Project record
Gorée's active WACA ResIP package combines rock-armour protection, dike and breakwater work, wall and embankment stabilization, and heritage-compatible landscaping. WACA reported 82% overall completion as of 31 March 2026. The later World Bank project paper dated 25 June uses a different boundary: 85% for protection works and 75% when landscaping is included, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Neither statement is owner-acceptance evidence.
Senegal / Africa
Coastal infrastructure
Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed / Confirmed
16 July 2026
Coverage
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe paper reports 85% completion for protection works and 75% when landscaping is included, then seeks EUR 3.5 million in additional IDA credit and a 30 June 2027 close. It remains a financing proposal and completion plan, not acceptance evidence.
SourceWACA reported the 390-metre eastern work front nearly complete and the 900-metre western work front at 82%, with a 30 June 2026 delivery expectation. The later financing paper supersedes that schedule expectation without proving handover.
SourceThe World Bank mission identified NGE Contracting, NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, Pier 8 supply constraints, and active environmental and archaeological controls. Physical progress was estimated at 15%.
SourceThe July mission memo records the execution-study and work-start action as achieved on 8 May. The same memo separately states that Lot 2 began in February for 15 months and physical works began in March, so the date is a formal milestone rather than a single universal mobilization date.
SourceApproval established the investment-finance programme that later funded the Gorée package. It does not identify the later works contract or establish any construction output by itself.
SourceEvidence gap