Project record

Malaga Port Quay 4 facing rehabilitation

Participation
Submissions closed
Participation checked

Malaga Port Authority declared Quay 4 procedure 26exma-033 unsuccessful on 7 September 2026 after receiving no bids; the 15 September notice retains the seven-zone repair design and EUR 78,739.06 excluding-VAT tender budget, with no works award under this procedure

Participation source

Malaga Port Authority is procuring a focused repair to the upper submerged face of Quay 4, where missing and degraded masonry blocks have left the quay core exposed to wave and vessel action. The issued project divides the work into seven repair areas with 42.5 metres of combined frontage, 81.25 square metres of face preparation and formwork, 994.5 kilograms of anchored reinforcement and 116.25 cubic metres of marine-grade structural concrete. The package also includes temporary removal and reinstatement of three SC-1600 fenders, a 42.5-metre turbidity curtain, R4 structural repair mortar at the emerged transition and photographic records for each repair stage.

Pre-tender close view of masonry voids and displaced blocks on the submerged quay face of Malaga Port Quay 4

Malaga Port Authority; exact-site condition photograph 4 from the issued 26exma-033 project, not construction-progress evidence

Location

Spain / Europe

Segment

Submerged masonry quay repair and structural concrete rehabilitation

Phase

Tender / Confirmed

Last checked

15 October 2026

Coverage

Related sectors

Submerged masonry quay repair and structural concrete rehabilitation is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Malaga Port Authority (Autoridad Portuaria de Malaga)
Procurement references
26exma-033
Delivery parties
Construction works contract - procedure declared unsuccessful after zero bids, Professional-diving, marine-plant, concrete, reinforcement, temporary-works and waste-management parties - no appointment evidenced under 26exma-033
Contract route
File 26exma-033 used the open simplified summary procedure under article 159.6 of Spain's Public Sector Contracts Law, with one lot, electronic submission in one envelope and 100% price weighting. The published deadline was 2 September 2026 at 23:59 and the private opening was scheduled for 3 September at 09:09. The authority's decision dated 7 September, published on 15 September, declares the procedure Desierto because no bidders participated; the notice records zero offers and no awardee.
Execution window
The unsuccessful tender allowed 28 days, expressed in the project as four weeks, with a one-year warranty from works acceptance. No awarded programme, site possession or mobilisation is established by this procedure. The issued design requires work around continued port operations and the owner's engineer's approval before commencement; actual execution and warranty dates remain unconfirmed.
Works package
Clean and sound seven cavities in the upper three metres of the submerged quay face; drill into retained masonry and anchor horizontal and vertical reinforcement; install sealed, made-to-measure formwork; pump HA-35/F/20/XS3+SR concrete from the base of each void in a single controlled pour; strip the formwork and remove projections; reinstate three fenders; apply R4 structural repair mortar across the emerged transition; install a 42.5-metre turbidity curtain; and document every repair stage. Tender measurements total 81.25 m2 of cleaning, formwork and stripping, 994.5 kg of reinforcement and 116.25 m3 of concrete.
Marine interfaces
Execution combines professional diving, a support craft, crane and pumping operations against an active berth. Formwork must seal irregular masonry closely enough to prevent cement washout while allowing water to escape through a top feed opening. The temporary fender removals affect berth protection, and the turbidity curtain, controlled pour sequence, waste handling and photo records are direct controls on the water-quality and acceptance interfaces.
Commercial evidence boundary
The EUR 66,167.27 execution budget allocates EUR 4,667.81 to preliminary cleaning, EUR 17,804.70 to formwork and reinforcement, EUR 31,470.04 to concrete, EUR 2,582.13 to stripping and final cleaning, EUR 6,844.77 to auxiliary works, EUR 889.82 to waste and EUR 1,908.00 to safety. Adding 13% general overhead and 6% industrial profit produces the EUR 78,739.06 excluding-VAT tender budget, or EUR 95,274.26 including VAT. These are owner estimates, not an award price, paid amount or final account.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Tender and commercial baseline

26exma-033 Quay 4 facing rehabilitation

Named party
Malaga Port Authority
Evidence status
Confirmed
Source position
The original one-lot tender carried a EUR 78,739.06 excluding-VAT budget, 2 September 2026 deadline and price-only evaluation; the authority subsequently declared it unsuccessful after zero bids. Source
Submerged structural repair

Seven cavity repairs on the upper Quay 4 face

Named party
Future works contractor and professional-diving team
Evidence status
Confirmed
Source position
The issued project measures 81.25 m2 of repair face, 994.5 kg of anchored reinforcement and 116.25 m3 of marine-grade concrete across seven areas. Source
Berth and environmental interfaces

Fender handling, turbidity control, R4 mortar and waste

Named party
Future works contractor
Evidence status
Confirmed
Source position
The project includes three temporary fender removals and reinstatements, 42.5 m of turbidity curtain and 42.5 m of structural transition mortar, plus waste certificates and stage photography. Source
Unsuccessful procurement and delivery boundary

Contract execution, mobilisation and acceptance

Named party
Malaga Port Authority; no awardee under 26exma-033
Evidence status
Not evidenced
Source position
The 7 September decision, published on 15 September, records Desierto and zero offers. This procedure supplies no works award, site possession, mobilisation, installed quantities, acceptance or payment record. Source

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

PLACSP published the unsuccessful-procedure outcome

The Adjudicación notice reports Desierto, zero bids and no awardee. The publication date is distinct from the authority's 7 September decision and establishes no replacement procurement or physical works.

Source

The authority declared procedure 26exma-033 unsuccessful

No bidders participated. The decision closes this procurement without appointing a works contractor; the original seven-zone design and budget remain historical tender evidence.

Source

The authority uploaded a further correction to the administrative conditions

The procurement file now carries the latest correction alongside the rectified notice and specifications; the live portal record should control bid preparation.

Source

The Quay 4 repair tender and rectification were published

The issued documents fixed the seven-zone repair scope, current 28-day term and revised 2 September submission deadline for electronic bids.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Bid opening, award decision and executed contract
  • Named construction prime, diving team and support-craft provider
  • Pre-start cavity survey and approved repair geometry
  • HA-35 marine-concrete mix, reinforcement and anchorage approvals
  • Formwork sealing, pump sequence and concrete washout control
  • Berth access and temporary removal of three SC-1600 fenders
  • Turbidity monitoring, waste certificates and stage photographs
  • Certified quantities, acceptance, final account and warranty close-out

Reporting status

Project phase
Tender
Evidence confidence
Confirmed
Last checked
15 October 2026
Cited sources
6