Jurien Bay's proposed entrance reconfiguration adds 170 metres to the northern breakwater to divert seagrass wrack before it enters the harbour. The transport department's 17 August 2026 position places the structural works in detailed design and confirms maintenance dredging completed in April. Construction procurement and a measured operating benefit remain ahead.
Ports and coastal protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Department of Transport and Major Infrastructure, Western Australia
Delivery parties
Construction contractor - not named in the cited August 2026 position, Design delivery - in progress; external designer not identified in the cited records
Contract route
Construction request for tenders was to follow detailed design in the 17 August 2026 update. The 2024 announcement's expectation of design and construction awards in 2025 is an earlier programme statement; the cited August position names no construction award.
Execution window
April 2026 maintenance dredging is reported complete. A September 2025 parliamentary answer expected detailed design by the end of 2025, while the August 2026 update still describes design in progress. No revised construction start or completion date is provided.
Works package
A proposed 170m extension to the northern breakwater forms a spur groyne. The concept uses truck-delivered rock and earthmoving plant; final rock quantities, contract packaging and tender price are absent from the cited historical record.
Marine interfaces
Wrack decomposition reduces oxygen and can cause odour and fish kills. Entrance geometry is intended to redirect incoming material, with possible periodic accumulation on the northern beach. Harbour access, beach management and future maintenance therefore remain linked.
Commercial evidence boundary
The May 2024 release announced AUD 17.5 million; the September 2025 parliamentary answer stated an approved budget of AUD 17.047 million. The documents disclose no reconciliation between those figures or August 2026 contract value. Local rock and contractor opportunities were anticipated in the 2024 announcement, without named awarded lower tiers.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
Entrance design
170m northern breakwater extension
Named party
Transport WA
Evidence status
Confirmed
Source position
The 17 August 2026 update describes detailed design in progress and a construction tender to follow. Source
Maintenance
Harbour navigation and water-quality dredging
Named party
Transport WA
Evidence status
Confirmed
Source position
The owner reports the most recent maintenance dredging campaign completed in April 2026. Source
Performance
Wrack diversion and seasonal water quality
Named party
Transport WA
Evidence status
Reported
Source position
Approximately 80% diversion is a modelling result; the cited records contain no built-structure performance measurements. Source
Evidence gap
What remains unverified
Outstanding evidence
Construction tender, rock quantities and access arrangements
Updated design programme and current cost baseline
Northern-beach wrack management responsibilities
Post-construction wrack, oxygen and maintenance monitoring