Project record
Liberia's Monrovia Metropolitan Climate Resilience Project plans a rock revetment at West Point, a densely occupied Atlantic shoreline where UNDP reports approximately 30 metres of retreat and the loss of 670 homes over the preceding decade. The Environmental Protection Agency permit published by UNDP on 4 March 2026 authorizes construction within defined UTM coordinates after approval of the environmental and social impact assessment. The wider GCF-financed project remains under implementation to July 2027. The construction contractor, executed works value, notice to proceed, mobilisation date and installed and accepted revetment are not identified.
Liberia / Africa
Coastal infrastructure
The West Point revetment has an approved ESIA and March 2026 environmental permit; construction award, notice to proceed and physical start are not established / Confirmed
17 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The permit authorises the revetment within defined coordinates after ESIA approval. No works contractor, contract value, notice to proceed, or mobilisation record has yet been published.
Read controlling sourceThe proposal set the wider climate-resilience budget and the concept for a West Point revetment. That programme budget is not a construction contract, and the design still had to pass through permits, final drawings, procurement, and field delivery.
Read controlling sourceDelivery watch
Seek the public works solicitation or award, named contractor and consultant, executed value and quantities, final drawings and permit-condition matrix, notice to proceed, quarry and armourstone approvals, mobilisation, baseline shoreline survey, installed toe and armour records, boat-access and promenade interfaces, environmental and social monitoring, completion certificate, as-built documents and funded maintenance handover.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerUNDP's current project page controls the intervention purpose, institutional roles, project duration, met-ocean and safeguard achievements and the absence of a published works milestone. The 4 March 2026 permit controls authorization for the revetment inside specified UTM coordinates following ESIA approval. GCF controls FP160 status, financing and estimated completion. The approved funding proposal and stakeholder plan provide conceptual design and social-interface context, not final construction quantities or award evidence. The available evidence therefore places the project at approval rather than construction.
Phase: approval. Evidence reviewed: 17 July 2026.