Project record
IFB W912DS26BA027 closed after the extended 6 August 2026 deadline; SAM lists the opportunity as inactive and publishes the bid abstract
New York District's IFB W912DS26BA027 covers 237,945 cubic yards in six base dredging areas across the Main Channel 50-foot reach and Port Newark Channel 40-foot reach. Another 196,485 cubic yards sits in five optional dredging items, with a separate 300-short-ton debris option. The extended bid deadline was 6 August 2026 at 14:00 EDT; SAM now lists the opportunity as inactive.
Ken Lund / Wikimedia Commons, CC BY-SA 2.0; Newark Bay location context, not FY26 dredging progress
United States / Americas
Dredging and waterways
Tender / Confirmed
15 October 2026
Coverage
Dredging and waterways is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogUSACE moved bid submission from 31 July to 6 August at 14:00 EDT. The current SAM record lists the opportunity as inactive and includes the bid abstract posted on 7 August; the linked award panel was empty when checked on 15 October.
SourceThe IFB fixed the six-area, 237,945-CY base dredging scope, separately funded options, 31 July bid close and 108-day basic period without identifying an award or contractor.
SourceThe notice described about 830,000 CY across several channels and annual cycles, environmental-bucket dredging and upland placement. It sets the broader programme context but not the FY26 IFB base quantity.
SourceEvidence gap