Coastal Delivery
Gorée reports 85% completion, with finance and handover still unresolved
WACA measured Gorée at 82% overall on 31 March 2026. A later World Bank paper uses a narrower and newer boundary: 85% for protection works and 75% including landscaping, while seeking EUR 3.5 million (US$4.0 million equivalent) and a 30 June 2027 close. Owner acceptance has not been reported.
Published scope and current milestone
The July 2025 World Bank implementation mission identifies NGE Contracting and NORDA STELO-IDEV, approximately 1.275 kilometres of rock-armour protection, 15% execution, Dakar Pier 8 logistics, environmental baselines, and preventive underwater archaeology. WACA's 9 June 2026 article reports an 82% overall baseline at 31 March, with a 390-metre eastern work front nearly complete and a 900-metre western work front at 82%. The later 25 June project paper reports 85% for protection works and 75% including landscaping, cites rough-sea stoppages, an early seven-month rock-supply delay, the school-wall collapse, mosque-slope instability, and UNESCO validation, and seeks EUR 3.5 million plus a 30 June 2027 close. The figures use different dates and measurement boundaries; none proves acceptance.
Coastal delivery and performance implications
The reported 85% still leaves eastern and western dike and breakwater work, the school wall and mosque slope, heritage validation, promenade and landscaping, environmental and archaeological controls, and handover. Because the later percentage uses a narrower boundary, the 82% and 85% records must remain attached to their own scope definitions.
Evidence conclusion
Geometry, acceptance and performance evidence
The reported 85% anchors the construction baseline, but the unfinished portion includes more than rock placement. The proposed credit must become effective, remaining quantities and dates need to be fixed in the contracts, and the six breakwaters, dikes, school-side extension and mosque slope have to be completed as one protection system. UNESCO and archaeological requirements, the promenade and access works, as-built inspection and a funded maintenance plan remain part of handover. A financing paper or percentage update does not settle those items.
Outstanding evidence
- Approval and effectiveness of the proposed EUR 3.5 million credit
- NGE contract amendments, remaining quantities, cost allocation, and 30 June 2027 date
- Dakar Pier 8 rock stocks, sea-state workability, and two-front sequencing
- Eastern and western dike segments, six breakwaters, and accepted geometry
- Mariama Bâ wall, mosque slope, UNESCO validation, promenade, and landscaping
- Environmental, archaeological, grievance, safety, and livelihood close-out
- As-built records, owner acceptance, maintenance funding, and post-storm performance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- Senegal WACA ResIP additional-financing project paper World Bank, 25 June 2026; disclosed 7 July 2026
- Gorée Protected: Coastal Protection Works Near Completion WACA Program / World Bank, 9 June 2026; progress measured 31 March 2026
- Senegal WACA ResIP national implementation-support mission aide-memoire World Bank, 7-11 July 2025
- West Africa Coastal Areas Resilience Investment Project restructuring paper World Bank, 21 May 2025
- Gorée coastal-protection environmental and social impact assessment WACA ResIP Senegal / World Bank, December 2022
- West Africa Coastal Areas Resilience Investment Project World Bank, Approved 9 April 2018