Fa. Gebr. Van der Lee signed the EUR 8.199 million contract on 31 March 2026; the contract is live through 2027, while no public evidence of physical mobilisation, vessel assignment or accepted production was identified by the 7 August 2026 review
Rijkswaterstaat awarded Fa. Gebr. Van der Lee contract 31205036 for three Walcheren beach-nourishment packages. The Walcheren design set calls for 550,000 m3 in situ at Westkapelse Zeedijk, 750,000 m3 between Westkapelle and Zoutelande, and 440,000 m3 at Breezand, a combined 1.74 million m3 across about 7.05 km of beach. TenderNed identifies no contract-specific vessel, site mobilisation, placed quantity or acceptance milestone.
Beach and foreshore nourishment is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Rijkswaterstaat Programma's, Projecten en Onderhoud
Delivery parties
Fa. Gebr. Van der Lee - signed engineering and execution contractor, Assigned TSHD, survey team, sand source and beach pipeline spread - not identified in the reviewed official record, Lower-tier suppliers and subcontractors - no subcontracting was declared in the award notice; subsequent appointments remain unverified
Contract route
The Walcheren package went through an open European Engineering and Construct procedure under UAV 2012. Seven bids were received, including one from an SME. TenderNed records Fa. Gebr. Van der Lee as winner at EUR 8,199,000 excluding VAT and a contract signature date of 31 March 2026.
Execution window
TenderNed schedules execution from 9 April 2026 to 15 December 2027. The programme factsheet and final design allocate three Walcheren work packages. A project-specific mobilisation sequence and physical start remain absent from the official notices.
Works package
WP1 Westkapelse Zeedijk beach: 550,000 m3 in situ over about 1.5 km. WP2 Westkapelle-Zoutelande beach: 750,000 m3 over about 4.7 km. WP3 Breezand beach: 440,000 m3 over about 0.85 km. The contractor must develop execution design, mobilise marine and shore spreads, place and grade sand, survey the works and comply with environmental and safety requirements.
Marine interfaces
The three sites require offshore borrow and TSHD logistics, floating and shore pipeline configuration or alternative approved placement, beach grading, hydrographic and topographic measurement, public-access controls and coordination with exposed Walcheren coastal conditions. Separate site geometry and windows make mobilisation sequencing commercially important.
Commercial evidence boundary
EUR 8.199 million is the signed contract value. The 1.74 million m3 combined design volume provides a scope denominator, but not a valid unit-rate calculation because the public price includes engineering, mobilisation, surveys, environmental controls, pipeline operations and package-specific risk. No package prices, variations, certified quantities, payments or final account are public.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
Legal award
31205036
Named party
Fa. Gebr. Van der Lee
Evidence status
Confirmed
Source position
TenderNed records a EUR 8.199 million contract signed on 31 March 2026 after seven bids. Source
Designed nourishment scope
WP1-WP3
Named party
Rijkswaterstaat and Fa. Gebr. Van der Lee
Evidence status
Confirmed
Source position
Final design documents indicate 1.74 million m3 in situ at three Walcheren beach locations. Source
Contractor capability
Dredging and coastal protection
Named party
Fa. Gebr. Van der Lee
Evidence status
Confirmed
Source position
The contractor's official page states that it operates its own trailing-suction hopper dredger fleet and delivers dredging, land reclamation, coastal defence and port development. Source
Physical delivery
Mobilisation, placement, survey and acceptance
Named party
Not publicly evidenced
Evidence status
Not evidenced
Source position
No reviewed official source identifies a contract-specific vessel, first placement, measured quantity or acceptance.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The public award release disclosed the EUR 8.199 million value, seven-bid competition and contract period while leaving the execution spread and physical start open.