Project record

Yukonhaven Jetty 4 LNG bunker-loading berth

LNG carrier at Gate terminal's existing Rotterdam loading facilities, showing the live-terminal and marine berth context for Yukonhaven Jetty 4

Port of Rotterdam Authority; existing Gate terminal and LNG-berth context, not evidence of Jetty 4 construction progress

Port of Rotterdam is developing a 160-metre LNG berth opposite Gate terminal's Jetty 3 in Yukonhaven. TenderNed records a 6 February 2026 contract with the combination of Hakkers Waterbouw and Aannemingsbedrijf De Klerk after Gate took FID in January. The marine package covers the jetty, a roughly 200-metre combi-wall, mooring dolphins and walkways, a roughly 145-metre fender and mooring structure, dredging and shore works. Rijkswaterstaat notifications naming De Klerk and a harbour-light restriction from 6 April support early construction, while accepted quantities, contractor workshares, plant, lower tiers and contract price remain unpublished.

Project signal

Construction in Netherlands

Current status Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028 Source confidence Confirmed

Location

Netherlands / Europe

Segment

LNG jetty, combi-wall, mooring structures, dredging and shore works

Status

Gate took FID in January 2026, Port of Rotterdam signed the Hakkers Waterbouw-De Klerk combination on 6 February, and April works notices support early construction; start-up is planned around the end of 2028 / Confirmed

Last checked

6 August 2026

Coverage

Related sectors

LNG jetty, combi-wall, mooring structures, dredging and shore works is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Port of Rotterdam Authority - marine-infrastructure buyer and developer; Gate Terminal B.V. - terminal operator, FID party and topside and shore-power interface
Delivery parties
combinatie Hakkers Waterbouw en Aannemingsbedrijf De Klerk - TenderNed award supplier, Hakkers Waterbouw - named combination member; project-specific workshare and deployed plant not published, B.V. Aannemingsbedrijf De Klerk - named combination member and applicant in two project-specific Rijkswaterstaat notifications, Gate Terminal B.V. - operator-side jetty systems, small-scale LNG service and shore-power interface; not the marine-works prime, Dredging plant, steel and pile suppliers, survey, environmental, electrical, mechanical and other lower tiers - not disclosed in the cited records
Contract route
Port of Rotterdam used a European negotiated procedure with prior competition under internal reference i.001385 and a UAV-GC design-and-construct form. The December 2024 notice allowed up to four parties into the award stage and said only engineering would be instructed initially; execution would follow after conditions including permits and FID by Gate and the Port. Gate announced FID on 13 January 2026. TenderNed's award announcement published 11 February records the Hakkers-De Klerk combination as supplier and a contract signature on 6 February. The electronic value field is EUR 0 and is treated as undisclosed, not as the commercial value.
Execution window
The original notice stated a two-year duration. Gate now plans start-up around the end of 2028, while Port of Rotterdam says the 160-metre berth is expected in the second half of 2028. Rijkswaterstaat notices published 20 and 23 March name De Klerk in project-specific soil or dredged-material application and construction-discharge activities. Harbour Master notice 050/2026 removed the Yukonhaven red harbour light from 6 April to 31 August because of construction in and around the basin. These sources support mobilisation and early works, not completion of the full marine scope.
Works package
The award-stage description covers a roughly 160-metre jetty for seagoing and inland vessels at about NAP -10 m nautical depth, with future deepening capability to about NAP -13 m; a roughly 200-metre north-side combi-wall connecting to Jetty 3; mooring dolphins and walkways; a roughly 145-metre fender and mooring structure; and dredging, coastal and shore works to enlarge Yukonhaven. The procurement also contemplated an unspecified part of future Jetty 5 while excluding Jetty 6. Gate separately places shore power within the operator-side project interface.
Marine interfaces
Delivery takes place in an operating LNG and petroleum-harbour regime beside Gate's existing loading facilities. The berth must connect marine civil structures, future deepening, dredging and shore works with Gate's process, transfer, safety and shore-power systems. Existing Jetty 3 service continues to define the operating context, but no cited record publishes construction windows around LNG calls, temporary navigation geometry, accepted dredge prism, piling sequence or systems-integration responsibility matrix.
Commercial evidence boundary
No public contract value is disclosed. TenderNed's EUR 0 value is a missing or non-published amount, not a price. The 2024 tender described approximately 450,000 m3 of dredging and associated shore work; the 2026 award release describes approximately 350,000 m3. That 100,000 m3 difference may reflect design development, boundary movement or measurement changes, but no approved quantity schedule or variation record is public. Gate's shore-power programme is a separate operator-side package and should not be folded into the marine works price.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Marine D&C contract

TenderNed i.001385 / award announcement 411585

Named party
combinatie Hakkers Waterbouw en Aannemingsbedrijf De Klerk
Status
Confirmed
Source position
TenderNed records the combination as supplier and the contract signed on 6 February 2026. Source
Final investment decision

Gate Terminal Jetty 4

Named party
Gate Terminal B.V.
Status
Confirmed
Source position
Gate announced FID on 13 January 2026 and planned start-up around the end of 2028. Source
Marine structures

160 m jetty, 200 m combi-wall, dolphins, walkways and 145 m fender structure

Named party
Port of Rotterdam with the Hakkers-De Klerk combination
Status
Confirmed
Source position
The procurement and award descriptions define the principal marine structures and future deepening capability; individual member workshares remain unpublished. Source
Dredging and basin enlargement

Dredging, coastal and shore works

Named party
Hakkers-De Klerk combination; lower-tier allocation undisclosed
Status
Confirmed
Source position
The tender-stage notice states about 450,000 m3 while the award-stage release states about 350,000 m3. No accepted quantity schedule resolves the difference. Source
Early field activity

Soil or dredged-material application, construction discharges and harbour marking

Named party
Aannemingsbedrijf De Klerk and Port of Rotterdam Harbour Master
Status
Confirmed
Source position
Two Rijkswaterstaat notices name De Klerk for Gate Yukonhaven Jetty 4 activities, and BAS 050/2026 records construction in and around Yukonhaven from 6 April. Source
Shore-power interface

High-voltage shore power to IEC/ISO/IEEE 80005-1:2019

Named party
Gate Terminal B.V.
Status
Confirmed
Source position
RVO identifies Gate as applicant and a 2026-2028 delivery window. The record does not identify the electrical contractor or merge this scope into the Port marine contract. Source
Completion and operating release

Accepted berth, dredge prism, systems integration and service start

Named party
Port of Rotterdam, Gate Terminal and the delivery combination
Status
Not evidenced
Source position
Current records show FID, award and early construction only. They do not certify accepted quantities, completed structures, commissioning, navigation release or start-up.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Harbour marking changed for Yukonhaven construction

The Harbour Master removed the red harbour light through 31 August because of construction in and around the basin, supporting an early field-activity classification.

Source

A second Rijkswaterstaat notice tied De Klerk to Jetty 4 construction

The notice concerns discharges associated with realisation of Jetty 4 and strengthens the project-specific mobilisation evidence without allocating the full contract scope.

Source

Port of Rotterdam signed the Hakkers-De Klerk combination

The award resolves the legal marine D&C supplier and updates the public dredging description to about 350,000 m3 while leaving price and member workshares undisclosed.

Source

Gate took final investment decision

FID resolves one express tender-stage condition for execution and establishes the operator's start-up target around the end of 2028.

Source

The marine D&C tender established a conditional execution route

Port of Rotterdam said engineering would be instructed first and physical execution would depend on permits and FID; the tender described about 450,000 m3 of dredging.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Final permits and the owner execution-release or notice-to-proceed chain
  • Reconciliation of the 450,000 m3 tender quantity and 350,000 m3 award quantity
  • Hakkers and De Klerk engineering, fabrication, piling, dredging and shore-work allocation
  • Dredger, piling barge, crane vessels, survey and support fleet
  • Combi-wall, dolphin, walkway, fender, bollard and steel suppliers
  • Baseline bathymetry, dredge prism, material classification and placement route
  • Gate process, transfer-arm, utility, electrical and shore-power interfaces
  • Installed quantities, variations, payments, completion, navigation release and start-up

Reporting status

Construction, confirmed confidence

Last checked 6 August 2026 across 9 cited sources. The dated timeline above carries the project events.

Last checked 6 August 2026 Cited sources 9

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 9