Project record
Barbados Fisheries Division; official drone progress image taken 15 November 2025
The fisheries-marina repair contract was signed on 14 March 2025 and work began soon after. By 18 November, the project team said the failed arm and corner had been rebuilt with salvaged dolos, filter rock and armour stone, while capping, the final crest, jetty work, access-road removal and navigation-light decisions remained. The Fisheries Division recorded steady progress again on 15 November. A May 2026 readiness exercise confirms that the complex was in use. Final inspection, as-built acceptance and contract close-out have not been published by the owner or lender.
Barbados / Americas
Coastal infrastructure
Arm and head rebuilt; formal completion and owner acceptance not published / Confirmed
20 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Operation Tempest involved the Bridgetown Fisheries Complex and its administration in a 34-vessel readiness exercise. This establishes facility use and emergency coordination, not breakwater acceptance or contract close-out.
Read controlling sourceBaird reported the arm and corner rebuilt with salvaged dolos and described the filter and armour layers. Capping, the full crest, jetty replacement, access-road removal and the navigation-light decision remained open despite a first-week-of-December target.
Read controlling sourceThe dated drone image documents armour placement at the breakwater head without providing an inspection, accepted as-built survey or handover certificate.
Read controlling sourceThe feature records imported Norwegian armour rock, diver-guided alignment and geo-referenced placement. It supports the construction method and quality-control chain without establishing completion.
Read controlling sourceThe official anniversary update identifies a new breakwater under construction and dates its progress imagery to 24 June 2025.
Read controlling sourceThe World Bank implementation report records contract signing and work start. It does not give the contract price, detailed acceptance tests or final completion date.
Read controlling sourceDelivery watch
A dated owner, engineer or World Bank record confirming the final crest and cap, jetty and access-road close-out, navigation light and turning-space release, as-built survey, defects status, owner acceptance and post-construction condition.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerHurricane Beryl breached the existing protection in July 2024 and damaged more than 200 fishing vessels at the complex. The World Bank's April 2025 implementation report dates contract signing to 14 March and says work started. Fisheries material dated 1 July 2025 shows reconstruction in progress, and the World Bank's September feature describes imported Norwegian armour rock, underwater alignment and geo-referenced placement. The Fisheries Division's 2025 review says armour stone was securely placed at the head on 15 November. The updated stakeholder plan details a meeting three days later: the arm and corner had been rebuilt with salvaged dolos, filter and armour layers were in place, and capping, the full 4.1-metre crest, jetty replacement, access-road removal and the final navigation-light decision remained. A May 2026 exercise used the complex. The latest official updates do not include a completion certificate, accepted as-built survey or owner handover.
Phase: construction. Evidence reviewed: 20 July 2026.