Project record

Gorée Island east and west coastal protection works

Aerial overview of Gorée Island showing its exposed shoreline, dense heritage fabric, landing area, and surrounding Atlantic water

Ji-Elle via Wikimedia Commons, public domain

Gorée's active WACA ResIP package combines rock-armour protection, dike and breakwater work, wall and embankment stabilization, and heritage-compatible landscaping. WACA reported 82% overall completion as of 31 March 2026. The later World Bank project paper dated 25 June uses a different boundary: 85% for protection works and 75% when landscaping is included, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Neither statement is owner-acceptance evidence.

Project signal

Construction in Senegal

Current status Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed Source confidence Confirmed

Location

Senegal / Africa

Segment

Coastal infrastructure

Status

Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed / Confirmed

Last checked

16 July 2026

Coverage

Related sectors

Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Government of Senegal through the WACA ResIP Senegal implementing structure
Delivery parties
NGE Contracting - coastal protection works, NORDA STELO-IDEV joint venture - works supervision and control
Contract route
World Bank investment project financing. The 25 June 2026 project paper seeks EUR 3.5 million in additional IDA credit for cost overruns and a 12-month extension, with no change to the project development objective or core scope.
Execution window
The July 2025 implementation memo gives three source-specific start references: Lot 2 began in February 2025 for 15 months, physical works began in March, and the execution-study and work-start milestone was recorded as achieved on 8 May. WACA then reported 82% overall completion at 31 March 2026 and expected 30 June delivery. The later 25 June project paper seeks a 30 June 2027 close and reports 85% protection works or 75% including landscaping.
Works package
The July 2025 mission defines approximately 1.275 kilometres of lowered and widened rock-armour protection at +3.1 m CM around the island's low-lying edge. WACA's March 2026 baseline describes 390-metre eastern and 900-metre western work fronts. The June 2026 project paper describes eastern and western dike segments, six riprap breakwaters, the Mariama Bâ school wall, mosque-slope stabilization, landscaping, promenade work, and market-stand support.
Marine interfaces
Repeated strong swells and storms, quarry-to-island rock supply through Dakar's Pier 8, shoreline and foundation conditions, six-breakwater and dike geometry, public beach access, the school and mosque interfaces, submerged archaeology, UNESCO validation, environmental monitoring, landscaping, and maintenance handover form one coastal delivery system.
Commercial evidence boundary
The additional-financing paper seeks EUR 3.5 million (US$4.0 million equivalent) for existing Components 2, 3, and 4; it is not a new coastal-works award. The June paper says seven months of early rock-supply delay were resolved, but rough-sea stoppages, new wall and embankment risks, heritage validation, landscaping, and cost escalation still require a revised programme. Approval and effectiveness have not been independently confirmed.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

World Bank paper reset the completion boundary and sought additional credit

The paper reports 85% completion for protection works and 75% when landscaping is included, then seeks EUR 3.5 million in additional IDA credit and a 30 June 2027 close. It remains a financing proposal and completion plan, not acceptance evidence.

Source

WACA recorded an 82% overall field baseline

WACA reported the 390-metre eastern work front nearly complete and the 900-metre western work front at 82%, with a 30 June 2026 delivery expectation. The later financing paper supersedes that schedule expectation without proving handover.

Source

Implementation mission named the delivery team and measured 15% execution

The World Bank mission identified NGE Contracting, NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, Pier 8 supply constraints, and active environmental and archaeological controls. Physical progress was estimated at 15%.

Source

Execution studies and the work-start milestone were recorded as achieved

The July mission memo records the execution-study and work-start action as achieved on 8 May. The same memo separately states that Lot 2 began in February for 15 months and physical works began in March, so the date is a formal milestone rather than a single universal mobilization date.

Source

World Bank approved the Senegal WACA ResIP financing baseline

Approval established the investment-finance programme that later funded the Gorée package. It does not identify the later works contract or establish any construction output by itself.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Additional-credit approval, effectiveness, contract amendments, and revised closing date
  • NGE programme, remaining quantities, cost allocation, and Dakar Pier 8 rock stocks
  • Sea-state work windows and two-front construction plan
  • Eastern and western dike segments, six breakwaters, and accepted coastal geometry
  • Mariama Bâ school wall and mosque-slope stabilization
  • UNESCO validation, promenade, landscaping, beach access, and market-stand interfaces
  • Environmental, archaeological, grievance, safety, and social close-out
  • As-built evidence, owner acceptance, post-storm condition, and maintenance handover

Reporting status

Construction, confirmed confidence

Last checked 16 July 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 16 July 2026 Cited sources 6

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 6