Contract Close-out

Cheticamp's CAD 1.264m award lacks public handover evidence

Published 9 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Cheticamp Jobs Wharf view of floating docks, steel strongarms, a gangway and harbour dredging beside timber piles and a rock breakwater

IMWO artist's impression accompanying this evidence brief

CanadaBuys confirms Superior Contracting Ltd. at CAD 1,264,230 for the Cheticamp Jobs Wharf package. The tender joins timber-pile wharf demolition, harbour-bottom dredging, designated disposal, breakwater raising and repair, upland grading, floating docks, strongarms, gangways, concrete works and electrical reinstatement. Its published contract window ended on 31 March 2023; federal public records supply no accepted quantities, commissioning certificate, owner handover or final account.

One award joins seven workstreams but closes none of their acceptance records

CanadaBuys controls the prime, CAD 1,264,230 total, award date, expiry and related procurement identity. Official attachments control the tendered work boundaries, not execution or acceptance. Federal project records publish no measured dredging, disposal close-out, as-built breakwater levels, installed dock inventory, electrical commissioning, lower-tier assignments, final payment or owner handover. The illustration is editorial scope context only.

The unresolved evidence sits below the prime award

This package cannot be assessed from the expiry date alone. Dredging closes on surveys and accepted disposal records; the breakwater closes on as-built geometry and rock acceptance; floating access closes on inventory, anchoring and gangway checks; concrete and electrical work close on inspection and commissioning. Harbour reopening needs a dated owner release after those interfaces converge.

Evidence conclusion

Physical completion still requires owner acceptance

Outstanding evidence

  • Pre- and post-dredge hydrographic surveys
  • Measured sediment quantity and designated disposal acceptance
  • Breakwater fill, elevation and slope-protection as-builts
  • Installed float, strongarm and gangway inventory
  • Concrete abutment and retaining-wall inspection
  • Electrical power and lighting commissioning
  • Named marine, civil, electrical and survey lower tiers
  • Final account, owner acceptance and harbour return to service

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.