Nanumaga and Nanumea climate-resilient small-boat harbors

Aerial visualization of the Nanumaga and Nanumea workboat harbor programme, showing a Tuvalu reef channel, armour breakwaters, wharf, ramp and cargo shed

IMWO artist's impression of the published Nanumaga and Nanumea climate-resilient small-boat harbors scope

Contract 1850494 records Hall Civil Contracting Pty Ltd as the supplier for TV-MPWIELMD-360039-CW-RFP, covering design and construction of small-boat harbors at Nanumaga and Nanumea. Hall Civil's signature followed on 21 July 2025 for USD 62,551,749.20. A June 2025 mission set target completion dates by island, while actual mobilisation, design approval and field progress after signature remain unverified.

Project signal

Award in Tuvalu

Current status Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress Source confidence Confirmed

Location

Tuvalu / Global islands

Segment

Ports and coastal protection

Status

Hall Civil Contracting signed the USD 62.552 million design-build contract on 21 July 2025; the latest cited mission set August 2027 and January 2028 completion targets for Nanumaga and Nanumea, but no cited source confirms physical mobilisation or current progress / Confirmed

Last checked

5 August 2026

Coverage

Related sectors

Ports and coastal protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Government of Tuvalu under the World Bank-financed Maritime Investment in Climate Resilient Operations II project
Delivery parties
Hall Civil Contracting Pty Ltd - design-build contractor under TV-MPWIELMD-360039-CW-RFP, Nanumaga and Nanumea harbor supervision consultant - separate contract reported signed on 19 June 2025; firm name not identified in the cited mission text, Marine survey, dredging, armour-rock, concrete, building, utility and local logistics subcontractors - not identified in the cited award record
Contract route
Contract 1850494 identifies a prior-review Request for Proposals for works and records the 21 July 2025 signature. The June 2025 aide-memoire describes a sole-bidder negotiation process and reports negotiated island pricing before contingency and withholding tax. Those negotiation figures are not final island contract allocations in the supplier API.
Execution window
The June 2025 mission table set August 2027 as Nanumaga's estimated completion and January 2028 as Nanumea's. The current World Bank project API lists 31 July 2029 as the programme closing date. Neither date proves current design, mobilisation, construction or acceptance status.
Works package
The project API describes Nanumaga as a new safe harbor for a 10 m workboat with cargo and passenger areas and an upgraded access road. Nanumea covers extension of existing harbor facilities with passenger holding, cargo storage, additional berthing for local fishing boats and road upgrades. The wider programme contemplates reef channels, turning basins, breakwaters, jetties, small wharves, ramps, navigation aids and coastal protection, but the exact contract schedule is not public in the cited award record.
Marine interfaces
Design and construction must resolve reef-channel geometry, wave penetration, workboat manoeuvring, breakwater armour, berth and ramp levels, imported materials, utility links, local access and inter-island logistics. Separate island surveys, environmental controls, weather windows, material sources and acceptance tests are required; the signed award alone does not allocate them.
Commercial evidence boundary
The USD 62.552 million committed supplier amount is the combined two-island contract value. The aide-memoire's island estimates exclude contingency and withholding tax and should not be used as a final contract split. Additional-financing needs and the separate Nukufetau funding gap do not belong to this award value.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Hall Civil signed the two-island design-build contract

Contract 1850494 reports USD 62,551,749.20 for small-boat harbor design and construction at Nanumaga and Nanumea under one Hall Civil award.

Source

Mission set separate island completion targets

The aide-memoire expected award by 31 July and listed August 2027 for Nanumaga and January 2028 for Nanumea, while flagging low contingency and imported-material cost risk.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Island-specific design approvals and construction notices
  • Nanumaga and Nanumea mobilisation dates and progress baselines
  • Supervision consultant identity and resident-engineer mobilisation
  • Reef-channel, turning-basin and breakwater design outcomes
  • Imported fill, armour rock, concrete and inter-island logistics
  • Dredging, survey, navigation-aid and local subcontractors
  • Updated August 2027 and January 2028 completion targets
  • Commissioning, acceptance and climate-resilience performance

Reporting status

Award, confirmed confidence

Last checked 5 August 2026 across 5 cited sources. The dated timeline above carries the project events.