The Harbour Master's 22 June 2026 report confirms Van Oord completed dredging at Batson, Lincombe and Kingsbridge, with pontoons reopened by April; published draft meeting minutes record subsequent receipt of the post-dredge survey
Salcombe Harbour Authority's report to the 22 June 2026 board meeting confirms Van Oord completed the quinquennial dredging at Batson, Lincombe and Kingsbridge. A consistent basin finish allowed rapid pontoon reinstatement and reopening by April. The report was awaiting the post-dredge survey; published draft minutes record its subsequent receipt. The signed contract value remains GBP 101,600 excluding VAT, or GBP 121,920 including VAT. Accepted hydrographic levels, final account and supplier payment remain unconfirmed.
Maintenance dredging and operating-port access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
South Hams District Council on behalf of Salcombe Harbour Authority
Procurement references
RQ/499; ocds-h6vhtk-05dac3; 021748-2026
Delivery parties
Van Oord UK Limited - confirmed 2026 contractor, Companies House 01805156, Van Oord / Van Oord UK Ltd - confirmed supplier on separate 2015 and 2021 Salcombe dredging awards; those earlier contracts are context only, Hydrographic survey, environmental monitoring, marine plant and any other downstream parties for the 2026 contract - not identified in the cited sources
Contract route
Procurement reference RQ/499 used a below-threshold open competition under the Procurement Act 2023 and OCID ocds-h6vhtk-05dac3. The tender weighted price at 60% and quality at 40% and sought one supplier. The contract-details notice names Van Oord UK Limited and dates signature to 11 March 2026.
Execution window
The November 2025 tender estimated 15 January to 12 March 2026; the signed-contract record gives an estimated 11 March to 11 May period. The 22 June Harbour Master report records later-than-planned deployment following bad weather and a mechanical fault, completed dredging and pontoon reopening by April. Exact work dates and the duration attributable to each delay cause are not stated.
Works package
Maintenance dredging at Batson Creek, Lincombe and Kingsbridge within the Salcombe-Kingsbridge estuary, reported complete by the Harbour Master. The tender expected water injection dredging; the cited owner text does not specify the actual method, achieved volume or accepted hydrographic levels. A separate 2021 contract specified at least 7,500 cubic metres at Batson and Lincombe; that quantity retains its historical scope.
Marine interfaces
The Harbour Authority describes a busy estuary extending from the sea to Kingsbridge and used by bathers, paddlers, dinghies, yachts, power boats, superyachts, ferries and a shell-fishing fleet. The 2026 package therefore sits within live navigation and a sensitive estuary. A 2015 tender imposed method and environmental-monitoring boundaries, but those historical terms should not be represented as the current contract's conditions unless the 2026 documents are published.
Commercial evidence boundary
The tender estimate was GBP 99,999 excluding VAT and GBP 120,000 including VAT; the signed value is GBP 101,600 excluding VAT and GBP 121,920 including VAT. The June draft minutes place recent dredging expenditure in the 2026/27 year-end report and anticipate delivery within the approved budget. Assessed amounts, variations, final account, supplier payment and lower-tier allocation remain unknown.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
2026 works contract
RQ/499 South Hams Dredging
Named party
Van Oord UK Limited
Evidence status
Confirmed
Source position
The official OCDS record reports a GBP 101,600 excluding-VAT contract, GBP 121,920 including VAT, signature on 11 March 2026 and estimated end on 11 May 2026. Source
Tendered scope
Batson Creek, Lincombe and Kingsbridge maintenance dredging
Named party
South Hams District Council for Salcombe Harbour Authority
Evidence status
Reported
Source position
The UK4 tender identified the three locations and said WID was expected. It did not confirm the method ultimately used or publish a current quantity. Source
Schedule baseline
Tender programme versus signed contract
Named party
South Hams District Council
Evidence status
Confirmed
Source position
The tender estimated 15 January to 12 March 2026; the signed record instead runs 11 March to 11 May 2026. The later end date is not a completion certificate. Source
Historical recurrence
2021 Batson and Lincombe WID contract
Named party
Van Oord
Evidence status
Confirmed
Source position
A separate Contracts Finder release records a GBP 43,250 Van Oord award and tender scope of at least 7,500 cubic metres at Batson and Lincombe by WID. It is not the 2026 quantity or completion evidence. Source
Historical method boundary
2015-2016 Salcombe Harbour estuary dredging
Named party
Van Oord UK Ltd
Evidence status
Confirmed
Source position
A separate GBP 60,000 award followed a tender allowing water agitation, WID or an environmentally no-more-damaging alternative and requiring avoidance of persistent dense fluid mud. Those terms are historical context only. Source
Physical delivery
Batson, Lincombe and Kingsbridge dredging and pontoon reinstatement
Named party
Salcombe Harbour Authority and Van Oord UK Limited
Evidence status
Confirmed
Source position
The 22 June Harbour Master report, section 3.5.2, records completed dredging after delayed deployment following bad weather and a mechanical fault. Basin consistency allowed quick pontoon reinstatement and reopening by April. Exact work dates, achieved quantity and accepted levels are not given. Source
Post-dredge survey and account
Survey receipt and 2026/27 expenditure reporting
Named party
Salcombe Harbour Authority / South Hams District Council
Evidence status
Reported
Source position
Published draft minutes for the 22 June meeting, SH.07/26, record that the survey had just been received and that recent dredging expenditure would enter the 2026/27 year-end report. The account was anticipated to remain within budget; survey acceptance, final amount and payment are not stated. Source
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Harbour Board records completed dredging and survey receipt
The Harbour Master report confirms completed works and pontoon reopening by April. The published draft meeting minutes subsequently record survey receipt and expected 2026/27 expenditure reporting; accepted levels, formal acceptance and supplier payment remain unconfirmed.
The signed contract records Van Oord UK Limited, GBP 101,600 excluding VAT and an estimated period through 11 May 2026. The later owner report supplies physical delivery evidence.
South Hams identified Batson Creek, Lincombe and Kingsbridge, but the notice described the method and programme as expectations rather than completed work.
Van Oord UK received an earlier three-area estuary contract
The GBP 60,000 award and its environmental method boundary provide historical precedent only and must not be carried forward as current contractual evidence.
Page 3 records subsequent survey receipt and anticipated 2026/27 expenditure reporting. Draft minutes; final account and supplier payment are not stated.