HME Construction is carrying out the FY26 maintenance dredging of Redwood City Channel for the U.S. Army Corps of Engineers. The Coast Guard's July notice names the DB Seahorse, two dump scows, an ocean-going tug and support tug Douglas, with material routed to the Alcatraz Island placement site and the SF-DODS ocean site. USACE's March plan used a 200,000-cubic-yard estimate; that planning figure is not presented as the final paid quantity.
Project signal
Construction in United States
Current statusHME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026Source confidenceConfirmed
Location
United States / Americas
Segment
Dredging and waterways
Status
HME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026 / Confirmed
Last checked
21 July 2026
Coverage
Related sectors
Dredging and waterways is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, San Francisco District
Delivery parties
HME Construction, Inc. - maintenance dredging contractor
Contract route
USACE ran W912P726BA002 as a total small-business set-aside invitation for bids and awarded firm-fixed-price contract W912P726CA017 to HME Construction on 24 June 2026. The SAM.gov award notice records USD 4,947,796.
Execution window
The Coast Guard notice lists 24/7 operations from 8 to 30 July 2026. A separate USACE boater notice says dredging was expected to begin on or after 15 July and continue until project completion, tentatively in early November. The Port's April update used a broader completion target before 30 November. These are separate notices and should remain separate until USACE issues a controlling update.
Works package
Annual maintenance dredging of Redwood City Channel to the authorized depth of 30 feet MLLW plus one foot of paid overdepth. USACE's 9 March programme estimated 200,000 cubic yards and specified clamshell dredging, with material sent to SF-11 and SF-DODS. The live marine notice identifies DB Seahorse, two dump scows and two tugs for the July work.
Marine interfaces
The work runs from the channel north of Bair Island into Redwood City Harbor and ultimately to the inner turning basin beside Wharf 5. It shares a live deep-draft commercial channel with cargo and recreational traffic, requires scow swaps and ocean-going tows, and uses VHF channels 67 or 69 while monitoring 13 and 14.
Commercial evidence boundary
This is active contractor workload, not a tender watch. The Coast Guard plant-and-route notice establishes current field activity. The Port's USD 7.35 million figure is the federal work-plan allocation; SAM.gov records the HME contract award at USD 4.948 million. They describe different commercial layers.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.