Three Kustlijnzorg contracts move from award to a mixed execution pipeline

Published 7 August 2026 Publisher IMWO Region Europe Confidence Confirmed
High-aerial visualization of three separated Netherlands coastal nourishment operations using a trailing suction hopper dredger portfolio

IMWO artist's impression accompanying this evidence brief, depicting Kustlijnzorg

Rijkswaterstaat's three signed Kustlijnzorg contracts total EUR 50.599 million and final design documents indicate 14.705 million m3 in situ across 13 nourishment work packages at nine coastal locations. Boskalis has an owner-announced Den Helder execution window; Van der Lee and Van den Herik hold the other signed contracts, while most vessels, lower tiers and accepted production remain undisclosed.

Three signed awards now expose a 14.705m m3 delivery map

The three TenderNed award notices establish the signed contractors, legal values, signature dates, bid counts and delivery periods. Final bestek documents establish the 14.705 million m3 arithmetic design total. Rijkswaterstaat's current pages establish the Den Helder and Maasvlakte 2 execution schedule, but not certified progress. The aggregate value and volume are direct arithmetic across official records rather than an owner-published programme budget or completed total.

The contract family opens multiple vessel, survey, pipeline and sand-supply interfaces

The three awards are one of the clearest near-term European coastal-nourishment portfolios available in public procurement data. Their final design packages separate beach, foreshore and tidal-channel placement across North Holland, Texel, Walcheren, Scheveningen, Katwijk and Maasvlakte 2. That creates a sustained demand map for hopper-dredger capacity, hydrographic and topographic surveys, pipeline spreads, beach earthmoving, sand-source logistics, environmental controls and marine-object removal rather than a single undifferentiated dredging contract.

Evidence conclusion

Den Helder has the sole public current-work notice

TenderNed records three signed contract values: EUR 26.098 million for Boskalis, EUR 8.199 million for Fa. Gebr. Van der Lee and EUR 16.302 million for Van den Herik, an arithmetic aggregate of EUR 50.599 million. Final design documents indicate 9.055, 1.74 and 3.91 million m3 in situ respectively, an arithmetic aggregate of 14.705 million m3; these are design quantities, not completed volumes. Rijkswaterstaat separately announces 5.5 million m3 at Den Helder from mid-July and 1.425 million m3 at Maasvlakte 2 in September. Its Maasvlakte schedule names Van den Herik and Van der Kamp, but the signed award names only Van den Herik and does not disclose a subcontract or joint venture. This distinction is commercially material and should remain open until direct contract-chain evidence appears.

Outstanding evidence

  • Boskalis Den Helder vessel identity, production and mid-October completion
  • Julianadorp sinker-pipe recovery and disposal
  • North Holland beach and Texel Midden package mobilisation
  • Van der Lee first Walcheren site, TSHD and pipeline spread
  • Westkapelse Zeedijk, Westkapelle-Zoutelande and Breezand sequence
  • Van der Herik and Van der Kamp commercial relationship at Maasvlakte 2
  • Maasvlakte 2 September vessel and beach-versus-foreshore sequence
  • Scheveningen and Katwijk package start dates
  • Borrow areas, sand specifications and environmental conditions
  • Hydrographic and topographic survey providers
  • Package variations, certified in situ quantities and owner acceptance
  • Lower-tier pipeline, earthmoving, marine services and support-vessel appointments