Project record

Ocean City and Peck Beach 2026 Periodic Nourishment

Great Lakes Dredge & Dock hopper dredge TEXAS working offshore from Ocean City while beachfill pipeline and sand-handling equipment occupy the foreground

U.S. Army Corps of Engineers, Philadelphia District

The U.S. Army Corps of Engineers' Philadelphia District awarded Great Lakes Dredge & Dock a USD 19.5 million contract for periodic nourishment of the Great Egg Harbor and Peck Beach coastal storm risk management project at Ocean City, New Jersey. The contract calls for dredging, pumping and placing more than 1.6 million cubic yards of sand from an offshore borrow area, then grading it into an elevated beach berm between 12th Street and the Seaview Road groin area. USACE records construction as beginning on 7 July 2026 and the dredge Illinois as mobilised at the 10 July field-status boundary. The formal programme record traces the protection system to a 1991 partnership agreement and 1992 initial construction, while the City records the separate 2022-23 cycle as complete with 1.5 million cubic yards of beachfill and a 47,600-cubic-yard stockpile. Those historical quantities do not measure the current contract. The current evidence establishes an active marine works package, but not the quantity already placed, conformity with the design template, completion by the forecast early-September date or acceptance of the finished protection system.

Project signal

Construction in United States

Programme authority, prior-cycle completion, current award, dredge mobilisation, offshore production, pipeline delivery, placed quantity, surveyed template and owner acceptance remain separate records. The more-than-1.6-million-cubic-yard figure is current contracted scope rather than measured output; the 1.5-million-cubic-yard placement and 47,600-cubic-yard stockpile belong to the completed 2022-23 cycle; and the USD 19.5 million award is neither a lifetime programme value nor evidence of current accepted geometry.

Current status Great Lakes Dredge & Dock's USD 19.5 million nourishment contract is in construction; dredge mobilisation is evidenced, but placed volume, accepted beach template and completion remain open Source confidence Confirmed

Location

United States / Americas

Segment

Coastal infrastructure

Status

Great Lakes Dredge & Dock's USD 19.5 million nourishment contract is in construction; dredge mobilisation is evidenced, but placed volume, accepted beach template and completion remain open / Confirmed

Evidence reviewed

16 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
U.S. Army Corps of Engineers, Philadelphia District, with the New Jersey Department of Environmental Protection and City of Ocean City
Delivery parties
Great Lakes Dredge & Dock Company
Contract route
USACE awarded a USD 19.5 million periodic-nourishment contract to Great Lakes Dredge & Dock. Construction is cost shared 65% federally and 35% non-federally through the USACE, New Jersey and Ocean City partnership. The award covers the current nourishment cycle, not the original 1992 construction, previous cycles, future nourishment or the whole New Jersey coastal programme.
Execution window
USACE announced the award on 1 June 2026 and initially expected work to begin in early July. Its project status page records construction beginning on 7 July 2026, with completion forecast for early September 2026. The dredge Illinois was mobilised at the 10 July field-status boundary. The page carries a 14 July update label, but its controlling construction narrative remains the 10 July mobilisation statement. The forecast remains a programme date until production, beach survey, demobilisation and acceptance evidence are published.
Works package
The contract calls for more than 1.6 million cubic yards of sand to be dredged from an offshore borrow site near Great Egg Harbor Inlet, pumped through pipeline to Ocean City and graded into an elevated berm with a minimum 100-foot width at elevation +8.0 feet NGVD. Sand placement runs from 12th Street to the Seaview Road groin area. The project is periodic nourishment of a protection system first constructed in 1992 rather than a new greenfield shoreline scheme.
Marine interfaces
The acceptance chain covers borrow-area authorization and sediment suitability, dredge production, weather and navigation around Great Egg Harbor Inlet, floating and shore pipeline integrity, pump-out and beach access, environmental windows and species controls, daily placed-volume reconciliation, grading, dune and berm survey, transitions at groins and adjacent reaches, public-access restoration, demobilisation and post-work storm-risk performance.
Commercial read
This is a bounded current works contract with an identifiable owner, contractor, quantity, workfront and cost-sharing structure. The immediate operating questions concern production and accepted geometry rather than market formation. Mobilisation of the dredge Illinois is evidence of readiness, not production; a contractor quantity or beach closure notice is not proof of a complete 1.6 million-cubic-yard placement or accepted risk-reduction outcome.
Next milestone
Track first verified dredging and pump-out, daily and cumulative quantities, borrow-area and pipeline performance, environmental compliance, surveyed berm width and elevation, transitions at the groin and project limits, beach-access restoration, substantial completion, USACE acceptance and any post-construction monitoring or repair requirement.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

Dredge Illinois reached the mobilisation gate

USACE recorded the dredge Illinois as mobilised and set to begin operations. The statement establishes plant readiness at the workfront, not first production, pumped quantity, placed quantity, compliant geometry, completion or acceptance.

Read controlling source

USACE recorded the current construction start

The project page records construction beginning on 7 July. That milestone advances the package beyond award, while production, beachfill quantity, surveyed template, demobilisation and owner acceptance remain separate gates.

Read controlling source

USACE awarded the current periodic-nourishment contract

The USD 19.5 million Great Lakes Dredge & Dock award calls for more than 1.6 million cubic yards from the offshore borrow area and placement from 12th Street to the Seaview Road groin area. The quantity is contractual scope, not measured current-cycle output.

Read controlling source

City records closed the preceding nourishment cycle

Ocean City reports the 21 November 2022 to 15 February 2023 campaign complete with 1.5 million cubic yards of beachfill and a 47,600-cubic-yard stockpile. Those are prior-cycle results and cannot be carried into 2026 production or acceptance.

Read controlling source

The partnership agreement established the federal coastal programme

The USACE fact sheet records the Project Partnership Agreement on 18 September 1991 and initial construction in 1992, with approximately 6.2 million cubic yards of initial fill and an approximately three-year nourishment cycle. That programme baseline defines the asset history, not current-contract performance.

Read controlling source

Delivery watch

Evidence needed next

Track first verified dredging and pump-out, daily and cumulative quantities, borrow-area and pipeline performance, environmental compliance, surveyed berm width and elevation, transitions at the groin and project limits, beach-access restoration, substantial completion, USACE acceptance and any post-construction monitoring or repair requirement.

Decision watchpoints

  • Dredge Illinois production start and plant availability
  • Borrow-area authorization, sediment suitability and environmental controls
  • Daily and cumulative dredged, pumped and placed quantities
  • Pipeline integrity, shore landings and public-access management
  • Surveyed 100-foot berm width and +8.0-foot NGVD elevation
  • Transitions at groins, limits and previously nourished reaches
  • Substantial completion, demobilisation and USACE acceptance
  • Post-work storm response and the next nourishment decision

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 16 July 2026 Sources in this record 6

Source record

The 1 June 2026 USACE award release controls the contractor, USD 19.5 million value, contractual quantity, borrow source, placement reach, cost share and expected July start. The project page controls the 7 July construction start, dredge Illinois mobilisation, early-September forecast, 100-foot berm at +8.0 feet NGVD and programme history; its page label says updated 14 July while the field-status narrative remains dated 10 July. The USACE fact sheet controls the 18 September 1991 partnership agreement, 1992 initial construction, approximately 6.2-million-cubic-yard initial fill and approximately 1.1-million-cubic-yard three-year nourishment baseline. The City of Ocean City page controls the separate 2022-23 completion and quantities. The district programme page and NJDEP page supply programme and partnership context. A current placed quantity, accepted survey, completion certificate and performance result are not published.

Phase: construction. Evidence reviewed: 16 July 2026.

Project sources 6