Location
Poland / Europe
Project record
Port Gdynia / D. Adamski; exact first-caisson tow in July 2026
The Maritime Office in Gdynia and Port of Gdynia Authority are delivering almost 2.5 kilometres of protective breakwaters for the future Outer Port through a PLN 438.70 million net design-build contract. Budimex leads the delivery consortium with a 50% share, while Roverpol and Rover Maritime each hold 25%. A May 2026 building permit enabled the transition to principal in-water works, and the first of 49 reinforced-concrete caissons was launched and towed toward its placement position in July. The legal consortium is confirmed; published project records do not name a downstream subcontractor.
Poland / Europe
Caisson breakwaters and port access infrastructure
The May 2026 building permit has moved the design-build contract into principal in-water works; the first reinforced-concrete caisson was launched and towed toward its placement position in July 2026, with the remaining 48 caissons and breakwater systems still to be delivered / Confirmed
2 August 2026
Coverage
Caisson breakwaters and port access infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe first of 49 planned caissons was launched and towed toward its placement position, marking the shift from design and permitting to principal hydrotechnical construction on the water.
SourceThe Maritime Office reports approval of the building permit in May 2026, closing the principal design-and-permit gate before the caisson installation programme.
SourceContract MZ/67/KJ/MG/2024 fixed the Budimex-Rover consortium, PLN 438,699,534.11 net value and the contractual route toward a Q2 2028 target.
SourceThe procurement notice separated breakwaters, existing-structure strengthening, seabed preparation, dredging, foundations, backfill, wave attenuation and navigation lighting from the future terminal works.
SourceEvidence gap