Japan's 315 MW Oga-Katagami-Akita project is moving through certified foundation design, base-port preparation, submarine-cable planning, navigation coordination, and a Sea Challenger charter for installation of 21 V236-15MW turbines ahead of a June 2028 operating target.
Japan / Asia Pacific
Offshore energy
Design certification complete; base-port and offshore installation preparation active / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The certificate closes the published design and certification process under Japanese technical requirements, while fabrication release, installed foundations, offshore construction, commissioning, and commercial operation remain separate delivery gates.
Read controlling sourceThe meeting records formal discussion of project waters, related ports and fishing harbours, marine traffic and navigation safety. Final controls, work windows and permits were not approved by this record.
Read controlling sourceThe charter fixes the named 1,600-tonne-lift installation vessel and Japan Offshore Marine interface for 21 turbines, without proving mobilisation, component readiness, installation cadence, or offshore completion.
Read controlling sourceThe agreement grants project use of the designated base port and sets the public-authority access framework. Berth preparation, heavy-component handling readiness and offshore construction remain future evidence.
Read controlling sourceThe contract names the base-port works counterparty and moves the port interface into contracted preparation. Completed construction, accepted facilities and installation-base availability remain unreported.
Read controlling sourceDelivery watch
Track base-port readiness, foundation installation sequencing, submarine-cable mobilisation, Sea Challenger arrival, and navigation-safety controls ahead of turbine installation.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerOga Katagami Akita Offshore Green Energy's official project page defines a 315 MW fixed-bottom offshore wind scheme comprising 21 Vestas V236-15MW turbines off Oga, Katagami, and Akita, with commercial operation targeted for 30 June 2028. Its published schedule connects base-port use, foundation installation, submarine cable laying, turbine installation, commissioning, and onshore transmission works. The developer's 2 April 2025 update confirms Sawakigumi's base-port development contract, and its 16 May 2025 update confirms the Akita Port wharf lease with Akita Prefecture and the Tohoku Regional Development Bureau under the Port and Harbor Act. Penta-Ocean's 29 May 2026 release says the developer chartered the 1,600-tonne-lift Sea Challenger from Japan Offshore Marine, the DEME Offshore and Penta-Ocean joint venture, for turbine installation. The developer's 1 July 2026 update confirms completion of conformity assessment against Japanese technical standards and an earlier Ports and Harbours Act technical-compliance certificate, and identifies Kajima with Kobori Research Complex and COWI on monopile foundation design, Vestas and MHI Vestas Japan on turbine and tower design, and Arup Japan as owner's engineer support. The 30 June 2026 Navigation Safety Committee establishes a live stakeholder process covering the construction plan, surrounding waters, port and fishing-harbour use, marine traffic, and navigation safety; it does not establish approved navigation controls. JERA's February 2026 update adds that base-port development was under way ahead of major offshore equipment arrival.
Phase: construction. Evidence reviewed: 15 July 2026.