Contract Completion
Winterton wharf contract is marked complete in Public Accounts
Maher's Contracting's Winterton award grew from CAD 2,616,163.75 to CAD 2,759,914 in CanadaBuys. The federal Public Accounts separately present CAD 2,399,925 as amount contracted, mark the contract completed in 2023-24 and report CAD 2,399,651 spent to date. The exact 1.15 ratio is consistent with HST treatment; the values describe one contract, not two funding streams.
The federal completion marker closes the status gap
CanadaBuys reports the displayed award and amendment values and dates. The official bid package defines the quantified scope and 56-week term. Public Accounts lists the amount contracted, expenditures and completed-contract marker. The exact 1.15 ratio is an arithmetic reconciliation consistent with HST; Public Accounts does not label it as tax, and the ledgers are reconciled rather than added.
Separate federal ledgers describe the same contract
The same wharf appears in an award notice, two amendment pages and annual Public Accounts. Their headline amounts differ because the ledgers use different reporting bases. The initial CanadaBuys award is exactly 1.15 times the initial CAD 2,274,925 Public Accounts amount; amendment 001 is exactly 1.15 times the CAD 125,000 increase; and CAD 2,399,925 maps to CAD 2,759,913.75, rounded by CanadaBuys to CAD 2,759,914. This relationship is consistent with 15% HST treatment, although Public Accounts labels the column only Amount Contracted. The reconciliation describes one contract and prevents the values being counted twice.
Evidence conclusion
Physical quantities remain distinct from contract completion
The 2023-24 Receiver General table defines note f as contract completed, so Winterton can move to completed with confirmed confidence. That does not establish every tender quantity as installed or accepted. The bid schedule fixes the tender baseline at 781 m2 concrete deck, 3,950 m3 rock-ballasted timber cribwork, 275 m3 Class B dredging, 17 ladders and 60 mooring devices. The decisive remaining evidence is final bathymetry, accepted quantities, as-built records, commissioning, amendment reasons, lower-tier assignments and the CAD 274 expenditure difference.
Outstanding evidence
- Owner completion and acceptance certificates
- Final bathymetry and accepted 275 m3 dredged quantity
- As-built timber-crib and reinforced-concrete deck records
- Mooring, ladder, slipway and electrical acceptance
- Harbour reopening and defects closeout
- Reasons for the two 2022 contract amendments
- Named dredging, timber, concrete and marine-plant lower tiers
- CAD 274 final expenditure reconciliation
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- F6140-210681/001/PWD award notice CanadaBuys / Government of Canada, Awarded 22 October 2021
- F6140-210681/001/PWD amendment 001 CanadaBuys / Government of Canada, 7 November 2022
- F6140-210681/001/PWD amendment 002 CanadaBuys / Government of Canada, 15 November 2022
- F6140-210681 official specifications and drawings Fisheries and Oceans Canada / PSPC via CanadaBuys, Published 13 September 2021
- Public Accounts of Canada 2022-23, Volume III Section 4 Receiver General for Canada / PSPC, Fiscal year ended 31 March 2023
- Public Accounts of Canada 2023-24, Volume III Section 4 Receiver General for Canada / PSPC, Fiscal year ended 31 March 2024