Terminal Capacity

Gate Adds Storage Ahead of Its Next Loading Jetty

Published 1 November 2026 Publisher IMWO Region Europe Confidence Confirmed
Gate comparison distinguishes liquid tank storage, reported annual terminal capacity, jetty duty and expected end 2028 service rather than equating the units.

IMWO original engineering diagram; source: Port of Rotterdam Authority

Gate's fourth LNG tank is commissioned. Its fourth jetty remains under construction for expected end-2028 service, leaving storage, gas send-out and vessel loading on different expansion schedules.

October brings a commissioned tank and a later berth

The Port of Rotterdam Authority reported on 5 October that Gate's fourth LNG tank, with 180,000 m3 of storage, had been completed and commissioned. It puts terminal capacity at 20 billion m3 per year. The authority is building a fourth jetty for small-scale loading and bunkering, expected to start by the end of 2028. Gate took the jetty investment decision in January [1-2].

Storage volume and loading capacity need separate calculations

The tank stores LNG as a liquid; the annual terminal figure concerns gas throughput; a loading berth serves vessel calls through a transfer system and an operating window. Vessel-loading capacity follows a berth-occupancy and transfer-cycle calculation. A marine-capacity assessment should begin with vessel size, parcel size, transfer rate, connection and disconnection time, and the usable hours after competing movements and weather constraints. Storage then supports that schedule by buffering arrivals and withdrawals.

Evidence conclusion

Test the vessel cycle against the complete transfer system

The marine contract names the Hakkers Waterbouw-De Klerk combination and covers a roughly 160 m jetty, a 200 m combi-wall, mooring structures and dredging [3]. For handover, those structures and access have to connect to loading equipment, utilities, controls and the agreed trials. The October commissioning provides a tank in service while the additional loading position follows its own construction programme. A capacity forecast should state the first usable vessel service and its operating limits, then identify which equipment releases and tests enable the full service range. Gate's expected end-2028 start-up is the planning date to test against that integrated sequence.

Outstanding evidence

  • Jetty marine and terminal-system handover sequence
  • Transfer-cycle assumptions for small-scale loading and bunkering
  • Operating trials and actual first service