Project record

Glace Bay small craft harbour wharf reconstruction

Participation
Not assessed
Project facts checked

Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

Project sources

Zutphen Contractors received CAD 8,896,913.40 contract CW2454987 from Public Services and Procurement Canada on behalf of Fisheries and Oceans Canada for Glace Bay Small Craft Harbour. The package demolishes and reconstructs wharf structures D1 to D11, replacing mainly timber-crib structures with a steel H-pile-supported marginal wharf. CanadaBuys records a 2 June 2026 award and 31 March 2027 expiry. DFO's navigation filing independently identifies the marginal-wharf site at Renwick Brook, but neither source confirms site possession, pile-driving mobilisation, installed quantities or acceptance.

D1-D11 timber crib wharf demolition beside steel H-pile marginal wharf construction at an Atlantic Canadian fishing harbour

IMWO artist's impression of the published Glace Bay small craft harbour wharf reconstruction scope

Location

Canada / Americas

Segment

Fishing harbour wharf, dredging and shore protection

Phase

Award / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Fisheries and Oceans Canada, Small Craft Harbours, procured through Public Services and Procurement Canada
Delivery parties
Zutphen Contractors - prime contractor under CW2454987, Demolition, steel H-pile, structural steel, concrete, plant, survey, environmental and disposal lower tiers - not named in the cited public records
Contract route
PSPC ran open competitive solicitation WS5666301439 on DFO's behalf and selected the lowest-price bid. CanadaBuys records a 2 June 2026 award to Zutphen Contractors under contract CW2454987 at CAD 8,896,913.40. Published contract fields do not disclose bid ranking detail, priced quantities, subcontract awards or amendment history beyond the current total.
Execution window
CanadaBuys records a nine-month contract period from 2 June 2026 to 31 March 2027. These dates define the commercial window, not site mobilisation, first demolition, first pile, structural completion, harbour reopening or owner acceptance.
Works package
The package covers demolition and reconstruction of existing wharf structures D1 through D11. The replacement is described as a steel H-pile-supported marginal wharf replacing structures that are mainly timber cribs. Public records reviewed do not publish pile count or length, driving criteria, deck dimensions, concrete quantities, steel tonnage, fender and bollard scope, demolition quantities, disposal route or temporary-works design.
Marine interfaces
The work sits inside a core fishing harbour managed locally by the Harbour Authority of Glace Bay. Delivery must separate demolition, pile driving and wharf framing from fishing-vessel access and navigation at Renwick Brook. Critical open interfaces include construction-zone limits, temporary berthing, debris containment, pile-driving tolerances, weather exposure, survey control and staged return of structures D1-D11.
Commercial evidence boundary
CAD 8,896,913.40 is CanadaBuys' current total for CW2454987, not the harbour programme budget or final account. No public value split identifies demolition, piling, structural steel, deck, marine plant, disposal, navigation controls, survey or environmental work. Changes, certified progress, claims, retention and final quantities remain undisclosed.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Prime award

CW2454987 D1-D11 wharf reconstruction

Named party
Zutphen Contractors
Evidence status
Confirmed
Source position
CanadaBuys records the 2 June 2026 award, CAD 8,896,913.40 current total and 31 March 2027 expiry. Source
Wharf system

Timber-crib demolition and steel H-pile marginal wharf

Named party
Zutphen Contractors
Evidence status
Confirmed
Source position
The official contract description identifies structures D1-D11 and the change from mainly timber cribs to a steel H-pile-supported marginal wharf. Source
Navigation filing

Marginal wharf at Renwick Brook

Named party
DFO Small Craft Harbours
Evidence status
Confirmed
Source position
DFO's notice records Common Project Registry 13039 and NPP file 2025-214961 at approximately 46°11'43.41"N, 59°57'03.65"W. Source
Mobilisation and lower tiers

Demolition, piling, framing, deck and handover

Named party
Undisclosed delivery chain
Evidence status
Not evidenced
Source position
No cited public record names lower tiers or confirms site mobilisation, installed quantities, completion or acceptance.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Zutphen received the D1-D11 reconstruction award

The CAD 8.90 million contract places demolition and the new steel H-pile marginal wharf under one named prime through March 2027, without proving a physical start.

Source

DFO posted the marginal-wharf navigation filing

The filing fixed the project-registry identity and Renwick Brook location; it did not establish final approval, contractor selection or construction.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Site possession, notice to proceed and first demolition
  • D1-D11 sequence and temporary fishing-harbour access
  • Steel H-pile count, length, driving criteria and acceptance
  • Structural steel, deck, fender and bollard quantities
  • Timber-crib demolition, debris containment and disposal route
  • Named piling, steel, concrete, survey and marine-plant lower tiers
  • As-built survey, structural acceptance and harbour reopening
  • Contract amendments, certified progress and final account

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
8 August 2026
Cited sources
4

Sources and related records