IJsselmeerdijk foreshore and conventional dike reinforcement

Participation
Not assessed
Project facts checked

Owner reports realization has begun with the lake-side foreshore; conventional dike work planned from early 2027, quantities and acceptance unconfirmed

Project sources

Waterschap Zuiderzeeland identifies a foreshore-first programme with the Boskalis and Van Oord combination. Approximately 12 km of foreshore and 5 km of conventional dike measures form separate treatments within the reinforcement scope.

IJsselmeerdijk workfront diagram for Zuiderzeeland and the Boskalis Van Oord combination: initial Maxima Ketelbrug foreshore, worksite crossing and planned early-2027 existing-dike works

IMWO original IJsselmeerdijk workfront/interface diagram from dated owner and PAGW statements; non-geographic programme schematic, not surveyed progress

Location

Netherlands / Europe

Segment

Coastal infrastructure

Phase

Construction / Confirmed

Last checked

4 September 2026

Coverage

Related sectors

Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Waterschap Zuiderzeeland
Delivery parties
Boskalis and Van Oord, Combinatie IJsselmeerdijk
Contract route
European procurement with provisional selection announced in June 2025 and definitive execution contract reported in July 2025. The cited announcements do not disclose a works contract price.
Execution window
Initial foreshore realization between Maxima power station and Ketelbrug reported in September 2026; existing-dike work between Flevokust Haven and Maxima planned from early 2027. Final acceptance date and measured completion remain unconfirmed.
Works package
Approximately 12 km foreshore with a wave-attenuating dam and shallow-water/reed zone; around 5 km conventional measures including dike raising and exterior revetment replacement. These are announced scope lengths, not accepted constructed lengths.
Marine interfaces
Lake-side material delivery and unloading interact with other waterway users and land access. The dated mobility plan supplies assumptions for nautical logistics; supply-vessel frequency, material tonnage and plant dimensions are not actual deliveries or a selected fleet. Worksite and temporary dike-crossing interfaces require separate execution information.
Commercial evidence boundary
Lake-side and conventional workfronts involve different supply and access interfaces. The June provisional selection and July signed contract are successive procurement milestones. Production rates, final contract price and accepted hydraulic performance are not disclosed by the cited announcements; logistics quantities remain planning assumptions.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Foreshore protection

Lake-side wave attenuation and shallow-water zone

Named party
Boskalis and Van Oord combination
Evidence status
Confirmed
Source position
Owner account identifies the initial Maxima-Ketelbrug workfront and approximate 12 km foreshore programme; accepted length and output unconfirmed. Source
Conventional dike reinforcement

Existing dike and exterior revetment

Named party
Boskalis and Van Oord combination
Evidence status
Confirmed
Source position
Owner account identifies around 5 km conventional measures and early-2027 start for Flevokust-Maxima existing-dike work; not reported complete. Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dated execution schedules for separate lake-side and conventional packages
  • Identified material delivery, unloading and navigation arrangements
  • Reported quantities and accepted protection performance
  • Access arrangements at the worksite and temporary dike crossing

Reporting status

Project phase
Construction
Evidence confidence
Confirmed
Last checked
4 September 2026
Cited sources
4

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 4