Project record

Winterton small craft harbour wharf reconstruction

Official Winterton new-site plan showing the timber crib finger pier, concrete deck, dredging limits, slipway and paved approach

Fisheries and Oceans Canada / Fudge, Perrett & Pearce; official C2-00220 drawing C3 of 7, issued for final review in February 2020 and included in the 2021 bid package

Maher's Contracting Limited received contract F6140-210681/001/PWD from Public Services and Procurement Canada for Fisheries and Oceans Canada's Winterton wharf reconstruction on 22 October 2021. The official package called for demolition of the existing crib-and-span finger pier; a new treated-timber crib finger pier with reinforced-concrete deck; 275 cubic metres of Class B dredging to -2.0 metres LNT; slipway-anchor cribs; approach, electrical and culvert work; and 60 cleats and mooring rings. CanadaBuys records an initial CAD 2,616,163.75 award and a CAD 143,750 amendment, reaching CAD 2,759,914. The 2023-24 Public Accounts separately report CAD 2,399,925 amount contracted, CAD 2,399,651 spent to date and the federal completion marker.

Project signal

Completed in Canada

Current status Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed Source confidence Confirmed

Location

Canada / Americas

Segment

Fishing harbour wharf, dredging and shore protection

Status

Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed / Confirmed

Last checked

13 August 2026

Coverage

Related sectors

Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Fisheries and Oceans Canada - Small Craft Harbours, procured through Public Services and Procurement Canada
Delivery parties
Maher's Contracting Limited - construction prime under F6140-210681/001/PWD, Dredging, timber, concrete, electrical, survey, testing, marine-plant and material-supply lower tiers - not named in the cited public records
Contract route
PSPC published F6140-210681/A under the Canadian Free Trade Agreement as an open, lowest-price construction competition for DFO. CanadaBuys records award to Maher's on 22 October 2021, followed by amendment 001 on 7 November 2022 and amendment 002 on 15 November 2022. The original contract-history record shows a rounded CAD 2,616,164 tax-inclusive value; amendment 001 adds CAD 143,750, while amendment 002 carries the cumulative CAD 2,759,914 value and extends expiry to 10 February 2023.
Execution window
Bidders were required to complete the work within 56 weeks of acceptance. CanadaBuys later records contract expiry extended from 18 November 2022 to 10 February 2023. Public Accounts for the fiscal year ended 31 March 2024 applies note f, defined by the Receiver General as contract completed; no cited record gives the exact substantial-completion, acceptance or return-to-service date.
Works package
The bid schedule quantifies 781 square metres of reinforced-concrete deck, 28 square metres of precast panels, 3,950 cubic metres of rock-ballasted treated-timber cribwork, 40 cubic metres of concrete-ballasted cribwork, 50 cubic metres of rockfill, 75 cubic metres of Class A and B fill, 30 cubic metres of scour protection, 275 cubic metres of Class B dredging, 80 square metres of asphalt, 17 ladders, 10 Type A cleats, 16 Type B1 cleats and 34 mooring rings. The general scope also includes full finger-pier demolition, crib scribing to hard bottom, slipway extension, electrical upgrades, approach regrading, culvert protection and armour-stone reinstatement.
Marine interfaces
The package couples demolition in an operating fishing-harbour footprint with dredging to -2.0 metres LNT, timber cribs founded and scribed on hard bottom, rock and concrete ballast, a reinforced-concrete working deck, slipway anchor cribs and a dense mooring-and-ladder schedule. Delivery depended on floating plant, pre- and post-dredge surveys, electronic sweeping, controlled work beside retained community-stage and slipway assets, tidal planning and temporary support or diversion at the culvert interface.
Commercial evidence boundary
The CanadaBuys award notice gives CAD 2,616,163.75, exactly 1.15 times the initial CAD 2,274,925 Public Accounts amount. Amendment 001 adds CAD 143,750, exactly 1.15 times CAD 125,000; amendment 002 reports the resulting CAD 2,759,914 cumulative contract value, while Public Accounts later show CAD 2,399,925 amount contracted. This arithmetic is consistent with CanadaBuys including 15% HST and Public Accounts excluding it, but neither ledger should be relabelled beyond its official headings or added to the other. The CAD 274 difference between amount contracted and expenditure to date is not evidence of an open construction contract because the same official row marks the contract completed, but it does leave the final financial reconciliation unpublished.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Construction prime

F6140-210681/001/PWD

Named party
Maher's Contracting Limited
Status
Confirmed
Source position
CanadaBuys records the 22 October 2021 award, initial CAD 2,616,163.75 tax-inclusive value and lowest-price procedure. Source
Wharf and dredging scope

Timber cribs, deck, dredging, slipway, mooring and electrical works

Named party
DFO, PSPC and Maher's Contracting
Status
Confirmed
Source position
The official bid package fixes the 56-week term, quantified work schedule and detailed construction drawings. Source
Contract amendments

Amendments 001 and 002

Named party
PSPC and Maher's Contracting
Status
Confirmed
Source position
CanadaBuys records a CAD 143,750 amendment on 7 November 2022 and cumulative CAD 2,759,914 value with expiry extended to 10 February 2023 on amendment 002. Source
Completion and expenditure

Federal Public Accounts ledger

Named party
Fisheries and Oceans Canada and Maher's Contracting
Status
Confirmed
Source position
The 2023-24 Public Accounts list CAD 2,399,925 amount contracted, CAD 2,399,651 spent to date and note f, defined as contract completed. Source
Lower-tier supply chain

Dredging, timber, concrete, electrical, survey and marine plant

Named party
Undisclosed subcontractors and suppliers
Status
Undisclosed
Source position
The reviewed official records identify the prime and work packages but no named lower tiers.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Public Accounts marked the Winterton contract completed

The federal ledger closes the contract-status gap and reports CAD 2,399,651 expenditure to date against its CAD 2,399,925 amount-contracted field.

Source

Amendment 002 carried the cumulative CAD 2.76m value

The second amendment records the cumulative CAD 2,759,914 contract value and extends the published expiry from 18 November 2022 to 10 February 2023.

Source

Amendment 001 added CAD 143,750

The published amendment adds CAD 143,750; this is exactly 1.15 times the CAD 125,000 increase visible between annual Public Accounts amount-contracted fields, but the change scope remains undisclosed.

Source

Maher's received the integrated reconstruction award

The award placed finger-pier demolition, timber-crib reconstruction, concrete deck, dredging, slipway, mooring and electrical works under Maher's as the integrated prime contractor.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Completion and owner acceptance certificates
  • Accepted 275 m3 dredged quantity and -2.0 m LNT survey
  • As-built timber-crib, concrete-deck and slipway-anchor records
  • Mooring, ladder and electrical commissioning
  • Harbour reopening and defects closeout
  • Reasons for amendments 001 and 002
  • Named dredging, timber, concrete, electrical and marine-plant lower tiers
  • Final expenditure reconciliation against CAD 2,399,925 amount contracted

Reporting status

Completed, confirmed confidence

Last checked 13 August 2026 across 7 cited sources. The dated timeline above carries the project events.

Last checked 13 August 2026 Cited sources 7