Location
Senegal / Africa
Project record
Gorée's active WACA ResIP package combines rock-armour protection, dike and breakwater work, wall and embankment stabilization, and heritage-compatible landscaping. WACA reported 82% overall completion as of 31 March 2026. The later World Bank project paper dated 25 June uses a different boundary: 85% for protection works and 75% when landscaping is included, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Neither statement is owner-acceptance evidence.
Senegal / Africa
Coastal infrastructure
Works active; EUR 3.5 million additional credit and a 30 June 2027 close are proposed / Confirmed
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The paper reports 85% completion for protection works and 75% when landscaping is included, then seeks EUR 3.5 million in additional IDA credit and a 30 June 2027 close. It remains a financing proposal and completion plan, not acceptance evidence.
Read controlling sourceWACA reported the 390-metre eastern work front nearly complete and the 900-metre western work front at 82%, with a 30 June 2026 delivery expectation. The later financing paper supersedes that schedule expectation without proving handover.
Read controlling sourceThe World Bank mission identified NGE Contracting, NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, Pier 8 supply constraints, and active environmental and archaeological controls. Physical progress was estimated at 15%.
Read controlling sourceThe July mission memo records the execution-study and work-start action as achieved on 8 May. The same memo separately states that Lot 2 began in February for 15 months and physical works began in March, so the date is a formal milestone rather than a single universal mobilization date.
Read controlling sourceApproval established the investment-finance programme that later funded the Gorée package. It does not identify the later works contract or establish any construction output by itself.
Read controlling sourceDelivery watch
Track approval and effectiveness of the proposed credit, contract amendments, the revised closing date, eastern and western dike and breakwater completion, the 105-metre school-side extension and wall, mosque-slope stabilization, UNESCO validation, promenade and landscaping, environmental and archaeological close-out, as-built records, owner acceptance, and maintenance handover.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe record preserves source chronology instead of manufacturing one percentage. The July 2025 World Bank mission names NGE Contracting and NORDA STELO-IDEV, defines a 1.275-kilometre rock-armour line, reports 15% execution, and documents Pier 8 logistics, environmental baselines, and preventive underwater archaeology. WACA's June 2026 article reports an 82% overall baseline at 31 March, with a 390-metre eastern work front nearly complete and a 900-metre western work front at 82%. The later 25 June project paper reports 85% for protection works and 75% including landscaping, identifies rough seas, a seven-month rock-supply delay, the school-wall collapse, mosque-slope instability, and UNESCO validation, and seeks EUR 3.5 million plus a 30 June 2027 close. These figures use different dates and scope boundaries and are not evidence of accepted completion.
Phase: construction. Evidence reviewed: 16 July 2026.