IJsselmeerdijk foreshore and conventional dike reinforcement
Participation
Not assessed
Project facts checked
Owner reports realization has begun with the lake-side foreshore; conventional dike work planned from early 2027, quantities and acceptance unconfirmed
Waterschap Zuiderzeeland identifies a foreshore-first programme with the Boskalis and Van Oord combination. Approximately 12 km of foreshore and 5 km of conventional dike measures form separate treatments within the reinforcement scope.
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Waterschap Zuiderzeeland
Delivery parties
Boskalis and Van Oord, Combinatie IJsselmeerdijk
Contract route
European procurement with provisional selection announced in June 2025 and definitive execution contract reported in July 2025. The cited announcements do not disclose a works contract price.
Execution window
Initial foreshore realization between Maxima power station and Ketelbrug reported in September 2026; existing-dike work between Flevokust Haven and Maxima planned from early 2027. Final acceptance date and measured completion remain unconfirmed.
Works package
Approximately 12 km foreshore with a wave-attenuating dam and shallow-water/reed zone; around 5 km conventional measures including dike raising and exterior revetment replacement. These are announced scope lengths, not accepted constructed lengths.
Marine interfaces
Lake-side material delivery and unloading interact with other waterway users and land access. The dated mobility plan supplies assumptions for nautical logistics; supply-vessel frequency, material tonnage and plant dimensions are not actual deliveries or a selected fleet. Worksite and temporary dike-crossing interfaces require separate execution information.
Commercial evidence boundary
Lake-side and conventional workfronts involve different supply and access interfaces. The June provisional selection and July signed contract are successive procurement milestones. Production rates, final contract price and accepted hydraulic performance are not disclosed by the cited announcements; logistics quantities remain planning assumptions.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
Foreshore protection
Lake-side wave attenuation and shallow-water zone
Named party
Boskalis and Van Oord combination
Evidence status
Confirmed
Source position
Owner account identifies the initial Maxima-Ketelbrug workfront and approximate 12 km foreshore programme; accepted length and output unconfirmed. Source
Conventional dike reinforcement
Existing dike and exterior revetment
Named party
Boskalis and Van Oord combination
Evidence status
Confirmed
Source position
Owner account identifies around 5 km conventional measures and early-2027 start for Flevokust-Maxima existing-dike work; not reported complete. Source
Evidence gap
What remains unverified
Outstanding evidence
Dated execution schedules for separate lake-side and conventional packages
Identified material delivery, unloading and navigation arrangements
Reported quantities and accepted protection performance
Access arrangements at the worksite and temporary dike crossing
Planning assumptions and nautical/access interfaces, not delivered quantities or selected fleet. February 2024 phasing is not a definitive execution programme.