Coastal Delivery
IJsselmeerdijk starts on the lake side, with conventional dike work to follow
The Boskalis and Van Oord combination has begun IJsselmeerdijk realization with lake-side foreshore works, according to Zuiderzeeland. Its announced scope separates approximately 12 km of foreshore protection from 5 km of conventional reinforcement.
The first workfront is between Maxima and Ketelbrug
Boskalis and Van Oord's IJsselmeerdijk combination has begun realization of the reinforcement programme, according to the owner's account republished by PAGW on 3 September. The first workfront is the foreshore between the Maxima power station and Ketelbrug. Conventional reinforcement of the existing dike between Flevokust Haven and the power station is expected to start in early 2027. These are different workfronts and schedules within the same defence programme.
The programme combines two defence treatments
The announced scope divides roughly 17 km into around 12 km of lake-side foreshore protection and 5 km of conventional dike measures. The foreshore incorporates a wave-attenuating dam with a partly shallow-water and reed zone behind it. The remaining section includes dike raising and replacement of exterior revetment. This establishes the engineering division; it does not report constructed lengths, accepted hydraulic performance or a final as-built section. Marine supply and land access connect the two workfronts. The dated mobility study identifies nautical logistics and traffic interfaces, including material handling around Flevokust and access for other lake users. Its tonnage, vessel-frequency and plant dimensions are planning assumptions, not a delivery tally or an announced vessel fleet. The February 2024 phasing is expressly not a definitive execution programme. Any commercial estimate should preserve those qualifications.
Evidence conclusion
Contract stages and execution evidence need separate records
The procurement history also has distinct stages. The June 2025 owner announcement described a credit decision and provisional selection. Its statement that appeals were still running belongs to that announcement, not an assessment of their September 2026 status. A later owner statement reports a signed contract and definitive execution award. The subsequent kickoff therefore should not be described as a fresh award to an unidentified contractor. Lake-side delivery and unloading, other lake users and land access connect the two workfronts. Production rates and accepted protection require dated delivery statistics and acceptance records, neither disclosed in these announcements. The existing dike is described as currently safe; reinforcement addresses future standards.
Outstanding evidence
- Dated execution schedules for separate lake-side and conventional packages
- Identified material delivery, unloading and navigation arrangements
- Reported quantities and accepted protection performance
- Access arrangements at the worksite and temporary dike crossing
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
-
IJsselmeerdijk realization begins with the foreshore
PAGW, republishing Waterschap Zuiderzeeland, 3 September 2026
Explicit owner republication: initial lake workfront and later conventional dike works, not independent measured progress.
-
Definitive execution contract with Boskalis and Van Oord
Waterschap Zuiderzeeland, 11 July 2025
Signed contract and definitive award; no contract price stated.
-
Credit decision and provisional contractor selection
Waterschap Zuiderzeeland, 11 June 2025
Earlier procurement and then-current appeals, not present appeal status.
-
IJsselmeerdijk mobility plan
Waterschap Zuiderzeeland, owner-hosted project document, 10 July 2024
Planning assumptions and nautical/access interfaces, not delivered quantities or selected fleet. February 2024 phasing is not a definitive execution programme.