Harwich Haven Authority's March 2026 Find a Tender award notice names Suffolk Dredging LLP on a GBP 100 million excluding-VAT maintenance-dredging package. Scope covers clay and silt in Harwich Harbour, Port of Felixstowe deep and shallow berths and the western approach channel; sand at the eastern approach; Tiamat and other dredging methods; coastal beneficial-use sites; and early contractor involvement in capital and beneficial-use schemes. The notice records a planned 17 April 2026 start, but the award and contract remained pending in the published data and no later contract-details notice has been located.
United Kingdom / Europe
Maintenance dredging, beneficial use and dredging technology
GBP 100m award notice names Suffolk Dredging LLP for a five-year base term; a contract-details notice, reconciled extension limit and attribution of 2026 field activity remain unconfirmed / Confirmed
5 August 2026
Coverage
Maintenance dredging, beneficial use and dredging technology is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCompanies House filings establish the current corporate-control step after the scheduled contract date, but do not by themselves prove that the maintenance-dredging contract was signed or that field work transferred to the LLP.
SourceThe award notice scheduled signature and commencement for 17 April. No contract-details notice or equivalent owner confirmation has been located in the reviewed public process record.
SourceHHA published the affiliated-entity rationale, five-year base term, extension language and combined conventional, Tiamat, beneficial-use and early-contractor-involvement scope while retaining pending award and contract status.
SourceThe owner named Boskalis Westminster for sediment pumping and Amicus Civil Engineering for temporary bunds and coir rolls under the predecessor operating context. That project is relevant beneficial-use evidence but not proof of Suffolk Dredging performance.
SourceCompanies House records the LLP's formation at a Boskalis-linked Fareham address before HHA entered as a designated member in April 2026.
SourceEvidence gap