Project record

Gorée Island east and west coastal protection works

Aerial overview of Gorée Island showing its exposed shoreline, dense heritage fabric, landing area, and surrounding Atlantic water

Ji-Elle via Wikimedia Commons, public domain

Gorée's active WACA ResIP package combines rock-armour protection, dike and breakwater work, wall and embankment stabilization, and heritage-compatible landscaping. WACA reported 82% overall completion as of 31 March 2026. The later World Bank project paper dated 25 June uses a different boundary: 85% for protection works and 75% when landscaping is included, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Neither statement is owner-acceptance evidence.

Project signal

Construction in Senegal

Read progress by dated source and measurement boundary. The 82% WACA baseline, the later 85% protection-only figure, and the 75% figure including landscaping are not interchangeable. Remaining decisions concern financing approval and effectiveness, contract amendments, rock supply and sea-state workability, UNESCO validation, physical close-out, environmental and archaeological controls, and owner handover.

Current status Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed Source confidence Confirmed

Location

Senegal / Africa

Segment

Coastal infrastructure

Status

Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed / Confirmed

Evidence reviewed

16 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Government of Senegal through the WACA ResIP Senegal implementing structure
Delivery parties
NGE Contracting - coastal protection works, NORDA STELO-IDEV joint venture - works supervision and control
Contract route
World Bank investment project financing. The 25 June 2026 project paper seeks EUR 3.5 million in additional IDA credit for cost overruns and a 12-month extension, with no change to the project development objective or core scope.
Execution window
The July 2025 implementation memo gives three source-specific start references: Lot 2 began in February 2025 for 15 months, physical works began in March, and the execution-study and work-start milestone was recorded as achieved on 8 May. WACA then reported 82% overall completion at 31 March 2026 and expected 30 June delivery. The later 25 June project paper seeks a 30 June 2027 close and reports 85% protection works or 75% including landscaping.
Works package
The July 2025 mission defines approximately 1.275 kilometres of lowered and widened rock-armour protection at +3.1 m CM around the island's low-lying edge. WACA's March 2026 baseline describes 390-metre eastern and 900-metre western work fronts. The June 2026 project paper describes eastern and western dike segments, six riprap breakwaters, the Mariama Bâ school wall, mosque-slope stabilization, landscaping, promenade work, and market-stand support.
Marine interfaces
Repeated strong swells and storms, quarry-to-island rock supply through Dakar's Pier 8, shoreline and foundation conditions, six-breakwater and dike geometry, public beach access, the school and mosque interfaces, submerged archaeology, UNESCO validation, environmental monitoring, landscaping, and maintenance handover form one coastal delivery system.
Commercial read
The additional-financing paper seeks EUR 3.5 million (US$4.0 million equivalent) for existing Components 2, 3, and 4; it is not a new coastal-works award. The June paper says seven months of early rock-supply delay were resolved, but rough-sea stoppages, new wall and embankment risks, heritage validation, landscaping, and cost escalation still require a revised programme. Approval and effectiveness have not been independently confirmed.
Next milestone
Track approval and effectiveness of the proposed credit, contract amendments, the revised closing date, eastern and western dike and breakwater completion, the 105-metre school-side extension and wall, mosque-slope stabilization, UNESCO validation, promenade and landscaping, environmental and archaeological close-out, as-built records, owner acceptance, and maintenance handover.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

World Bank paper reset the completion boundary and sought additional credit

The paper reports 85% completion for protection works and 75% when landscaping is included, then seeks EUR 3.5 million in additional IDA credit and a 30 June 2027 close. It remains a financing proposal and completion plan, not acceptance evidence.

Read controlling source

WACA recorded an 82% overall field baseline

WACA reported the 390-metre eastern work front nearly complete and the 900-metre western work front at 82%, with a 30 June 2026 delivery expectation. The later financing paper supersedes that schedule expectation without proving handover.

Read controlling source

Implementation mission named the delivery team and measured 15% execution

The World Bank mission identified NGE Contracting, NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, Pier 8 supply constraints, and active environmental and archaeological controls. Physical progress was estimated at 15%.

Read controlling source

Execution studies and the work-start milestone were recorded as achieved

The July mission memo records the execution-study and work-start action as achieved on 8 May. The same memo separately states that Lot 2 began in February for 15 months and physical works began in March, so the date is a formal milestone rather than a single universal mobilization date.

Read controlling source

World Bank approved the Senegal WACA ResIP financing baseline

Approval established the investment-finance programme that later funded the Gorée package. It does not identify the later works contract or establish any construction output by itself.

Read controlling source

Delivery watch

Evidence needed next

Track approval and effectiveness of the proposed credit, contract amendments, the revised closing date, eastern and western dike and breakwater completion, the 105-metre school-side extension and wall, mosque-slope stabilization, UNESCO validation, promenade and landscaping, environmental and archaeological close-out, as-built records, owner acceptance, and maintenance handover.

Decision watchpoints

  • Additional-credit approval, effectiveness, contract amendments, and revised closing date
  • NGE programme, remaining quantities, cost allocation, and Dakar Pier 8 rock stocks
  • Sea-state work windows and two-front construction plan
  • Eastern and western dike segments, six breakwaters, and accepted coastal geometry
  • Mariama Bâ school wall and mosque-slope stabilization
  • UNESCO validation, promenade, landscaping, beach access, and market-stand interfaces
  • Environmental, archaeological, grievance, safety, and social close-out
  • As-built evidence, owner acceptance, post-storm condition, and maintenance handover

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 16 July 2026 Sources in this record 6

Source record

The record preserves source chronology instead of manufacturing one percentage. The July 2025 World Bank mission names NGE Contracting and NORDA STELO-IDEV, defines a 1.275-kilometre rock-armour line, reports 15% execution, and documents Pier 8 logistics, environmental baselines, and preventive underwater archaeology. WACA's June 2026 article reports an 82% overall baseline at 31 March, with a 390-metre eastern work front nearly complete and a 900-metre western work front at 82%. The later 25 June project paper reports 85% for protection works and 75% including landscaping, identifies rough seas, a seven-month rock-supply delay, the school-wall collapse, mosque-slope instability, and UNESCO validation, and seeks EUR 3.5 million plus a 30 June 2027 close. These figures use different dates and scope boundaries and are not evidence of accepted completion.

Phase: construction. Evidence reviewed: 16 July 2026.

Project sources 6