Dredging Award
Miengo EUR 2.65m award awaits contract
The award confirms a three-company UTE and marine scope, including 12,880 cubic metres of dredging, 223 metres of pontoons, 18 piles and 86 berths, while contract and mobilisation remain unverified.
A live award converts a design record into a procurement watch
The award resolution controls the three-member UTE, value, offer count, duration trigger, price review and guarantee. The technical project controls planned quantities and method assumptions but is not progress evidence. UTE members are not subcontractors. No signed contract, setting-out act, plant mobilisation, downstream appointment, executed quantity or acceptance record is public as of 9 August 2026.
The UTE award leaves contract and mobilisation unconfirmed
Marine awards are often flattened into a single contractor field. Here, three companies jointly form the awardee, so none should be relabelled as a subcontractor. The delivery chain still has unresolved appointments across dredging plant, sediment transport and disposal, pontoon supply, piling, utilities and marine support. Those gaps become actionable only when contract, setting-out and mobilisation evidence appears.
Evidence conclusion
The evidence stops before contract execution
The 7 August resolution establishes award value, party and future contract terms. It explicitly leaves a standstill before formalization and ties the 24-month clock to a viable setting-out act. The November 2024 design quantifies dredging, pontoons, piles, berths, utilities and sediment routing. That specificity supports supply-chain monitoring, but it cannot identify actual plant, suppliers or subcontractors. The record therefore remains at award stage, with contract, setting-out, mobilisation and lower-tier evidence tracked as separate gates.
Outstanding evidence
- Contract formalization and viable setting-out act
- First dredging and piling mobilisation
- Dredging plant, marine transport and disposal operators
- Pontoon, finger, pile and service-pedestal suppliers
- Harbour-operability and small-craft access controls
- Measured quantities, monthly certifications and variations
- Reception, guarantee commencement and final value
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Expediente 4.1.82/25 procurement record Plataforma de Contratacion del Sector Publico, Award 6 August 2026; award resolution published 7 August 2026
- La Pozona de Miengo works award resolution Government of Cantabria via PLACSP, Signed and published 7 August 2026
- La Pozona de Miengo integral upgrade technical project Government of Cantabria via MITECO, Project dated November 2024; reviewed 9 August 2026
- Miengo public-domain concession consultation Spanish Ministry for the Ecological Transition and Demographic Challenge, 20 January 2025
- BOE concession notice for the La Pozona port works Boletin Oficial del Estado, 20 January 2025