Project record

Le Goulet Harbour 2026 maintenance dredging

Participation
Awarded
Submission deadline
Participation checked

CanadaBuys' 13 October data records the CAD 948,750 tax-inclusive Le Goulet contract CW2466490 awarded to Les Entreprises P E C inc on 10 September 2026; mobilisation, plant, dredged quantities and acceptance remain unreported

Participation source

CanadaBuys' 13 October 2026 award data records Les Entreprises P E C inc on contract CW2466490 under solicitation WS5822483507, awarded on 10 September. The original contract amount and cumulative total are both CAD 948,750; the official data dictionary defines the contract amount as tax-inclusive. The recorded contract period runs from 10 September to 31 December 2026. Its description includes harbour dredging, dredged-material management, containment-cell operations, dewatering, environmental controls and site restoration. Quantities, depth, disposal location, plant and field delivery remain unconfirmed in the inspected records. ECO Technologies Ltd.'s CAD 469,397.56 contract CW2417112 covers the separate 2025 campaign, including barge-excavator and scow dredging and containment-cell reconfiguration.

Aerial view of the Le Goulet small-craft harbour entrance, navigation channel, breakwaters and sheltered basin in New Brunswick

GEMTEC; exact Le Goulet small-craft harbour and navigation-channel context from a separate assignment, not evidence of the 2026 tender's award, method or progress

Location

Canada / Americas

Segment

Fishing harbour wharf, dredging and shore protection

Phase

Award / Confirmed

Last checked

15 October 2026

Coverage

Related sectors

Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Public Services and Procurement Canada as contracting authority on behalf of Fisheries and Oceans Canada, Small Craft Harbours
Procurement references
EC015-270630; WS5822483507; CW2466490
Delivery parties
Les Entreprises P E C inc - prime contractor recorded on the 10 September 2026 original award CW2466490, Dredging, marine transport, approved-disposal, survey, environmental and plant lower tiers - not publicly disclosed, ECO Technologies Ltd. - contractor on separate 2025 Le Goulet contract CW2417112, not the current 2026 contractor
Contract route
The competitive open-bidding RFP EC015-270630 / WS5822483507 was published on 7 August 2026. Its tender CSV records an expired competition with a 1 September 14:00 closing value in fixed UTC-05:00, as defined by the CanadaBuys dictionary. The 13 October award data records original award 000 to Les Entreprises P E C inc on 10 September under CW2466490. PSPC is the contracting entity and DFO the end user. The executed contract has not been obtained.
Execution window
The award data records a contract start of 10 September and expiry on 31 December 2026; the dictionary defines these as the effective and last valid contract dates. The tender CSV's earlier expected start was 30 September. Actual site possession, mobilisation, production, completion and acceptance require separate dated works records. The prior 2025 contract expired on 31 December 2025.
Works package
The tender description covers maintenance dredging in designated harbour-basin areas, transport and disposal of dredged material at approved sites, and associated work. The award description adds dredged-material management, containment-cell operations, dewatering, environmental controls and site restoration. The inspected tender and award records do not specify the dredge prism, quantity, target depth, sediment classification, disposal coordinates, detailed containment requirements, method, plant, production rate, survey basis or acceptance criteria; full technical attachments have not been obtained.
Marine interfaces
The package must coordinate dredging inside an operating small-craft harbour with basin access, fishing-vessel movements, bathymetric control, sediment handling, marine transport and an approved disposal route. The exact navigation controls, environmental windows, disposal approval, tug and scow sequence and harbour operating restrictions remain open evidence items.
Commercial evidence boundary
Original award 000 records CAD 948,750 in both the contract-amount and cumulative-total fields. CanadaBuys defines the contract amount as including taxes; a net price is not supplied in that row. CAD 469,397.56 belongs to ECO Technologies' separate 2025 contract. Scope differences, undisclosed quantities and unreviewed contract attachments prevent a like-for-like production-rate or unit-cost comparison. Awarded value is distinct from certified work, payments and final account.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Procurement history

EC015-270630 / WS5822483507 Le Goulet basin dredging

Named party
PSPC on behalf of DFO Small Craft Harbours
Evidence status
Confirmed
Source position
CanadaBuys records publication on 7 August, a closing value of 1 September 2026 at 14:00 fixed UTC-05:00, and Expired tender status in the 13 October data. Source
Published marine scope

Harbour-basin maintenance dredging, transport and approved disposal

Named party
Les Entreprises P E C inc, named on the original 2026 award
Evidence status
Confirmed
Source position
The tender confirms basin dredging, transport and approved disposal; the award adds containment-cell operations, dewatering, environmental controls and restoration. Quantities, depth, method, plant and disposal location remain unspecified in these records. Source
Historical campaign

CW2417112 Le Goulet 2025 dredging and containment-cell works

Named party
ECO Technologies Ltd.
Evidence status
Confirmed
Source position
CanadaBuys records CAD 469,397.56, award on 8 September 2025 and expiry on 31 December 2025 for a separate prior contract. Source
2026 award

Bid selection, contract, mobilisation, dredging and acceptance

Named party
Les Entreprises P E C inc
Evidence status
Confirmed
Source position
The 13 October official data records original contract CW2466490 awarded on 10 September at CAD 948,750 including taxes, with recorded dates through 31 December. Plant, field start, production, survey and acceptance remain unconfirmed. Source

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

CanadaBuys records the original award to Les Entreprises P E C inc

CW2466490 links the 2026 solicitation to CAD 948,750 including taxes and recorded contract dates of 10 September to 31 December. The award is separate from the 2025 ECO Technologies campaign; actual works and acceptance remain unconfirmed.

Source

CanadaBuys published the 2026 competition

The notice opened a new Le Goulet basin-dredging procurement while leaving value, quantity, method, plant and delivery dates undisclosed.

Source

ECO Technologies received the separate 2025 contract

The prior CAD 469,397.56 award supplies historical context only and cannot be treated as the 2026 award or contractor assignment.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Contract amendments or termination after the 13 October 2026 data snapshot
  • Bill of quantities, dredge limits, target depth and sediment classification
  • Approved disposal site, transport route and environmental conditions
  • Required dredger, excavator barge, scow, tug and survey plant
  • Executed contract, approved programme and named lower tiers
  • Mobilisation, measured production, post-dredge survey and owner acceptance
  • Reconciliation with the separate 2025 ECO Technologies contract and 2024 federal programme context

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
15 October 2026
Cited sources
9