Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account
Cheticamp's integrated harbour package moved to Superior Contracting Ltd. under contract EB144-222071/001/PWA, procured by Public Services and Procurement Canada for Fisheries and Oceans Canada. CanadaBuys records a CAD 1,264,230 total and a contract period ending 31 March 2023. The package demolishes the existing timber-pile wharf, dredges the harbour bottom, repairs and raises the breakwater, modifies the upland area, installs floating docks, strongarms, gangways, concrete abutments and retaining walls, and replaces electrical power and lighting. Accepted quantities, subcontractors, completion certification and final account remain unpublished.
IMWO artist's impression of the published Cheticamp Jobs Wharf floating-dock reconstruction scope
Canada / Americas
Fishing harbour wharf, dredging and shore protection
Delivery / Confirmed
9 August 2026
Coverage
Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCanadaBuys carries 31 March 2023 as the expiry date without publishing final inspection, accepted quantities, operating release or a certified final account.
SourceThe CAD 1,264,230 contract placed demolition, dredging, breakwater, floating-dock, concrete, upland and electrical works under Superior Contracting Ltd. as prime.
SourceEvidence gap