World Bank contract record 1841608 names C. O. Williams Construction Limited at USD 8,482,143.17 for BB-BPI-462298-CW-DIR, the temporary emergency breakwater repairs at Bridgetown Fishing Harbour. The commercial identity is clear, but the public signing chronology is not: the contract description says 4 March 2025, the April implementation report says 14 March and works started, while STEP's structured contract field and later procurement plans show 21 June. By 18 November, the project team said the failed arm and corner had been rebuilt with salvaged dolos, filter rock and armour stone, while capping, the final crest, jetty work, access-road removal and navigation-light decisions remained. A May 2026 readiness exercise confirms facility use, not formal completion or owner acceptance.
Project signal
Construction in Barbados
Current statusC. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublishedSource confidenceConfirmed
Location
Barbados / Americas
Segment
Coastal infrastructure
Status
C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished / Confirmed
Last checked
7 August 2026
Coverage
Related sectors
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Government of Barbados through the Beryl Emergency Response and Recovery Project, with the Barbados Fisheries Division and project implementation team
Delivery parties
W.F. Baird & Associates - coastal engineer and construction support, C. O. Williams Construction Limited - named works contractor for BB-BPI-462298-CW-DIR
Contract route
Contract 1841608 in the World Bank award dataset identifies a Prior-review, Direct Selection works award to C. O. Williams Construction Limited for USD 8,482,143.17 under reference BB-BPI-462298-CW-DIR. STEP's procurement plan lists a USD 10 million estimate and Signed status. The award is associated with the USD 54 million Beryl Emergency Response and Recovery Project, but the public record does not reconcile the 4 March date embedded in the contract description, the 14 March date in the implementation report and STEP's 21 June structured signing date.
Execution window
The April 2025 implementation report says works had started after a 14 March signing, while the later STEP plan records a 21 June signed-contract field and a 29 June planned date. The November stakeholder meeting targeted the first week of December for completion but still recorded unfinished capping, an incomplete 4.1-metre crest, jetty replacement, access-road removal and a later navigation-light decision. No dated owner or engineer notice has confirmed that target as the accepted completion date.
Works package
Reconstruct the storm-damaged fisheries-marina breakwater within its original footprint using salvaged dolos at the arm and corner, graduated filter rock and imported armour stone, with double-layer protection around the head and transition to the trunk. The published construction record also identifies capping, a 4.1-metre final crest, jetty replacement, removal of the temporary access road and restoration of vessel turning space.
Marine interfaces
Quarry-to-island stone supply, inspection and digital mapping of armour units, underwater alignment, filter and armour grading, crest and cap completion, the surviving dolos interface, temporary construction access, jetty reinstatement, vessel turning space, navigation lighting and storm-season performance form one harbour-protection system.
Commercial evidence boundary
For the Fisheries Division package, the World Bank reports USD 8,482,143.17 against the procurement plan's USD 10 million estimate. Their difference establishes neither savings nor a final account. Physical repair was well advanced by November 2025, but payment, variation, final quantities, engineer-certified completion and owner acceptance remain unpublished. Operation Tempest in May 2026 confirms that vessels and staff used the complex during a readiness exercise; it does not close the works contract, reconcile the signing date or certify every navigation and jetty interface.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
World Bank contract record 1841608 reports the contractor, USD 8,482,143.17, Direct Selection and Prior review. Source
Procurement chronology
Contract signing
Named party
Barbados Port Inc. / World Bank STEP
Status
Reported
Source position
The contract description says 4 March 2025, the April implementation report says 14 March and works started, and the STEP structured field and later procurement plans show 21 June. The executed contract or a correcting owner notice has not been located. Source
Physical delivery
Breakwater arm, corner, filter and armour layers
Named party
C. O. Williams with Baird construction support
Status
Confirmed
Source position
Dated owner and lender updates document reconstruction, imported armour rock, underwater alignment and an advanced November 2025 work front with remaining crest, jetty, access-road and navigation-light items. Source
Completion and acceptance
As-built survey, defects, handover and final account
Named party
Owner, engineer and works contractor
Status
Not evidenced
Source position
Facility use is confirmed, but no cited official source contains an accepted as-built survey, completion certificate, defects close-out, owner handover or final account.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
World Bank award data confirmed C. O. Williams and USD 8.482 million
Contract record 1841608 fixes the contractor, amount, reference, Direct Selection route and Prior review. Its 21 June structured signing field conflicts with the 4 March date embedded in the description and the 14 March date in the April implementation report.
Fisheries reported operational-readiness use at the complex
Operation Tempest involved the Bridgetown Fisheries Complex and its administration in a 34-vessel readiness exercise. That demonstrates facility use and emergency coordination, not breakwater acceptance or contract close-out.
Project team described an advanced but unfinished breakwater
Baird reported the arm and corner rebuilt with salvaged dolos and described the filter and armour layers. Capping, the full crest, jetty replacement, access-road removal and the navigation-light decision remained open despite a first-week-of-December target.
Fisheries recorded armour stone securely placed at the head
The dated drone image documents armour placement at the breakwater head without providing an inspection, accepted as-built survey or handover certificate.
World Bank documented underwater placement and rock traceability
The feature records imported Norwegian armour rock, diver-guided alignment and geo-referenced placement. It supports the construction method and quality-control chain without establishing completion.
Implementation report recorded a 14 March signing and work start
This dated report confirms that works had started, but its signing date conflicts with both the 4 March date in the contract description and STEP's 21 June structured field.