The Port Authority of New York and New Jersey is evaluating three bids for a work-order contract covering maintenance dredging, dredged-material amendment, transport and disposal at Port Newark, Elizabeth, Port Jersey and Howland Hook marine terminals.
Project signal
Evaluation in United States
Read the preliminary bid table as a procurement checkpoint. Donjon Marine's USD 51.424 million estimated total leads Jay Cashman's USD 54.4312 million and Posillico Civil's USD 68.498 million, but the Port Authority has not published an award, notice to proceed, work-order value, dredging quantity or placement facility.
Current statusThree preliminary bids opened for MFP-364.003; evaluation and award remain pendingSource confidenceConfirmed
Location
United States / Americas
Segment
Dredging
Status
Three preliminary bids opened for MFP-364.003; evaluation and award remain pending / Confirmed
Evidence reviewed
19 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Port Authority of New York and New Jersey
Delivery parties
Donjon Marine Co., LLC - preliminary low bidder, Jay Cashman, Inc. - preliminary second bidder, Posillico Civil, Inc. - preliminary third bidder
Contract route
Competitive Contract MFP-364.003 closed on 30 June 2026 after an advertised USD 50 million to USD 60 million estimate. The Port Authority's preliminary table records three estimated totals. Its bidder response directs award timing to the contract clause allowing acceptance or rejection within 60 days after bid opening; no award is identified.
Execution window
The engineer will issue work orders for terminal-specific tasks. The reviewed advertisement and public clarifications do not establish the first work order, notice to proceed, contract start, plant mobilisation or physical completion date. Each work order therefore needs its own location, quantity, sediment, placement, survey and acceptance record.
Works package
Maintenance dredging, amendment of dredged material, transport, disposal and related work at Port Newark, Elizabeth-Port Authority Marine Terminal, Port Jersey-Port Authority Marine Terminal and their New Jersey vicinities, plus Howland Hook Marine Terminal and its New York vicinity. The engineer controls the location and timing through individual work orders.
Marine interfaces
Bidders requested sediment chemistry, sediment test records, permit information and more time to evaluate disposal options. The Port Authority replied that the contractor must identify and choose the upland placement facility and follow the receiving state's acceptance criteria and regulations. That makes sediment suitability, facility capacity, cross-state transport and permit compliance part of delivery rather than a fixed owner-supplied route.
Commercial read
Donjon's preliminary total is USD 3.0072 million below Jay Cashman and USD 17.074 million below Posillico. The top two bids sit inside the advertised USD 50 million to USD 60 million range; Posillico is above it. These figures rank bids against the estimate but do not show evaluated responsiveness, award value, executed work orders or final paid quantity.
Next milestone
Track evaluated bid status, any formal award, the executed contract value, performance security, first work order, named dredging and material-processing plant, terminal and berth location, sediment classification, selected upland facility, state acceptance, measured quantity, post-dredge hydrography and work-order close-out.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Three bids set the preliminary commercial range
Donjon Marine submitted USD 51.424 million, Jay Cashman USD 54.4312 million and Posillico Civil USD 68.498 million. The table is preliminary and does not identify an award.
The final clarification left upland placement with the contractor
The contractor must select the upland facility and follow the receiving state's criteria. Sediment qualification, transport and facility acceptance remain live delivery interfaces.
The Port Authority advertised a four-terminal work-order contract
MFP-364.003 packages maintenance dredging, material amendment, transport and disposal across three New Jersey terminal systems and Howland Hook in New York at an advertised USD 50 million to USD 60 million range.
Track evaluated bid status, any formal award, the executed contract value, performance security, first work order, named dredging and material-processing plant, terminal and berth location, sediment classification, selected upland facility, state acceptance, measured quantity, post-dredge hydrography and work-order close-out.
Decision watchpoints
Formal evaluated bid result and contract award
Award value, performance security and executed contract term
First work order, terminal location and notice to proceed
Named dredger, support plant and material-amendment method
Sediment classification and receiving-state acceptance criteria
Selected upland placement facility and transport route
Pre- and post-dredge surveys, measured quantity and berth release
Work-order completion, final payment and any change orders
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed19 July 2026Sources in this record5
Source record
The official advertisement defines the four-terminal work-order scope and USD 50 million to USD 60 million estimate. The official preliminary bid table supplies the three contractor totals. Addendum No. 1 identifies the sediment reports made available to bidders, while the final question log places upland-facility selection and state acceptance with the contractor and points to a 60-day bid-acceptance clause. The published package stops before award or physical work.
Phase: evaluation. Evidence reviewed: 19 July 2026.