Cantabria awarded the EUR 2.647m works to a three-member UTE; contract and mobilisation remain unpublished
Cantabria awarded a three-company UTE the EUR 2.647m La Pozona harbour upgrade, covering dredging, pontoons, piles, berths, landside works and utilities under a confirmed procurement result.
Spain / Europe
Dredging, pontoons, piles and utilities
Award / Confirmed
9 August 2026
Coverage
Dredging, pontoons, piles and utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCantabria selected SERANCO, ESTRUCTURAS CONDAL and CONSTRUCCIONES Y EXCAVACIONES ANIBAL at EUR 2,647,200.62 excluding VAT, while contract formalization and mobilisation remain unconfirmed.
SourcePublication opened competition against a EUR 3,025,717.93 excluding-VAT baseline and a 24-month delivery framework before any awardee had been selected.
SourceMITECO published the concession and technical-project material, establishing the harbour footprint and design evidence layer rather than construction progress.
SourceThe technical project fixed the dredging, floating-harbour, piling, landside and utility design quantities; those quantities remain planned until measured execution is published.
SourceEvidence gap