Project record

Malaga Port Quay 4 facing rehabilitation

Pre-tender close view of masonry voids and displaced blocks on the submerged quay face of Malaga Port Quay 4

Malaga Port Authority; exact-site condition photograph 4 from the issued 26exma-033 project, not construction-progress evidence

Malaga Port Authority is procuring a focused repair to the upper submerged face of Quay 4, where missing and degraded masonry blocks have left the quay core exposed to wave and vessel action. The issued project divides the work into seven repair areas with 42.5 metres of combined frontage, 81.25 square metres of face preparation and formwork, 994.5 kilograms of anchored reinforcement and 116.25 cubic metres of marine-grade structural concrete. The package also includes temporary removal and reinstatement of three SC-1600 fenders, a 42.5-metre turbidity curtain, R4 structural repair mortar at the emerged transition and photographic records for each repair stage.

Project signal

Tender in Spain

Current status Malaga Port Authority's rectified tender remains open until 2 September 2026 for a four-week repair of seven damaged areas on Quay 4; the EUR 78,739.06 excluding-VAT budget is a tender baseline and no contractor has been selected Source confidence Confirmed

Location

Spain / Europe

Segment

Submerged masonry quay repair and structural concrete rehabilitation

Status

Malaga Port Authority's rectified tender remains open until 2 September 2026 for a four-week repair of seven damaged areas on Quay 4; the EUR 78,739.06 excluding-VAT budget is a tender baseline and no contractor has been selected / Confirmed

Last checked

15 August 2026

Coverage

Related sectors

Submerged masonry quay repair and structural concrete rehabilitation is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Malaga Port Authority (Autoridad Portuaria de Malaga)
Delivery parties
Construction works contract - unawarded, Professional-diving, marine-plant, concrete, reinforcement, temporary-works and waste-management parties - to be appointed under the works contract
Contract route
File 26exma-033 uses Spain's open simplified summary procedure under article 159.6 of the Public Sector Contracts Law. The works form one lot, bids are submitted electronically in one envelope and price carries 100% of the award weighting. The current notice gives a 2 September 2026 23:59 submission deadline and a private opening scheduled for 3 September at 09:09.
Execution window
The contract allows 28 days, expressed in the project as four weeks, with a one-year warranty from works acceptance. That duration begins under the eventual contract programme; the tender dates do not establish site possession, mobilisation or a field start. Works must be sequenced around continued port operations and approved by the owner's engineer before commencement.
Works package
Clean and sound seven cavities in the upper three metres of the submerged quay face; drill into retained masonry and anchor horizontal and vertical reinforcement; install sealed, made-to-measure formwork; pump HA-35/F/20/XS3+SR concrete from the base of each void in a single controlled pour; strip the formwork and remove projections; reinstate three fenders; apply R4 structural repair mortar across the emerged transition; install a 42.5-metre turbidity curtain; and document every repair stage. Tender measurements total 81.25 m2 of cleaning, formwork and stripping, 994.5 kg of reinforcement and 116.25 m3 of concrete.
Marine interfaces
Execution combines professional diving, a support craft, crane and pumping operations against an active berth. Formwork must seal irregular masonry closely enough to prevent cement washout while allowing water to escape through a top feed opening. The temporary fender removals affect berth protection, and the turbidity curtain, controlled pour sequence, waste handling and photo records are direct controls on the water-quality and acceptance interfaces.
Commercial evidence boundary
The EUR 66,167.27 execution budget allocates EUR 4,667.81 to preliminary cleaning, EUR 17,804.70 to formwork and reinforcement, EUR 31,470.04 to concrete, EUR 2,582.13 to stripping and final cleaning, EUR 6,844.77 to auxiliary works, EUR 889.82 to waste and EUR 1,908.00 to safety. Adding 13% general overhead and 6% industrial profit produces the EUR 78,739.06 excluding-VAT tender budget, or EUR 95,274.26 including VAT. These are owner estimates, not an award price, paid amount or final account.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Tender and commercial baseline

26exma-033 Quay 4 facing rehabilitation

Named party
Malaga Port Authority
Status
Confirmed
Source position
PLACSP records the published one-lot tender, EUR 78,739.06 excluding-VAT budget, 2 September 2026 deadline and price-only evaluation. Source
Submerged structural repair

Seven cavity repairs on the upper Quay 4 face

Named party
Future works contractor and professional-diving team
Status
Confirmed
Source position
The issued project measures 81.25 m2 of repair face, 994.5 kg of anchored reinforcement and 116.25 m3 of marine-grade concrete across seven areas. Source
Berth and environmental interfaces

Fender handling, turbidity control, R4 mortar and waste

Named party
Future works contractor
Status
Confirmed
Source position
The project includes three temporary fender removals and reinstatements, 42.5 m of turbidity curtain and 42.5 m of structural transition mortar, plus waste certificates and stage photography. Source
Award and physical delivery

Contract execution, mobilisation and acceptance

Named party
Malaga Port Authority and future contractor
Status
Not evidenced
Source position
The current tender does not identify an awardee or confirm contract signature, site possession, mobilisation, installed quantities, acceptance or payment.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The authority uploaded a further correction to the administrative conditions

The procurement file now carries the latest correction alongside the rectified notice and specifications; the live portal record should control bid preparation.

Source

The Quay 4 repair tender and rectification were published

The issued documents fixed the seven-zone repair scope, current 28-day term and revised 2 September submission deadline for electronic bids.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Bid opening, award decision and executed contract
  • Named construction prime, diving team and support-craft provider
  • Pre-start cavity survey and approved repair geometry
  • HA-35 marine-concrete mix, reinforcement and anchorage approvals
  • Formwork sealing, pump sequence and concrete washout control
  • Berth access and temporary removal of three SC-1600 fenders
  • Turbidity monitoring, waste certificates and stage photographs
  • Certified quantities, acceptance, final account and warranty close-out

Reporting status

Tender, confirmed confidence

Last checked 15 August 2026 across 4 cited sources. The dated timeline above carries the project events.

Last checked 15 August 2026 Cited sources 4

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 4