Location
Jersey / Europe
Project record
VolkerStevin; exact-project planning CGI, not evidence of construction progress
Ports of Jersey selected VolkerFitzpatrick through a two-stage design-and-build procurement for the marine works in the Elizabeth Harbour redevelopment. The official award record carries GBP 40 million and a 14 May 2025 to 31 December 2027 contract period. Owner and contractor releases identify the Portside alliance of VolkerFitzpatrick, VolkerStevin and Geomarine, with Arup and Boskalis named as specialist supply-chain partners. The planned works combine a suspended deck and reclamation, a new lift-on/lift-off berth, berth-pocket and basin dredging, demolition or incorporation of the eastern RoRo pier, and a concrete-block return wall and revetment. Current public evidence reaches final design and planning-condition discharge, not Stage Two construction authorization or marine mobilisation.
Jersey / Europe
Ferry-terminal marine works, dredging and demolition
Final design and planning-condition discharge are evidenced; construction was scheduled for autumn 2026, while Stage Two authorization, dredger or piling mobilisation and physical works start remain unpublished / Confirmed
4 August 2026
Coverage
Ferry-terminal marine works, dredging and demolition is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe owner identified VolkerFitzpatrick, VolkerStevin and Geomarine as the Portside alliance and named Arup and Boskalis as specialist partners while describing detailed design as the current workstage.
SourceContracts Finder recorded VolkerFitzpatrick as supplier at GBP 40 million, but the two-stage route keeps later construction authorization and final pricing as separate gates.
SourceThe Planning Committee approved the redevelopment and documented the LoLo berth, reclamation, dredging, offshore-disposal and piling assumptions that define the permitted workfront.
SourceEvidence gap