USACE awarded a placement-area maintenance contract in March 2024 with an initial plan to move about 500,000 cubic yards to Isle of Palms and 200,000 cubic yards to Sullivan's Island. A separate Cottrell package later dredged active AIWW shoals. USACE's completion release reports about 700,000 cubic yards across the two Isle of Palms projects; the City separately records 265,000 cubic yards under Cottrell. Both beach-placement campaigns finished on 27 February 2026, followed by removal of concentrated clay pockets in April.
Project signal
Completed in United States
Award and completion are documented, but the sources do not provide a contractor-by-contractor final quantity split. Keep the original Ahtna allocation of about 500,000 cubic yards for Isle of Palms and 200,000 for Sullivan's Island separate from the later combined completion figure. Keep Cottrell's City-reported 265,000 cubic yards separate as well; do not subtract it from the USACE total to manufacture an Ahtna final quantity. Long-term beach response still depends on survey evidence.
Current statusTwo dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in MaySource confidenceConfirmed
Location
United States / Americas
Segment
Coastal infrastructure
Status
Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May / Confirmed
Evidence reviewed
18 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
U.S. Army Corps of Engineers, Charleston District, with the City of Isle of Palms
Delivery parties
Ahtna Marine & Construction Company / Cavache Dredging, Cottrell Contracting Corporation, Sewee Construction (shoreline cleanup subcontractor)
Contract route
USACE awarded the placement-area maintenance contract in March 2024, funded in part by the Bipartisan Infrastructure Law and regular AIWW operations-and-maintenance funding. Cottrell's later active-shoal dredging was a separate federal package. Neither package value is published.
Execution window
The original rehandling contract required completion by 26 January 2025. USACE still recorded active Isle of Palms and Sullivan's Island placement in April 2025, and the City reported fewer than 200,000 cubic yards remaining under Ahtna on 23 January 2026. Ahtna and Cottrell both finished beach placement on 27 February 2026; clay cleanup followed in April and the last staging area was cleared by 12 May. Public records do not assign responsibility for the longer delivery period or identify approved extensions.
Works package
Ahtna rehandled material from four existing AIWW placement areas to recover future capacity. Its original allocation was about 500,000 cubic yards for Isle of Palms and 200,000 for Sullivan's Island. Cottrell first routed material from Dewees Inlet shoal and Breach Inlet shoal 1B to an open-water site, then placed material from shoal 1A on Isle of Palms. The City records 265,000 cubic yards under Cottrell; USACE's completion release reports about 700,000 cubic yards across both Isle of Palms jobs.
Marine interfaces
Active AIWW shoals, four upland placement areas, hydraulic dredging and rehandling, open-water placement, temporary pipeline and booster-pump systems, 24-hour intertidal placement, public-access ramps, turtle monitoring, tidal redistribution and shoreline cleanup
Commercial read
Reusing sand recovered storage capacity in four placement areas and avoided a disposal-only route. USACE chose below-high-tide placement partly to reduce cost and let tides wash out silt, clay and vegetation. That assumption was only partly self-executing: concentrated clay pockets still needed a separate six-day low-tide cleanup crew after placement.
Next milestone
Published channel and beach-profile surveys showing the maintained navigation condition and how the intertidal placement redistributed after completion
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Ahtna cleared the final staging area
The City reported that staging was removed and beach access and parking were restored, closing the remaining visible construction footprint.
The district reported about 700,000 cubic yards placed below high tide between 2nd and 10th Avenue. The figure covers the combined programme and does not provide a contractor-by-contractor final split.
Sewee Construction was brought in under Cottrell to remove concentrated clay and mud at low tide, turning a material-compatibility issue into a defined cleanup task after placement.
Ahtna entered its final borrow area as Cottrell approached
The City reported fewer than 200,000 cubic yards remaining. Ahtna shifted south of 6th Avenue so the separate Cottrell package could work nearby, while continuing 24-hour operations.
Cottrell's material routes were separated by shoal
The City said Dewees Inlet material and Breach Inlet shoal 1B material would go to an open-water site before shoal 1A material was placed on the Isle of Palms beach.
Published channel and beach-profile surveys showing the maintained navigation condition and how the intertidal placement redistributed after completion
Decision watchpoints
Post-dredge channel condition at Breach Inlet and the AIWW shoals
Beach-profile surveys between 2nd and 10th Avenue
Movement of the below-high-tide placement across the active profile
Any further clay or unsuitable-material cleanup
Recovered capacity in the four AIWW placement areas
Future maintenance frequency at the recurring shoals
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed18 July 2026Sources in this record7
Source record
The USACE project page provides the initial 500,000-cubic-yard Isle of Palms and 200,000-cubic-yard Sullivan's Island allocations, below-high-tide rationale and original 26 January 2025 completion requirement. The April 2025 AIWW fact sheet records the March 2024 placement-area maintenance award and confirms that placement remained active. City updates define Cottrell's open-water and beach-placement sequence, Ahtna's January 2026 remaining quantity and the coordination between the two contractors. USACE's 20 April 2026 release reports about 700,000 cubic yards across two Isle of Palms projects; the City separately records 265,000 cubic yards under Cottrell and both contractors' 27 February completion. A final Ahtna quantity, approved extensions, package values and responsibility for the longer delivery period are not published. Completion does not establish long-term shoreline performance.
Phase: completed. Evidence reviewed: 18 July 2026.