USACE Wilmington awarded Cape Romain Contractors USD 7,015,897.42 to stabilize eroding banks along Snow's Cut, the Atlantic Intracoastal Waterway link between the Cape Fear River and Myrtle Grove Sound. Work is expected to begin in the coming months. The award notice does not state which of the four previously identified reaches, or how much of the earlier 7,100-foot maximum, sits in the signed package.
Project signal
Award in United States
Current statusUSD 7.016 million contract awarded; mobilization and the awarded reach split remain unpublishedSource confidenceConfirmed
Location
United States / Americas
Segment
Coastal infrastructure
Status
USD 7.016 million contract awarded; mobilization and the awarded reach split remain unpublished / Confirmed
Last checked
21 July 2026
Coverage
Related sectors
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Wilmington District
Delivery parties
Cape Romain Contractors, Inc. - shoreline stabilization contractor
Contract route
USACE solicitation W912PM26BA001 was issued as a total small-business set-aside. The earlier notice described a firm-fixed-price construction contract; the 20 July release confirms Cape Romain and the USD 7,015,897.42 award.
Execution window
USACE says work is expected to begin in the coming months. A notice-to-proceed date, construction duration and completion date were not included in the award release.
Works package
Targeted bank stabilization along Snow's Cut. The planning and procurement record contemplated up to 7,100 feet across four areas west of the US 421 bridge, using bank clearing and grading, riprap and other erosion-protection measures, with breakwater or wave-attenuation concepts considered for some locations. The signed reach and quantity schedule is not public.
Marine interfaces
A live AIWW navigation channel, vessel wakes, tides and currents, eroded escarpments, shoreline toe and filter performance, rock delivery, land or barge access, nearby parkland, public access, wetlands and post-work channel clearance
Commercial evidence boundary
The award turns a long-running erosion study into named contractor workload, but it does not close the package boundary. The USD 7.016 million award is below the presolicitation's USD 10-25 million magnitude range; without the bid schedule, that difference cannot be translated into fewer reaches, less shoreline or a particular design change.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
USACE awarded the bank-stabilization contract to Cape Romain
The USD 7,015,897.42 award establishes the contractor and commercial event. Mobilization, the reach split, quantities and completion date remain unpublished.
The total small-business set-aside set a 9 July offer deadline under notice W912PM26BA001. The public SAM.gov screen did not carry the drawings or bid schedule.
The environmental record moved to a final EA and FONSI
USACE's index lists the final Snow's Cut EA and FONSI in April 2026. The earlier public EA maps four initial reaches and describes riprap, grading, vegetation and wave-attenuation alternatives.