement pipeline is contracted but not publicly handed over

Published 5 August 2026 Publisher IMWO Region Europe Confidence Confirmed
Dunkirk Port dredging context showing sand handling from the Swalinge at a quay

Dunkerque-Port; Dunkirk Port dredging and sand-management context, not identified as 2025 Braek pipeline progress

Grand Port Maritime de Dunkerque concluded a EUR 1,720,365 excluding-VAT contract with Baggerbedrijf de Boer B.V. to remove and replace the submerged sand-discharge line in front of the Braek dike. The tender required service by 31 May 2025, while public project records publish no physical completion or acceptance milestone. A 2018 predecessor award shows the same contractor installed a 1.5 km line intended to support annual nourishment of 0.5 million to 2 million m3.

Baggerbedrijf de Boer holds the replacement contract

BOAMP confirms the 2025 contract, value, contractor, five bids, winning variant and contract date. The corrected tender confirms the service deadline. The official BOAMP dataset controls the separate 2018 predecessor facts. Owner and regional sources explain beneficial reuse and coastal-protection context. Public project records publish no dated removal, installation, testing, acceptance or use milestone, and name no downstream project-specific supplier.

The 2018 award exposes the infrastructure lineage

This small contract controls a recurring coastal-protection interface: maintenance-dredging sand must move from vessel and pumping system through a submerged line to the Braek frontage. The 2025 result identifies the prime, value, five bids and a winning variant. It does not identify the replacement geometry, marine spread, downstream suppliers, installed condition or return to service.

Evidence conclusion

Physical installation and owner acceptance remain unpublished

The 2018 BOAMP record defines the predecessor asset: a 1.5 km original line, an annual nourishment requirement of 0.5 million to 2 million m3, a EUR 1,097,589 award to the same contractor and a five-million-m3 guarantee reference. Those facts explain the operating purpose but cannot be transferred to the replacement design. The current status should remain at contracted award until dated removal, installation, test and owner-acceptance evidence is public.

Outstanding evidence

  • Old-line removal and replacement-pipe delivery
  • Winning variant and current technical geometry
  • Named marine plant, diving, survey and fabrication parties
  • As-laid verification, integrity or flow testing and commissioning
  • Owner acceptance, first sand discharge and final account