The North Adriatic Sea Port Authority concluded contract G00033 for Molo Sali Lot 2 Phase B on 23 July 2026 with a planned RTI led by Rossi Renzo Costruzioni S.r.l. and including Locapal S.r.l., e-Marine S.r.l. and Impresa Costruzioni Mentucci Aldo S.r.l. TED notice 514687-2026, published on 24 July, records a EUR 8,295,571.84 result. Phase B is intended to restore the remaining perimeter sheet piling, complete the port quay and prepare the rear area for future port use and further filling. No cited record establishes notice to proceed, site possession, first marine operation, progress or acceptance.
Project signal
Award in Italy
Current statusTED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverifiedSource confidenceConfirmed
Location
Italy / Europe
Segment
Sheet-pile rehabilitation and port-yard conversion
Status
TED notice 514687-2026 records a EUR 8,295,571.84 contract concluded on 23 July 2026 with the Rossi Renzo Costruzioni-led four-member RTI; notice to proceed, mobilisation, named subcontractors and installed work remain unverified / Confirmed
Last checked
16 August 2026
Coverage
Related sectors
Sheet-pile rehabilitation and port-yard conversion is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Autorita di Sistema Portuale del Mare Adriatico Settentrionale, Ports of Venice and Chioggia
Delivery parties
Rossi Renzo Costruzioni S.r.l. - planned RTI leader identified by TED, Locapal S.r.l. - planned RTI member, e-Marine S.r.l. - planned RTI member, Impresa Costruzioni Mentucci Aldo S.r.l. - planned RTI member, Subcontractors - intended according to TED, but no organization is named in the reviewed award fields
Contract route
The port authority authorized an open procedure for Phase B under CUP F77I18000620005 and project G00033. TED procedure 0faf7c71-95c3-4c1b-b85d-771af88031b9 culminated in award notice 514687-2026. The notice records contract conclusion on 23 July and publication on 24 July 2026, one planned four-member RTI and intended subcontracting without named lower-tier parties.
Execution window
The contract-conclusion and publication dates move Phase B into award, but no cited source publishes the notice to proceed, site-possession date, contractual start, accepted programme or completion date. Phase A's separate completion and testing record cannot be carried across as Phase B progress.
Works package
Phase B addresses the remaining Molo Sali perimeter after Phase A. The owner describes restoration of the sheet-pile edge and completion of quay structures so the rear area can receive further fill up to approximately +2.30 m and be prepared for future port activities. The works support canal-margin stability and later yard and dock use. Exact Phase B quantities, wall lengths, pile sections, anchors, caps, pavement, utilities and dredged-material acceptance criteria are not exposed by the TED award fields.
Marine interfaces
The package combines an ageing sheet-pile perimeter, canal-edge stability, quay completion and conversion of a contained rear area toward port use in Porto Marghera. Its critical interfaces include retained Phase A works, wall alignment and tie-in, anchor and capping systems, dredged-material fill levels, settlement and drainage, navigation-side access, survey, environmental controls and future yard loading. Official project diagrams are design and geographic context, not as-built or progress evidence.
Commercial evidence boundary
TED records EUR 8,295,571.84 as the result. The authority's procedure decision records a separate EUR 11.4 million Phase B project budget, EUR 9,746,264.38 works amount and EUR 1,653,735.63 owner sums, plus optional additional works of EUR 1,473,788.46 including EUR 2,883.71 safety cost. The wider Phase A and B funding envelope is EUR 16 million. These figures use different bases and cannot be treated as a saving or final account without the contract schedule. TED says subcontracting is intended but names no subcontractor.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Main works award
G00033 Molo Sali Lot 2 Phase B
Named party
Planned RTI led by Rossi Renzo Costruzioni with Locapal, e-Marine and Mentucci Aldo
Status
Confirmed
Source position
TED notice 514687-2026 records the four winners, 23 July contract conclusion and EUR 8,295,571.84 result. Source
Phase B scope
Remaining sheet-pile restoration, quay completion and rear-area preparation
Named party
North Adriatic Sea Port Authority and winning RTI
Status
Confirmed
Source position
The authority describes stabilising the remaining perimeter and enabling further fill and future port-area use after Phase A. Source
Phase A boundary
Previously completed wall and tie-in context
Named party
North Adriatic Sea Port Authority and prior Phase A delivery chain
Status
Confirmed
Source position
The authority records Phase A completion on 26 March 2024 and testing on 7 November 2024; those milestones do not establish Phase B progress. Source
Phase B budget
Authorized project, works, owner sums and optional scope
Named party
North Adriatic Sea Port Authority
Status
Confirmed
Source position
The authority records an EUR 11.4 million Phase B project budget, EUR 9.746 million works basis and separately stated optional works, which are not the TED award value. Source
Subcontracting
Intended lower-tier scope
Named party
No subcontractor named
Status
Undisclosed
Source position
TED marks subcontracting yes but identifies no organization, package or lower-tier value. Source
Mobilisation and acceptance
Phase B site start, installed works and handover
Named party
North Adriatic Sea Port Authority and winning RTI
Status
Not evidenced
Source position
No cited source establishes notice to proceed, first marine operation, measured progress, completion testing, owner acceptance or final account.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.