Queensland TMR awarded Australian Marine & Civil CN-23611 to widen Poona's ramp to two lanes, add a support lane and floating walkway, dredge the approach for near all-tide access, place dredged material as beach nourishment and widen the landward approach. The official contract resource records AUD 2,041,001 in the original row and AUD 2,448,002 in a row marked as a variation. TMR initially anticipated full completion by January 2026, but MSQ then recorded dredging from 9 to 27 February and closure from 16 February while the upgrade works were completed. No later owner completion, reopening, acceptance or final-account record was located by 6 August 2026.
Project signal
Construction in Australia
Current statusAustralian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026Source confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Public boat-launch infrastructure, capital dredging and fixed access
Status
Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026 / Confirmed
Last checked
6 August 2026
Coverage
Related sectors
Public boat-launch infrastructure, capital dredging and fixed access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Queensland Department of Transport and Main Roads / Maritime Safety Queensland; Fraser Coast Regional Council is the appointed facility manager
Delivery parties
Australian Marine & Civil Pty Ltd - confirmed main works contractor under CN-23611, Floating-walkway, dredging, survey, environmental, concrete and other lower-tier parties - not publicly identified
Contract route
TMR used open procurement for CN-23611 and awarded Australian Marine & Civil on 29 July 2025. The current disclosure contains an original AUD 2,041,001 row marked Variation: No and a later AUD 2,448,002 row marked Variation: Yes. The disclosed increase is AUD 407,001, or about 19.94% of the original value. The resource does not state the variation scope, certification status, paid value or final account.
Execution window
Australian Marine & Civil's announced site window started on 8 September 2025, and MSQ advised that the ramp would close until approximately 19 December. TMR's 27 August media alert expected the ramp to reopen before Christmas and the full package to finish by January 2026. MSQ later scheduled dredging and foreshore nourishment for 9-27 February 2026 and closed the ramp from 16 February while upgrade works continued. No later official reopening or completion record was located by 6 August 2026.
Works package
The announced scope widens the existing one-lane ramp to two lanes, adds a northern support lane and floating walkway to shelter users from predominant north-easterly waves, dredges the approaches for near all-tide access, places dredged material as beach nourishment north of the ramp and widens the landward approach beside the existing car park. MSQ's February notice places the dredging workfront seaward about 250 metres from the ramp foot. No cited source publishes the achieved dredged volume, design or accepted depth, as-built channel geometry, nourishment quantity or final walkway specification.
Marine interfaces
The package links ramp and walkway geometry, a shallow approach channel, temporary navigation controls, dredging plant, foreshore placement and continued access restrictions within Poona Creek and the Great Sandy Strait. Near all-tide access depends on accepted bathymetry and later shoaling performance, while the nourishment area needs its own placement and environmental acceptance evidence. A June 2026 starboard lateral beacon is a navigation update, not proof of CN-23611 completion.
Commercial evidence boundary
An earlier TMR tender report used an approximate AUD 1.6 million contract value and QTRIP carries an AUD 1.85 million state project budget. The official contract disclosure records AUD 2,041,001 originally and AUD 2,448,002 after a row marked as a variation, a disclosed increase of AUD 407,001 or about 19.94%. TMR also said Poona used a portion of a wider AUD 6 million Great Sandy Marine Park boating-infrastructure allocation. These figures have different boundaries and must not be aggregated or treated as final expenditure, overrun, saving or final account.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Main works contract
CN-23611 ramp, floating-walkway support, access dredging, nourishment and landside works
Named party
Australian Marine & Civil Pty Ltd
Status
Confirmed
Source position
TMR's official disclosure identifies Australian Marine & Civil, open procurement, the 29 July 2025 award date, AUD 2,041,001 original value and AUD 2,448,002 variation row. Source
TMR's 27 August 2025 media alert defines the planned facility and initial four-month delivery window, including the January 2026 completion target. Source
Dredging and nourishment field window
Approach dredging about 250 metres seaward and foreshore nourishment
Named party
Contractor not named in the notice; CN-23611 prime is Australian Marine & Civil
Status
Confirmed
Source position
MSQ Notice 059(T) scheduled dredging and nourishment from 9 to 27 February 2026 and said the ramp would close from 16 February while upgrade works were completed. It does not identify the dredging subcontractor, plant, quantity or accepted output. Source
Post-dredging navigation state
Starboard lateral beacon in Poona Creek
Named party
Maritime Safety Queensland
Status
Confirmed
Source position
MSQ Notice 345 of 2026 records establishment of a starboard lateral beacon on 18 June 2026. The notice is navigation evidence only and does not certify CN-23611 completion, channel acceptance or near all-tide performance. Source
Closeout and downstream chain
Reopening, completion, final account, accepted dredging and subcontract register
Named party
Not publicly identified
Status
Not evidenced
Source position
No cited public record provides owner-confirmed reopening, practical completion, final payment, variation scope, accepted dredged quantity or depth, nourishment acceptance, completion certificate or lower-tier package register.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
MSQ's notice moved physical delivery beyond the earlier January completion target and kept the completion milestone open pending an owner-issued reopening or acceptance record.
Australian Marine & Civil's announced site window started
MSQ's closure advice identified the prime and expected closure until approximately 19 December 2025, but did not guarantee completion by that date or identify lower tiers.
The official disclosure fixes the original AUD 2,041,001 contract row; a separate variation row reports AUD 2,448,002 without describing the changed scope or payment status.