Inland navigation delivery chain

Lock and Dam 9 separates G&G fabrication from USACE installation

Published 11 August 2026 Updated 16 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Old and new miter gates at the Lock and Dam 9 replacement workfront during the July 2026 installation

USACE St. Paul District photo by Melanie Peterson via DVIDS; photographed 21 July 2026; public domain

USACE's 11 August completion account resolves the most important delivery-chain question at Lock and Dam 9. G&G Steel fabricated the four replacement miter-gate leaves in Alabama over about two years, but it did not perform the reported field installation. St. Paul and Rock Island District maintenance and repair crews completed that work over four July closure days with Rock Island's 500-ton heavy-lift crane The Quad Cities.

The summer schedule becomes reported physical completion

The DVIDS story is an official USACE St. Paul District completion account reporting the four-day installation, USACE crew, heavy-lift crane, fabrication duration, transport mode and 50% weight increase. The USACE project page identifies G&G Steel's fabrication role, anchorage scope and funding lines. The closure notice dates the July installation sequence.

Fabrication and installation sit on different evidence lines

Hydraulic-steel projects are easy to misread when one named supplier appears before installation. Confirmed roles cover a specialist fabricator, internal USACE engineering and contracting supervision, two-district force-account installation, barge transport and a named floating heavy-lift asset. The fabrication award value, transport contractor, rigging or diving lower tiers, accepted installation cost and final account remain undisclosed.

Evidence conclusion

Close the commercial and component-supply ledger next

USACE's dated completion story establishes physical completion of all four gate replacements. The USD 1.5 million for anchorage work and USD 1.25 million for installation are fiscal-year 2026 funding lines only. Neither amount is attributed to G&G Steel, whose evidenced role is fabrication rather than field installation, while private lower-tier participation remains unresolved. Commercial close-out still requires the fabrication contract, gate-component and coating suppliers, barge-transport responsibility, test and acceptance package and actual cost reconciliation.

Outstanding evidence

  • G&G Steel fabrication award, value and modification history
  • Gate steel, seals, coatings, machining and component suppliers
  • Barge transport, towage, rigging, diving and survey lower tiers
  • Installation testing and owner acceptance records
  • Actual cost against the two fiscal-year 2026 funding lines
  • First operating-season availability and maintenance
  • Winter inspection after ice loading
  • Defects close-out and final account