Molo Sali Phase B sheet-pile restoration and quay completion

Official Molo Sali project section at Porto Marghera showing the canal, sheet-pile quay edge and rear fill area

North Adriatic Sea Port Authority; exact official project illustration, not Phase B construction progress

The North Adriatic Sea Port Authority concluded contract G00033 for Molo Sali Lot 2 Phase B on 23 July 2026 with a planned RTI led by Rossi Renzo Costruzioni S.r.l. and including Locapal S.r.l., e-Marine S.r.l. and Impresa Costruzioni Mentucci Aldo S.r.l. TED notice 514687-2026, published on 24 July, records a EUR 8,295,571.84 result. Phase B is intended to restore the remaining perimeter sheet piling, complete the port quay and prepare the rear area for future port use and further filling. No cited record establishes notice to proceed, site possession, first marine operation, progress or acceptance.

Project signal

Award in Italy

Current status TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified Source confidence Confirmed

Location

Italy / Europe

Segment

Sheet-pile rehabilitation and port-yard conversion

Status

TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified / Confirmed

Last checked

16 August 2026

Coverage

Related sectors

Sheet-pile rehabilitation and port-yard conversion is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Autorita di Sistema Portuale del Mare Adriatico Settentrionale, Ports of Venice and Chioggia
Delivery parties
Rossi Renzo Costruzioni S.r.l. - planned RTI leader identified by TED, Locapal S.r.l. - planned RTI member, e-Marine S.r.l. - planned RTI member, Impresa Costruzioni Mentucci Aldo S.r.l. - planned RTI member, Subcontractors - intended according to TED, but no organization is named in the reviewed award fields
Contract route
The port authority authorized an open procedure for Phase B under CUP F77I18000620005 and project G00033. TED procedure 0faf7c71-95c3-4c1b-b85d-771af88031b9 culminated in award notice 514687-2026. The notice records contract conclusion on 23 July and publication on 24 July 2026, one planned four-member RTI and intended subcontracting without named lower-tier parties.
Execution window
The contract-conclusion and publication dates move Phase B into award, but no cited source publishes the notice to proceed, site-possession date, contractual start, accepted programme or completion date. Phase A's separate completion and testing record cannot be carried across as Phase B progress.
Works package
Phase B addresses the remaining Molo Sali perimeter after Phase A. The owner describes restoration of the sheet-pile edge and completion of quay structures so the rear area can receive further fill up to approximately +2.30 m and be prepared for future port activities. The works support canal-margin stability and later yard and dock use. Exact Phase B quantities, wall lengths, pile sections, anchors, caps, pavement, utilities and dredged-material acceptance criteria are not exposed by the TED award fields.
Marine interfaces
The package combines an ageing sheet-pile perimeter, canal-edge stability, quay completion and conversion of a contained rear area toward port use in Porto Marghera. Its critical interfaces include retained Phase A works, wall alignment and tie-in, anchor and capping systems, dredged-material fill levels, settlement and drainage, navigation-side access, survey, environmental controls and future yard loading. Official project diagrams are design and geographic context, not as-built or progress evidence.
Commercial evidence boundary
TED records EUR 8,295,571.84 as the result. The authority's procedure decision records a separate EUR 11.4 million Phase B project budget, EUR 9,746,264.38 works amount and EUR 1,653,735.63 owner sums, plus optional additional works of EUR 1,473,788.46 including EUR 2,883.71 safety cost. The wider Phase A and B funding envelope is EUR 16 million. These figures use different bases and cannot be treated as a saving or final account without the contract schedule. TED says subcontracting is intended but names no subcontractor.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Main works award

G00033 Molo Sali Lot 2 Phase B

Named party
Planned RTI led by Rossi Renzo Costruzioni with Locapal, e-Marine and Mentucci Aldo
Status
Confirmed
Source position
TED notice 514687-2026 records the four winners, 23 July contract conclusion and EUR 8,295,571.84 result. Source
Phase B scope

Remaining sheet-pile restoration, quay completion and rear-area preparation

Named party
North Adriatic Sea Port Authority and winning RTI
Status
Confirmed
Source position
The authority describes stabilising the remaining perimeter and enabling further fill and future port-area use after Phase A. Source
Phase A boundary

Previously completed wall and tie-in context

Named party
North Adriatic Sea Port Authority and prior Phase A delivery chain
Status
Confirmed
Source position
The authority records Phase A completion on 26 March 2024 and testing on 7 November 2024; those milestones do not establish Phase B progress. Source
Phase B budget

Authorized project, works, owner sums and optional scope

Named party
North Adriatic Sea Port Authority
Status
Confirmed
Source position
The authority records an EUR 11.4 million Phase B project budget, EUR 9.746 million works basis and separately stated optional works, which are not the TED award value. Source
Subcontracting

Intended lower-tier scope

Named party
No subcontractor named
Status
Undisclosed
Source position
TED marks subcontracting yes but identifies no organization, package or lower-tier value. Source
Mobilisation and acceptance

Phase B site start, installed works and handover

Named party
North Adriatic Sea Port Authority and winning RTI
Status
Not evidenced
Source position
No cited source establishes notice to proceed, first marine operation, measured progress, completion testing, owner acceptance or final account.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

TED publishes the Phase B award

The notice fixes the four-member RTI and EUR 8.296 million result while leaving mobilisation and named subcontractors open.

Source

Port authority concludes contract G00033

Phase B moves from procedure to contract award, but the conclusion date does not prove site possession or physical start.

Source

Authority authorizes the Phase B open procedure

The decision establishes the EUR 11.4 million project budget and separate works, owner-sum and optional-scope bases before the later contract result.

Source

Authority records the separate Phase A test

The Phase A close-out defines the physical handoff into Phase B but is not evidence that the new contract has mobilised.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • RTI constitution and Rossi Renzo Costruzioni leader role
  • Contract effectiveness, notice to proceed and site possession
  • Accepted Phase B programme and completion baseline
  • Remaining sheet-pile length, section, anchors and capping design
  • Tie-in and responsibility boundary with completed Phase A
  • Dredged-material fill level, settlement, drainage and acceptance
  • Quay, yard, pavement, utilities and future-load interfaces
  • Named subcontractors, suppliers, marine plant and package values
  • First physical operation and verified installed quantities
  • Completion testing, owner acceptance, variations and final account

Reporting status

Award, confirmed confidence

Last checked 16 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 16 August 2026 Cited sources 5