- Client / authority
- Oman Ministry of Agriculture, Fisheries and Water Resources, formerly Ministry of Agriculture and Fisheries
- Delivery parties
- Galfar Engineering and Contracting SAOG - reported prime construction award of approximately OMR 9.86 million, SeaWorks Co. - company-listed 2015 dredging and reclamation works for the Ministry, five-month duration; relationship to Galfar not published, Masirah Marine - company-listed 2017 quay-wall block installation for Galfar, Concrete Layer Innovations - CORE-LOC project reference for the two breakwaters; exact supply, licence or technical-services boundary not published, Al Fajar Al Alamia - company portfolio lists Fishery Harbour at Nabur, Liwa; exact package and contract tier not published
- Contract route
- A government fishing-port works contract was awarded to Galfar in December 2013 and announced with detailed Ministry scope in May 2014. The tender number, bid tabulation, signed form of agreement, bond, variation history and final account have not been disclosed. Company portfolios identify downstream marine work packages without publishing a complete subcontract chain.
- Execution window
- Galfar's award was reported on 23 December 2013, the Ministry agreement and detailed scope on 20 May 2014, and the marine-works launch on 20 March 2015 with an 18-20 month target. SeaWorks dates its five-month dredging-and-reclamation work to 2015. Masirah Marine dates quay-wall block installation for Galfar to 2017. The harbour was described as operating and serving fishermen and boats by August 2023; taking-over, defects-period and final-account dates remain unpublished.
- Works package
- Construct two rubble-mound breakwaters, a fixed berth, floating berths, basin and approach-channel dredging, a boat ramp, navigation aids and harbour support facilities. The 2014 owner report gives 1,524 m total breakwater length, a 100 m fixed berth, 3.5 m basin depth and 5 m channel depth. Concrete Layer Innovations separately records 865 m and 658 m CORE-LOC breakwaters, totalling 1,523 m, with 1.0, 1.3 and 1.5 m3 units; the one-metre difference is preserved as a source discrepancy rather than reconciled by inference.
- Marine interfaces
- The construction chain joined breakwater armour and CORE-LOC placement, dredging and reclamation, quay-wall block installation, fixed and floating berths, navigation aids and shoreside utilities. The public sources do not identify the quarry and armour-rock chain, dredger and survey spread, precast-block supplier, floating-pontoon supplier, navigation-aid supplier, testing authority or accepted hydrographic datum.
- Commercial evidence boundary
- The earliest award record reports OMR 9.86 million, while the 2015 marine-works launch article uses a rounded OMR 9 million project figure. Neither source publishes the signed schedule of prices, downstream package values, variations, claims, certified final cost or defects close-out. The later OMR 45 million figure associated with five fisheries investment opportunities is an aggregate pipeline value and must not be allocated to Liwa.