Project record

Dundee Beach boat-ramp maintenance

Official aerial site plan of Dundee Beach boat ramp, groyne, public access and adjoining parking area

Northern Territory Department of Infrastructure, Planning and Logistics; September 2024 Dundee Beach stakeholder notice. The marked layout concerns the earlier groyne works and is site context, not evidence of T25-1462 progress.

Northern Territory Tenders Online records Polaris Marine Constructions as the sole awardee for T25-1462 at AUD 676,047.56. The 12-month period contract covers the boat ramp, concrete decks, sea channel, fishing platform, jetty and surrounding areas, including removal of sand, mud, algae and debris. The live tender detail now agrees with the award dataset on the 12-month title and records 10 August 2026 as the award date. No cited public record provides a contract signing date, commencement, work order, mobilisation or completed quantity.

Project signal

Award in Australia

Current status Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis Source confidence Confirmed

Location

Australia / Asia Pacific

Segment

Public boat-launch infrastructure, maintenance dredging and fixed access

Status

Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis / Confirmed

Last checked

15 August 2026

Coverage

Related sectors

Public boat-launch infrastructure, maintenance dredging and fixed access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Northern Territory Department of Logistics and Infrastructure
Delivery parties
Polaris Marine Constructions Pty Ltd as The Trustee for Polaris Marine Constructions No. 1 - sole awardee named in the Northern Territory awarded-contract dataset, Dredging, excavation, survey, disposal, cleaning, diving and other lower-tier parties - not publicly identified
Contract route
The Northern Territory released public tender T25-1462 on 17 November 2025, closed it on 8 December 2025 and records award on 10 August 2026. The live tender detail and awarded-contract dataset identify Polaris Marine Constructions as the sole awardee at AUD 676,047.56 and describe the arrangement as a 12-month period contract using estimated unit rates. The cited public record does not provide a signing date or notice to proceed.
Execution window
The public tender title states 12 months, but no cited record publishes the executed start and end dates. Award on 10 August 2026 does not by itself establish contract signature, commencement, mobilisation or the issue of a first work order.
Works package
Maintain the Dundee Beach boat ramp and concrete decks, and keep the sea channel usable when the tide is 2.5 m LAT or above. Maintain the fishing platform, jetty structure and surrounding areas in a clean condition, free from algae, sand, mud and debris. Remove and dispose of sand deposits so sediment at the base of the ramp and in the departure channel does not exceed 1.5 m LAT. Public sources do not state estimated or accepted quantities, disposal routes, survey methods, work-order frequencies or final tolerances beyond that tender criterion.
Marine interfaces
The package links ramp usability to tidal access, sediment at the ramp toe and departure channel, and cleaning of fixed public marine assets. The current public boat-ramp page warns that sediment build-up can occur and describes access above 2.8 m, while the tender scope sets a 2.5 m LAT maintenance usability requirement. Those figures have different source contexts and are not reconciled into a claimed operating depth.
Commercial evidence boundary
AUD 676,047.56 is the sum of the single awardee amount in the Northern Territory dataset. Because payment is described as estimated unit rates, the figure is not presented as actual expenditure, a guaranteed ceiling, a final account or evidence of executed quantities. No signing date, work order, paid-to-date amount, variation, subcontract schedule or final payment record is published in the cited sources.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Contract award

T25-1462 Dundee Beach boat-ramp maintenance

Named party
Polaris Marine Constructions
Status
Confirmed
Source position
The official awarded-contract dataset names one awardee and records AUD 676,047.56 on an estimated-unit-rate period-contract basis. Source
Maintenance scope

Ramp, decks, departure channel, fishing platform and jetty

Named party
Northern Territory Department of Logistics and Infrastructure
Status
Confirmed
Source position
The tender detail requires asset cleaning and sediment removal, including a 1.5 m LAT maximum sediment level at the ramp base and departure channel. Source
Contract duration

T25-1462 period contract

Named party
Northern Territory procurement records
Status
Confirmed
Source position
The live tender detail and awarded-contract dataset both describe the package as a 12-month period contract. Executed start and end dates remain unpublished. Source
Earlier asset upgrade

Groyne, walkway, jetty and fishing-platform improvements

Named party
Northern Territory Department of Logistics and Infrastructure
Status
Confirmed
Source position
A June 2025 stakeholder notice says improvement works were complete and the facility reopened. The notice predates T25-1462 and is not evidence of delivery under the later maintenance award. Source
Delivery and closeout

Work orders, actual quantities, survey and acceptance

Named party
Not publicly evidenced
Status
Not evidenced
Source position
No cited public record provides a signing date, commencement, mobilisation, work order, plant list, actual quantity, disposal record, survey, acceptance or final account.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Official tender page records the 12-month award to Polaris

The live tender detail identifies Polaris, AUD 676,047.56, the estimated-unit-rate basis and the award date; its title now aligns with the award dataset on 12 months.

Source

Tender released with a 36-month title and measurable maintenance scope

The original tender established the ramp, channel, jetty and fishing-platform work boundary and the 1.5 m LAT sediment criterion. The live page now also records the award.

Source

Separate facility-improvement works completed

The owner announced completion of groyne, walkway, jetty and fishing-platform improvements before T25-1462 was released; those works remain a separate evidence chain.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Contract signature, executed start and end dates
  • Commencement and first maintenance work order
  • Pre-works and post-works bathymetry at the ramp toe and departure channel
  • Actual sediment-removal quantities and disposal destination
  • Ramp-access notices and achieved tidal usability
  • Fishing-platform, jetty, deck and surrounding-area maintenance records
  • Named survey, excavation, dredging, disposal and cleaning lower tiers
  • Variations, paid-to-date value, acceptance and final account

Reporting status

Award, confirmed confidence

Last checked 15 August 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 15 August 2026 Cited sources 6