Location
Italy / Europe
Project record
The Western Ligurian Sea Port Authority is moving Genoa's main breakwater seaward through a deep-water caisson system founded as far as 50 metres below sea level. Webuild reported the 24th caisson installed on 14 June 2026, five days after the works passed the first kilometre. Those are material production milestones, but the usable port-access outcome still depends on foundation completion, caisson and superstructure continuity, dredging, interfaces with the existing breakwater, and accepted navigation geometry.
Italy / Europe
Ports and coastal protection
24 caissons installed and the first kilometre passed; seabed foundation, superstructure, dredging, and navigation-opening gates remain active / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The record advances the repeatable tow-out and controlled-sinking work front to 24 installed units, while foundation completion, caisson-line continuity, filling, armour, superstructure, dredging, and navigation acceptance remain separate gates.
Read controlling sourceThe caisson alignment exceeded one kilometre while seabed consolidation continued. The milestone does not show proportional overall completion, an accepted entrance or an operational navigation route.
Read controlling sourceThe update records 15 installed caissons, more than 50,000 gravel columns, reported 79 percent foundation-column progress and 87 percent seabed gravel placement at that date. Foundation monitoring and downstream structural and navigation gates remained open.
Read controlling sourceThe owner record moves the project from caisson fabrication into offshore placement and documents the first completed tow, sinking, and positioning cycle, without proving repeat production, connected superstructure, or usable port access.
Read controlling sourceThe Port Authority and consortium launch record marks the transition from award and executive design into construction. Its original scope and schedule statements remain dated baseline context rather than current completion evidence.
Read controlling sourceDelivery watch
Track the remaining gravel-column and rock-foundation acceptance, caisson production and placement, filling and superstructure continuity, armour-block installation, dredging quantities and sediment route, existing-breakwater interfaces, hydrographic evidence, and formal opening of the Phase 1 eastern entrance. Keep the later 500-metre Sampierdarena channel and final ultra-large-vessel access as separate acceptance outcomes.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerWebuild's 14 June and 9 June 2026 records control the latest 24-caisson and first-kilometre milestones. Its current project page controls the present 4.8-kilometre Phase 1 frame, more-than-70-caisson basis, seabed and rock quantities, caisson envelope, vessel objective, and 2027/2030 phase targets. The 12 December 2025 record establishes a bounded foundation-treatment milestone, while Port Authority records establish the May 2023 start of works and the first caisson positioned in May 2024. The 2022 award record controls consortium and client-budget value. Legacy 100-caisson, over-90-caisson, 7-million-tonne, and November 2026 statements are retained as dated design or schedule context and are not merged into the current frame without an explicit reconciliation.
Phase: construction. Evidence reviewed: 15 July 2026.