Project record

NOC Southampton quayside wall and pontoon repairs

Participation
Awarded
Participation checked

National Oceanography Centre signed Seawork Marine Services on 8 May 2025 for GBP 88,800 including VAT; the contract period ran from 13 August to 12 September 2025, but no dated completion, acceptance or final-account record has been located

Participation source

The National Oceanography Centre signed Seawork Marine Services for quayside wall and pontoon repairs at its Southampton site. Find a Tender records GBP 88,800 including VAT, an 8 May 2025 signature and a 13 August to 12 September contract period. The below-threshold contract was placed without competition because NOC, as an Associated British Ports tenant, identified the supplier as ABP's preferred or nominated provider for the work. The notices do not publish dimensions, quantities, materials, mobilisation, completed work, acceptance or final payment.

National Oceanography Centre official Southampton dockside context showing the working port waterfront

National Oceanography Centre; Southampton dockside context image, not evidence of NOCP00510 mobilisation, repairs or completion

Location

United Kingdom / Europe

Segment

Seawall, quayside and pontoon repair

Phase

Award / Confirmed

Last checked

14 October 2026

Coverage

Related sectors

Seawall, quayside and pontoon repair is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
National Oceanography Centre
Procurement references
NOCP00510; ocds-h6vhtk-0500a2; 019766-2025
Delivery parties
Seawork Marine Services, Companies House 00721735 - confirmed signed supplier; the notice narrative also uses Sea Works Marine and SeaWork Marine Ltd, Associated British Ports - Southampton docks landlord and nominated-supplier context only; not identified as the contracting authority or works contractor, Design, survey, diving, materials, plant and any other downstream parties - not identified in the cited sources
Contract route
Procurement reference NOCP00510 used a below-threshold procedure without competition under OCID ocds-h6vhtk-0500a2. NOC stated that its ABP tenancy obliged it to use ABP's preferred or nominated supplier. The UK7 contract-details notice records signature on 8 May 2025.
Execution window
The April 2025 transparency notice estimated work from 7 to 25 July 2025. The later signed-contract notice changed the period to 13 August through 12 September 2025. Use the later dates as the contractual baseline, but not as evidence of mobilisation, completion or acceptance.
Works package
Quayside wall and pontoon repairs at the National Oceanography Centre's Southampton site. Although the procurement is titled Sea Wall Repairs and uses sea-wall construction CPV 45243300, the notices provide no wall length, pontoon count, repair method, structural detail, material quantity, utility scope or temporary-works boundary.
Marine interfaces
The work sits at NOC's waterfront site inside Southampton Docks. Quayside and pontoon repairs create live-water, access and operational interfaces, but the cited procurement record does not identify navigation restrictions, marine plant, diving, hydrographic survey, environmental controls or coordination measures.
Commercial evidence boundary
The signed value is GBP 88,800 including VAT. No excluding-VAT value, payment schedule, measured-work basis, variation, retention, final account or lower-tier allocation is disclosed. The direct route is explained through NOC's ABP tenancy and nominated-supplier obligation; it does not establish ABP payment or package ownership.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Signed works contract

NOCP00510 Sea Wall Repairs

Named party
Seawork Marine Services
Evidence status
Confirmed
Source position
The UK7 notice records an 8 May 2025 signature, GBP 88,800 including VAT and a 13 August to 12 September contract period. Source
Physical scope

Quayside wall and pontoon repairs at NOC Southampton

Named party
National Oceanography Centre and Seawork Marine Services
Evidence status
Confirmed
Source position
Both notices identify quayside wall and pontoon repairs but publish no dimensions, quantities, methods or material schedule. Source
Procurement route

Below-threshold award without competition

Named party
National Oceanography Centre
Evidence status
Confirmed
Source position
NOC states that, as an ABP tenant, it was obliged to use ABP's preferred or nominated supplier for the work. This explains the route without making ABP the contracting authority. Source
Schedule baseline

Initial estimate versus signed contract period

Named party
National Oceanography Centre
Evidence status
Confirmed
Source position
The UK5 notice estimated 7 to 25 July 2025; the later UK7 notice records 13 August to 12 September. Neither date set proves physical delivery. Source
Execution and closeout

Mobilisation, repaired quantities, handback and acceptance

Named party
National Oceanography Centre and Seawork Marine Services
Evidence status
Not evidenced
Source position
No cited source confirms physical start, repair method, completed quantities, defects close-out, owner acceptance or final account.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

NOC signed the quayside repair contract

The UK7 notice fixed Seawork Marine Services, GBP 88,800 including VAT and the later August-September contract period while leaving delivery and acceptance unpublished.

Source

Transparency notice disclosed the direct route

NOC identified the wall-and-pontoon scope and ABP nominated-supplier basis, but its earlier July estimate was superseded by the signed notice's later dates.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Physical mobilisation and worksite access
  • Wall length, pontoon count and repair quantities
  • Repair method, materials, temporary works and marine plant
  • Diving, survey, design and other downstream parties
  • Navigation restrictions and operational coordination
  • Pontoon and quayside handback
  • Completion, defects close-out and owner acceptance
  • Payment, variation and final account

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
14 October 2026
Cited sources
5

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 5