Location
Canada / Americas
Project record
Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record
Fisheries and Oceans Canada's Cap-des-Caissie programme separates into at least two awarded marine packages. Les Entreprises St Louis held a CAD 710,930 contract for 2025 harbour dredging and containment-cell reconfiguration. A later CanadaBuys award placed the CAD 5,094,275.75 king-pile wharf and shore-protection package with Mskikue'j Enterprises for 2026-27. The federal assessment fixes the principal geometry, including a 101 metre wharf stem, an 8.1 metre ell and 175 metres of revetment, but current official records do not prove mobilisation, accepted quantities or completion of either package.
Canada / Americas
Fishing harbour wharf, dredging and shore protection
Award / Confirmed
5 August 2026
Coverage
Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCW2456904 fixed the CAD 5.09 million prime appointment and March 2027 commercial window without proving mobilisation or field delivery.
SourceWharf #402 and shore protection #604 could proceed subject to mitigation; this regulatory gate is separate from contract award and construction start.
SourceCW2390571 ended its four-month term without a cited completion certificate, measured disposal ledger, post-dredge survey or final account.
SourceThe owner identified wharf reconstruction, armourstone protection, containment-cell upgrades and basin dredging but did not publish a project-level budget.
SourceEvidence gap