Project record

Bridgetown Fisheries Complex breakwater repair

Dated overhead view of the Bridgetown Fisheries Complex breakwater showing new armour stone along the trunk and head on 15 November 2025

Barbados Fisheries Division; official drone progress image taken 15 November 2025

World Bank contract record 1841608 names C. O. Williams Construction Limited at USD 8,482,143.17 for BB-BPI-462298-CW-DIR, the temporary emergency breakwater repairs at Bridgetown Fishing Harbour. The commercial identity is clear, but the public signing chronology is not: the contract description says 4 March 2025, the April implementation report says 14 March and works started, while STEP's structured contract field and later procurement plans show 21 June. By 18 November, the project team said the failed arm and corner had been rebuilt with salvaged dolos, filter rock and armour stone, while capping, the final crest, jetty work, access-road removal and navigation-light decisions remained. A May 2026 readiness exercise confirms facility use, not formal completion or owner acceptance.

Project signal

Construction in Barbados

Current status C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished Source confidence Confirmed

Location

Barbados / Americas

Segment

Coastal infrastructure

Status

C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished / Confirmed

Last checked

7 August 2026

Coverage

Related sectors

Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Government of Barbados through the Beryl Emergency Response and Recovery Project, with the Barbados Fisheries Division and project implementation team
Delivery parties
W.F. Baird & Associates - coastal engineer and construction support, C. O. Williams Construction Limited - named works contractor for BB-BPI-462298-CW-DIR
Contract route
Contract 1841608 in the World Bank award dataset identifies a Prior-review, Direct Selection works award to C. O. Williams Construction Limited for USD 8,482,143.17 under reference BB-BPI-462298-CW-DIR. STEP's procurement plan lists a USD 10 million estimate and Signed status. The award is associated with the USD 54 million Beryl Emergency Response and Recovery Project, but the public record does not reconcile the 4 March date embedded in the contract description, the 14 March date in the implementation report and STEP's 21 June structured signing date.
Execution window
The April 2025 implementation report says works had started after a 14 March signing, while the later STEP plan records a 21 June signed-contract field and a 29 June planned date. The November stakeholder meeting targeted the first week of December for completion but still recorded unfinished capping, an incomplete 4.1-metre crest, jetty replacement, access-road removal and a later navigation-light decision. No dated owner or engineer notice has confirmed that target as the accepted completion date.
Works package
Reconstruct the storm-damaged fisheries-marina breakwater within its original footprint using salvaged dolos at the arm and corner, graduated filter rock and imported armour stone, with double-layer protection around the head and transition to the trunk. The published construction record also identifies capping, a 4.1-metre final crest, jetty replacement, removal of the temporary access road and restoration of vessel turning space.
Marine interfaces
Quarry-to-island stone supply, inspection and digital mapping of armour units, underwater alignment, filter and armour grading, crest and cap completion, the surviving dolos interface, temporary construction access, jetty reinstatement, vessel turning space, navigation lighting and storm-season performance form one harbour-protection system.
Commercial evidence boundary
For the Fisheries Division package, the World Bank reports USD 8,482,143.17 against the procurement plan's USD 10 million estimate. Their difference establishes neither savings nor a final account. Physical repair was well advanced by November 2025, but payment, variation, final quantities, engineer-certified completion and owner acceptance remain unpublished. Operation Tempest in May 2026 confirms that vessels and staff used the complex during a readiness exercise; it does not close the works contract, reconcile the signing date or certify every navigation and jetty interface.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Works contract

BB-BPI-462298-CW-DIR temporary emergency breakwater repairs

Named party
C. O. Williams Construction Limited
Status
Confirmed
Source position
World Bank contract record 1841608 reports the contractor, USD 8,482,143.17, Direct Selection and Prior review. Source
Procurement chronology

Contract signing

Named party
Barbados Port Inc. / World Bank STEP
Status
Reported
Source position
The contract description says 4 March 2025, the April implementation report says 14 March and works started, and the STEP structured field and later procurement plans show 21 June. The executed contract or a correcting owner notice has not been located. Source
Physical delivery

Breakwater arm, corner, filter and armour layers

Named party
C. O. Williams with Baird construction support
Status
Confirmed
Source position
Dated owner and lender updates document reconstruction, imported armour rock, underwater alignment and an advanced November 2025 work front with remaining crest, jetty, access-road and navigation-light items. Source
Completion and acceptance

As-built survey, defects, handover and final account

Named party
Owner, engineer and works contractor
Status
Not evidenced
Source position
Facility use is confirmed, but no cited official source contains an accepted as-built survey, completion certificate, defects close-out, owner handover or final account.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

World Bank award data confirmed C. O. Williams and USD 8.482 million

Contract record 1841608 fixes the contractor, amount, reference, Direct Selection route and Prior review. Its 21 June structured signing field conflicts with the 4 March date embedded in the description and the 14 March date in the April implementation report.

Source

Fisheries reported operational-readiness use at the complex

Operation Tempest involved the Bridgetown Fisheries Complex and its administration in a 34-vessel readiness exercise. That demonstrates facility use and emergency coordination, not breakwater acceptance or contract close-out.

Source

Project team described an advanced but unfinished breakwater

Baird reported the arm and corner rebuilt with salvaged dolos and described the filter and armour layers. Capping, the full crest, jetty replacement, access-road removal and the navigation-light decision remained open despite a first-week-of-December target.

Source

Fisheries recorded armour stone securely placed at the head

The dated drone image documents armour placement at the breakwater head without providing an inspection, accepted as-built survey or handover certificate.

Source

World Bank documented underwater placement and rock traceability

The feature records imported Norwegian armour rock, diver-guided alignment and geo-referenced placement. It supports the construction method and quality-control chain without establishing completion.

Source

Fisheries showed reconstruction under way one year after Beryl

The official anniversary update identifies a new breakwater under construction and dates its progress imagery to 24 June 2025.

Source

Implementation report recorded a 14 March signing and work start

This dated report confirms that works had started, but its signing date conflicts with both the 4 March date in the contract description and STEP's 21 June structured field.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Executed-contract or owner record reconciling 4 March, 14 March and 21 June 2025 signing dates
  • Final cap and 4.1-metre crest completion
  • Jetty replacement and removal of the temporary access road
  • Restored vessel turning space and harbour-master navigation-light decision
  • As-built armour geometry, underwater inspection and engineer certification
  • Owner acceptance, defects list, payment, variation and final-account close-out
  • Post-construction storm condition and maintenance responsibility
  • Any decision on a future fisheries harbour kept separate from this repair

Reporting status

Construction, confirmed confidence

Last checked 7 August 2026 across 11 cited sources. The dated timeline above carries the project events.

Last checked 7 August 2026 Cited sources 11