Project record

La Pozona harbour upgrade

Official aerial view of La Pozona de Miengo showing the shallow small-craft harbour basin, existing berths, perimeter wall and adjacent estuary

Government of Cantabria technical project via MITECO; exact-location pre-construction context, not evidence of 2026 mobilisation or progress

Cantabria awarded a three-company UTE the EUR 2.647m La Pozona harbour upgrade, covering dredging, pontoons, piles, berths, landside works and utilities under a confirmed procurement result.

Project signal

Award in Spain

Current status Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished Source confidence Confirmed

Location

Spain / Europe

Segment

Dredging, pontoons, piles and utilities

Status

Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished / Confirmed

Last checked

9 August 2026

Coverage

Related sectors

Dredging, pontoons, piles and utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Consejeria de Fomento, Vivienda, Ordenacion del Territorio y Medio Ambiente, Government of Cantabria
Delivery parties
UTE SERANCO, S.A. - ESTRUCTURAS CONDAL, S.A. - CONSTRUCCIONES Y EXCAVACIONES ANIBAL, S.L. - awarded works contractor, SERANCO, S.A. - UTE member, ESTRUCTURAS CONDAL, S.A. - UTE member, CONSTRUCCIONES Y EXCAVACIONES ANIBAL, S.L. - UTE member, Dredging, marine transport, dewatering, disposal, pontoon, piling, utilities and specialist lower tiers - not identified in the cited public records
Contract route
PLACSP expediente 4.1.82/25 records three offers and award on 6 August 2026. The tender baseline is EUR 3,025,717.93 excluding VAT and EUR 3,661,118.70 including VAT; the award is EUR 2,647,200.62 excluding VAT, EUR 555,912.13 VAT and EUR 3,203,112.75 including VAT. The award resolution was signed and published on 7 August. It states that formalization cannot occur until 15 business days after award notification and then must follow within five calendar days of the contracting body's request, so the award is not evidence of a signed contract.
Execution window
The award resolution sets 24 months from the day after a viable setting-out and feasibility-check act, applies price-review formula 332 for dredging except rock and provides a 12-month guarantee after positive reception. No signed contract, setting-out act, execution-clock start, monthly certification, reception record or guarantee commencement is public as of 9 August 2026.
Works package
The November 2024 technical project restores the shallow harbour basin and reorganizes the small-craft facility. It specifies approximately 12,880 cubic metres of dredging to restore about +1.00 metre relative to Port of Suances zero in internal channels and pontoon areas; two main rows providing 86 berths, including 38 for 6.5-metre boats and 48 for 8-metre boats; approximately 223 linear metres of 2-metre-wide aluminium 6005 floating pontoons with fingers and gangways; 18 guide piles of 500-millimetre diameter with 252 metres total pile length; about 2,325 square metres of intertidal cleaning and regrading; a 305-square-metre pedestrian area; a 1,465-square-metre concrete boat-handling, launch and recovery area; a 1,322-metre aerial and underground electrical connection; and 22 water-and-electricity service pedestals on the pontoons.
Marine interfaces
The design links dredging, navigation, temporary small-craft access, pontoon and pile installation, tidal working, electrical and water connections, boat handling and environmental control. The dredged sediment assessment routes approximately 12,880 cubic metres as non-hazardous material after marine dredging, transport, temporary dewatering or drying and delivery to an authorized onshore facility. A self-propelled hopper or scow and truck route appear in the design methodology, but they are tender-stage assumptions rather than evidence of the awardee's selected plant or logistics chain.
Commercial evidence boundary
EUR 2,647,200.62 is the excluding-VAT award value, EUR 555,912.13 is VAT and EUR 3,203,112.75 is the including-VAT total; none is a signed final account or certified spend. The three named companies are members of the awarded UTE, not disclosed subcontractors. Subcontracting is permitted under the procurement terms, but no downstream package allocation or supplier is evidenced.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Owner

La Pozona de Miengo integral harbour-basin upgrade

Named party
Government of Cantabria infrastructure ministry
Status
Confirmed
Source position
The PLACSP record and award resolution identify the regional ministry as contracting authority. Source
Technical design

Harbour-basin, dredging, pontoon, landside and utility design

Named party
Estudio de Ingenieria Tres Mares, S.L.U.
Status
Confirmed
Source position
The official November 2024 technical project identifies the designer and project author and defines the integrated scope. Source
Works award

Expediente 4.1.82/25

Named party
UTE SERANCO - ESTRUCTURAS CONDAL - CONSTRUCCIONES Y EXCAVACIONES ANIBAL
Status
Confirmed
Source position
The award resolution records the three-member UTE, EUR 2,647,200.62 excluding VAT and award on 6 August 2026. Source
Dredging and sediment route

Approximately 12,880 m3 harbour-basin dredging, dewatering and authorized onshore disposal

Named party
Awarded UTE and undisclosed lower tiers
Status
Confirmed
Source position
The technical project defines the design volume, levels, sediment assessment and route; actual plant, subcontractor, quantities and disposal tickets remain unverified. Source
Floating harbour

Approximately 223 m of pontoons, fingers, gangways and 86 berths

Named party
Awarded UTE and undisclosed supplier or installer
Status
Confirmed
Source position
The technical project defines the berth mix and pontoon system, but no downstream manufacturer, installer or accepted quantity is published. Source
Piling

18 guide piles, 500 mm diameter and 252 m total length

Named party
Awarded UTE and undisclosed piling lower tier
Status
Confirmed
Source position
The design fixes the pile count and geometry; selected piling plant, installation contractor and as-built records remain undisclosed. Source
Utilities and landside works

Electrical connection, service pedestals, water, pedestrian and boat-handling areas

Named party
Awarded UTE and undisclosed specialist lower tiers
Status
Confirmed
Source position
The technical project defines the connection length, 22 service pedestals and landside areas; suppliers, installers and commissioning evidence remain unpublished. Source
Supply chain

Dredging, transport, disposal, pontoons, piles, utilities and marine support

Named party
Undisclosed lower tiers
Status
Undisclosed
Source position
The official records identify the three UTE members but do not name downstream contractors, suppliers, plant or package allocations.
Contract, mobilisation and acceptance

Formalization, setting-out, execution, reception and final account

Named party
Cantabria and the awarded UTE
Status
Not evidenced
Source position
The award resolution defines future formalization and delivery terms; no signed contract, setting-out act, production or acceptance record is public.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Three-company UTE awarded the harbour upgrade

Cantabria selected SERANCO, ESTRUCTURAS CONDAL and CONSTRUCCIONES Y EXCAVACIONES ANIBAL at EUR 2,647,200.62 excluding VAT, while contract formalization and mobilisation remain unconfirmed.

Source

Works procurement notice published

Publication opened competition against a EUR 3,025,717.93 excluding-VAT baseline and a 24-month delivery framework before any awardee had been selected.

Source

Public-domain concession consultation opened

MITECO published the concession and technical-project material, establishing the harbour footprint and design evidence layer rather than construction progress.

Source

Integral harbour-upgrade design baseline dated

The technical project fixed the dredging, floating-harbour, piling, landside and utility design quantities; those quantities remain planned until measured execution is published.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Contract formalization and viable setting-out act
  • Notice to proceed, work-zone establishment and first dredging mobilisation
  • Dredger, hopper or scow, piling and marine-support plant
  • Sediment dewatering, transport and authorized disposal chain
  • Pontoon, finger, pile and utility suppliers or installers
  • Harbour-operability and temporary small-craft access controls
  • Measured dredging, pile, pontoon and landside quantities
  • Monthly certifications, variations, reception and final value

Reporting status

Award, confirmed confidence

Last checked 9 August 2026 across 5 cited sources. The dated timeline above carries the project events.