Project record

Gulf three-port hopper maintenance procurement for 2027

Participation
Not assessed
Project facts checked

Consolidated unrestricted procurement planned; formal solicitation expected around 23 October 2026, no award announced

Project sources

The Enterprise Dredge Delivery Center intends to combine Calcasieu River Bar Channel, Pascagoula Harbor and Panama City entrance-channel maintenance in one procurement. The two October notices define consolidation and preliminary plant, placement and time-window requirements, rather than a completed award.

USACE Gulf hopper workfront matrix identifying Calcasieu, Pascagoula and Panama City plant capability depths and placement requirements

IMWO original USACE Gulf hopper workfront matrix from W912PM27BA002; equipment capabilities, not surveyed channel depths, ship drafts or accepted works

Location

United States / Americas

Segment

Dredging

Phase

Planning / Confirmed

Last checked

8 October 2026

Coverage

Related sectors

Dredging is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
USACE Enterprise Dredge Delivery Center
Delivery parties
Works contractor is not identified in the cited presolicitation
Contract route
W912PM27BA002: notice of intent to consolidate followed by an unrestricted firm-fixed-price presolicitation. A formal electronic solicitation is anticipated around 23 October 2026, with bid opening to be stated when issued.
Execution window
Planned 2027 periods: Calcasieu 15 January to an unspecified end date; Pascagoula 1 April-30 September; Panama City 1 August-30 September. These are preliminary work windows, not observed vessel dates or acceptance dates.
Works package
Three maintenance-dredging workfronts using hopper plant. Calcasieu requires self-propelled trailing-suction capability to -45ft MLLW; Pascagoula hopper capability to -46ft MLLW; Panama City medium-to-small hopper capability to -40ft MLLW. Final quantities are not supplied in the notices.
Marine interfaces
Calcasieu and Pascagoula material goes to ocean disposal sites. Pascagoula typically involves a three-to-five-mile transport leg; Panama City places material in the channel adjacent to the entrance jetty with an approximately one-mile leg. Dredging capabilities are not accepted navigable depths or vessel draft permissions. Mobile's March 2026 notice instead planned a cutterhead-pipeline campaign and channel-adjacent disposal at Pascagoula, illustrating why previous port activity cannot substitute for this hopper package's ocean-placement requirements.
Commercial evidence boundary
The combined procurement creates one intended acquisition across three different plant and disposal requirements. Contract value, offered rates, final quantities and an appointed contractor are undisclosed. Overlapping summer periods do not alone specify concurrent vessel operations.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Acquisition structure

W912PM27BA002

Named party
USACE EDDC
Evidence status
Confirmed
Source position
The special notice states an intent to consolidate the three maintenance contracts in an unrestricted competition. Source
Workfront requirements

Calcasieu / Pascagoula / Panama City

Named party
USACE EDDC
Evidence status
Confirmed
Source position
The presolicitation provides preliminary 2027 windows, hopper capability depths and material-placement routes; final quantities are not stated. Source

Evidence gap

What remains unverified

Outstanding evidence

  • Issued W912PM27BA002 solicitation and actual bid-opening date
  • Port-specific quantities, sediment and disposal conditions
  • Final work windows and fleet allocation requirements
  • Awarded contractor, notice to proceed and mobilisation

Reporting status

Project phase
Planning
Evidence confidence
Confirmed
Last checked
8 October 2026