Federal navigation crews replaced all four main-chamber miter gates at Lock and Dam 9 near Lynxville, Wisconsin, in July 2026. G&G Steel of Russellville, Alabama, fabricated the gates over about two years; they then moved by barge to the site. St. Paul District's maintenance and repair crew installed them with Rock Island District personnel and the 500-ton heavy-lift crane The Quad Cities. The four-day installation completed a four-to-five-year USACE design and delivery effort, but the public sources do not disclose G&G Steel's fabrication-contract value, fabrication subtiers, transport contracting, accepted installation cost or final account.
Project signal
Completed in United States
Current statusUSACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublishedSource confidenceConfirmed
Location
United States / Americas
Segment
Inland navigation lock rehabilitation and hydraulic steel structures
Status
USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished / Confirmed
Last checked
11 August 2026
Coverage
Related sectors
Inland navigation lock rehabilitation and hydraulic steel structures is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, St. Paul District, with Rock Island District delivery support
Delivery parties
G&G Steel, Inc. - confirmed fabricator of the Lock and Dam 9 miter gates in Russellville, Alabama, USACE St. Paul District maintenance and repair crew - field installation team named by USACE, USACE Rock Island District maintenance and repair personnel - joint installation support and operator of the 500-ton heavy-lift crane The Quad Cities, Fabrication subtiers, coating suppliers, barge transport contractor and other private lower tiers - not identified in the cited public records
Contract route
USACE's project page identifies G&G Steel as fabricator but does not publish the fabrication solicitation, award identifier, contract value, competition record, delivery terms or modification history. The same page separately allocates fiscal-year 2026 funding of USD 1.5 million for the Lock and Dam 9 anchorage upgrade and USD 1.25 million for miter-gate installation. The completion story states that USACE professionals supervised construction and contracting and that USACE crews performed installation; neither source establishes a private installation award.
Execution window
The gates took approximately two years to fabricate in Alabama and were transported by barge to Wisconsin. USACE scheduled 12-hour lock closures on 14, 16, 21 and 23 July 2026 to replace all four gates, then reported the four-day installation complete on 11 August. The broader design-to-install effort lasted four to five years. Public sources do not disclose the fabrication notice to proceed, gate delivery date, post-installation acceptance date, defects period or final commercial close-out.
Works package
The completed package replaced two upstream and two downstream miter-gate leaves in the main lock chamber and upgraded the anchorages and pin plates supporting the heavier gates. USACE states that the new gates retain the original length, width and height but are about 50% heavier, were designed to modern codes using current ice and current knowledge, and carry a nominal 50-year design life. Published records do not provide dimensions, steel tonnage, coating system, bearing details, seal manufacturer, hydraulic or electrical modifications, testing criteria or as-built drawings.
Marine interfaces
Delivery combined inland-waterway heavy fabrication, barge transport, controlled commercial-navigation closures, removal and lifting of four large steel leaves, anchorage work and recommissioning inside an operating nine-foot navigation system. Rock Island District's 500-ton floating crane The Quad Cities was the named heavy-lift asset. The closures protected both commercial and recreational traffic, but no cited record identifies towage, rigging, diving, survey, temporary works or gate-component suppliers.
Commercial evidence boundary
USD 1.5 million for the anchorage upgrade and USD 1.25 million for gate installation are USACE fiscal-year 2026 funding lines. They do not disclose G&G Steel's fabrication award, actual obligations, internal force-account cost, transport price, accepted quantities, variations or final account. No cited public source assigns a private installation contractor or names fabrication subcontracts; reporting G&G Steel as installer would therefore be incorrect.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Gate fabrication
Four main-chamber miter-gate leaves
Named party
G&G Steel, Inc.
Status
Confirmed
Source position
USACE names G&G Steel of Russellville, Alabama, as fabricator; the completion story says fabrication took approximately two years before barge transport to Wisconsin. Source
Anchorage preparation
Anchorage and pin-plate upgrades for heavier gates
Named party
USACE St. Paul and Rock Island District maintenance and repair teams
Status
Confirmed
Source position
USACE's programme page explains the anchorage and pin-plate work and assigns USD 1.5 million in fiscal-year 2026 funding; the cited records do not identify a private contractor. Source
Heavy-lift installation
Removal and replacement of four main-chamber miter gates
Named party
USACE St. Paul and Rock Island District maintenance and repair crews
Status
Confirmed
Source position
USACE reports a completed four-day installation using Rock Island District's 500-ton heavy-lift crane The Quad Cities. Source
Commercial close-out
Fabrication award, actual installation cost, variations and final account
Named party
USACE and G&G Steel
Status
Not evidenced
Source position
The official sources publish fiscal-year funding and role allocation but no fabrication-contract value, accepted force-account cost, subcontract ledger or final account.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The project moves from scheduled summer work to reported physical completion, with the two-district USACE installation team and heavy-lift asset now public.
The last planned closure completed the published four-date installation sequence; the 11 August USACE story later confirmed physical completion of all four replacements.
USACE publishes fabricator and fiscal-year funding baseline
G&G Steel is fixed as gate fabricator while USD 1.5 million anchorage and USD 1.25 million installation lines remain separate public funding baselines.